Attachment 3 - Questions and Answers.pdf
PDF 380 KB Posted
- Solicitation number
- 70Z0G822QBNCR0005
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment 5 - Drawing.jpg | JPG image | |
| Attachment 6 - Drawing.jpg | JPG image | |
| Attachment 4 - Proposed Water Lines.pdf | ||
| Attachment 2 - Pricing Spreadsheet.xlsx | XLSX spreadsheet | |
| RFQ 70Z0G822QBNCR0005 Schedule.pdf | ||
| Attachment 1 - Statement of Work.pdf | ||
| SF-1449 70Z0G822QBNCR0005.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFQ: 70Z0G822QBNCR0005
SOLICITATION QUESTIONS & ANSWERS
Reference
Question
Answer
1 N/A What size is the PVC piping The PVC is 2 inches in diameter
2 N/A How deep is the pipe buried below ground The pipe should be roughly 3 feet down.
3 N/A Could we run the new water line at the location highlighted in the sketch? This wold avoid disturbing the concrete culvert as well as the fiberglass fuel lines and other utilities. The existing line going to the boat house would become abandoned.
Yes, this is an option. As long as the valves are still installed appropriately and the old line entering into the boat house is capped off it should work fine.