Industry Survey Capital Asset Identification Financial Tracking Design-Build_USCG final.docx

DOCX document 30 KB Posted

Attached to
Feedback on CLIN Structure for Design-Build Construction Projects with Capital Asset Identification and Financial Tracking
Solicitation number
70ZS0927SCLINDBAT
Issued by
Not on record

About this file

This is an Industry Survey and Request for Information issued by the U.S. Coast Guard regarding the potential structure of Contract Line Item Numbers (CLINs), Schedules of Values, and capital asset tracking mechanisms for future design-build construction projects. The survey is market research only and does not constitute a solicitation, commitment to contract, or request for pricing or proposals. Responses must be submitted to Melissa Ardis at melissa.m.ardis@uscg.mil no later than December 16, 2026, at 5:00 PM EST. The Coast Guard seeks industry feedback on practical approaches for structuring large-dollar construction projects (potentially exceeding 25 CLINs) where the final design and asset configuration may not be fully defined at contract award, with particular focus on tracking work, cost, progress, and payments by facility, system, real property asset, or Real Property Unique Identifier (RPUID).

The survey requests detailed input across multiple categories: company background and relevant experience; experience managing large CLIN and Schedule of Values structures; preferred structural approaches for design-build projects; Schedule of Values alignment with capital asset tracking; invoicing and reporting capabilities at the asset level; impacts of contract modifications during design development; cost and competition implications; and best practices or lessons learned. Specific topics include whether industry can accommodate asset-level invoicing and progress reporting, what information the Government should provide to enable practical tracking, anticipated system and accounting impacts, optimal frequencies and methods for updating asset-related tracking elements as design evolves, and estimated cost increases associated with such requirements. The survey also solicits recommendations on avoiding burdensome structures and identifying approaches that would reduce contractor costs while maintaining accurate financial and asset tracking throughout project execution and closeout.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Industry Survey Feedback on Contract Line Item Number (CLIN) Structure for Design-Build Construction Projects with Capital Asset Identification and Financial Tracking Agency: U.S. Coast Guard Notice Type: Request for Information / Sources Sought / Market Research Subject: Industry Feedback on Potential CLIN and Schedule of Values Structure for Design-Build Projects with Capital Asset Tracking

1. Purpose This request is for market research and planning purposes only. It is not a Request for Proposal, solicitation, or commitment to issue a future contract. The Coast Guard is not requesting pricing, proposals, or offers. We are asking for industry’s practical input on what would be clear, manageable, and efficient from a contractor’s perspective.

The Coast Guard recognizes that high-dollar construction projects may require more than 25 CLINs. Depending on project size and complexity, a project could involve dozens or even hundreds of CLINs, sub-CLINs, or Schedule of Values entries, especially where work must be tracked by building, system, phase, funding source, or real property asset.

2. Background The Coast Guard is considering whether future design-build construction projects could be structured to better support capital asset identification and financial tracking during project execution.

For design-build projects, the final design may evolve after award. As a result, the exact number, type, or configuration of capital assets may not be fully known at the time of award. The Coast Guard is interested in industry’s views on practical ways to structure contract line items, Schedules of Values, and reporting requirements when capital assets may need to be tracked as the design develops.

For purposes of this survey, “capital asset tracking” may include tracking work, cost, progress, or payment information by facility, system, real property asset, or Real Property Unique Identifier, also known as RPUID.

A notional example is included as Exhibit A to show one possible approach. The example is illustrative only and does not represent an actual project, requirement, solicitation, or preferred contract structure.

3. Industry Feedback Survey Please provide practical recommendations, concerns, lessons learned, or alternative approaches based on your experience.

A. Company Information

1. Company name:

2. Unique Entity Identifier (UEI):

3. Point of contact:

Name:

Title:

Email:

Phone:

4. Business size:

Select one.

a. Small Business

b. Other than Small Business

c. Not applicable / prefer not to answer

d. Other: [Open response]

5. Socioeconomic status, if applicable:

Select all that apply.

a. Small Disadvantaged Business/8(a) (SDB)

b. HUBZone (HUBZone)

c. Service-Disabled Veteran-Owned Small Business (SDVOSB)

d. Woman-Owned Small Business (WOSB)

e. Economically Disadvantaged Woman-Owned Small Business (EDWOSB)

f. Veteran-Owned Small Business (VOSB)

g. Other: [Open response]

h. Not applicable / prefer not to answer

6. Relevant experience:

Select all that apply.

a. Design-build construction

b. Design-bid-build construction

c. Federal construction

d. Large-dollar construction projects ($10M+)

e. Projects with 25-99 CLINs or sub-CLINs

f. Projects with more than 100 CLINs, sub-CLINs, or Schedule of Values entries

g. Schedule of Values development

h. Asset-level cost tracking

i. RPUID or real property asset tracking

j. Invoicing tied to detailed work breakdown structures

k. Other: [Open response]

B. Experience with Large CLIN or Schedule of Values Structures

7. What is the largest number of CLINs, sub-CLINs, exhibit line items, or Schedule of Values entries your company has managed on a single construction project?

a. 1 to 25

b. 26 to 50

c. 51 to 100

d. 101 to 250

e. More than 250

f. Not sure

g. Other / explanation: [Open response]

8. Please briefly explain what makes a large CLIN or Schedule of Values structure easier or harder to manage.

[Open response]

C. Preferred Structure for Design-Build Projects

9. For design-build construction projects where the final asset configuration may not be known at award, which structure would be most effective?

Select most preferred option.

a. Fewer CLINs with a detailed Schedule of Values

b. Separate CLINs by building or facility

c. Separate CLINs by real property asset or RPUID

d. CLINs by major work category, with sub-CLINs by asset

e. CLINs by phase, such as design, construction, commissioning, and closeout

f. High-level contract structure at award, contract modification at completion to create CLINs for each RPUID

g. Exhibit line items or informational line items to map costs to assets

h. A separate asset-tracking exhibit updated during performance

i. Other: [Open response]

10. At award, what level of detail is reasonable when the design is not yet complete?

a. High-level CLINs only

b. CLINs by major facility or system

c. CLINs with estimated sub-CLINs

d. Provisional or placeholder CLINs

e. Detailed Schedule of Values after design development

f. Other: [Open response]

11. Would tying CLINs, sub-CLINs, or Schedule of Values entries to RPUIDs or other asset identifiers create challenges?

a. No significant challenges

b. Minor administrative challenges

c. Moderate challenges

d. Significant challenges

e. Depends on the project

f. Not sure

12. Please explain any concerns or recommendations related to asset-level or RPUID-level tracking.

[Open response]

D. Schedule of Values, Invoicing, and Reporting

13. What is the most practical way to align a Schedule of Values with capital asset tracking?

Select all that apply.

a. By building or facility

b. By RPUID or real property asset

c. By construction phase

d. By trade or discipline

e. By specification section

f. By work breakdown structure

g. By funding source

h. By major system, such as HVAC, electrical, utilities, or sitework

i. Other: [Open response]

14. Would your company be able to invoice or report progress at the asset level if required?

a. Yes

b. Yes, with limitations

c. No

d. Not sure

15. What information would the Government need to provide to make asset-level tracking practical?

Select all that apply.

a. Initial asset list

b. RPUID list

c. Asset descriptions

d. Site plans or drawings

e. Work breakdown structure

f. Required Schedule of Values template

g. Required invoice template

h. Examples of acceptable reporting

i. Instructions for assets not known at award

j. Process for adding, revising, or removing assets

k. Other: [Open response]

16. Would your company need to change internal systems or processes to support this type of tracking?

a. No

b. Yes, minor changes

c. Yes, moderate changes

d. Yes, significant changes

e. Not sure

17. Please describe any expected system, accounting, invoicing, subcontractor, or project controls impacts.

[Open response]

E. Contract Changes and Design Development

18. As the design develops, what is the best way to add, remove, or revise asset-related tracking elements?

Select all that apply.

a. Formal contract modifications

b. Updated Schedule of Values approved by the Contracting Officer

c. Updated exhibit or attachment

d. Contractor-maintained asset-tracking matrix

e. Government-provided template updated at defined milestones

f. Updates at design milestones, such as 35%, 65%, 95%, and final design

g. Other: [Open response]

19. Would frequent contract modifications to update CLINs or asset information create burden or delay?

a. No significant burden

b. Minor burden

c. Moderate burden

d. Significant burden

e. Depends on frequency and complexity

f. Not sure

20. What approach would reduce the need for frequent modifications while still allowing accurate asset tracking?

[Open response]

F. Cost, Schedule, and Competition Impacts

21. Would this type of CLIN, Schedule of Values, or asset-tracking requirement likely increase contractor cost?

a. No

b. Yes, slightly

c. Yes, moderately

d. Yes, significantly

e. Depends on structure

f. Not sure

22. Where would additional costs most likely occur?

Select all that apply.

a. Estimating

b. Proposal preparation

c. Accounting system setup

d. Project controls

e. Subcontractor pricing and coordination

f. Schedule of Values development

g. Invoicing and payment tracking

h. Contract administration

i. Contract modifications

j. Closeout and turnover documentation

k. Other: [Open response]

23. Would this type of requirement affect your company’s decision to compete for a future project?

a. No

b. Yes, but we would likely still compete

c. Yes, and it could discourage us from competing

d. Depends on the final solicitation requirements

e. Not sure

24. What would help reduce cost, schedule, or competition concerns?

[Open response]

G. Additional Recommendations, Considerations

25. Would a notional asset list or example exhibit, similar to Exhibit A, be helpful in a future solicitation?

a. Yes

b. No

c. Maybe

d. Not sure

26. What should the Government avoid when structuring CLINs, sub-CLINs, or asset-tracking requirements for design-build projects?

[Open response]

27. What best practices, examples, or lessons learned would you recommend?

[Open response]

28. Any additional comments or recommendations?

[Open response]