This is an Abstract of Offers for a construction contract for dredging at the U.S. Coast Guard Station Shinnecock in Hampton Bays, NY. The solicitation (No. 70Z0G125BSLIS00152) was issued on 6/18/2025, with offers to be opened on 7/22/2025 by the USCG CEU Providence office. The project involves dredging 5,800 cubic yards, including pre and post-dredge surveys and associated mobilization/demobilization costs.

Six contractors submitted bids, with total bid prices ranging from $1,608,203 to $2,252,000. The lowest bidder was Chesterfield Associates, Inc. at $1,608,203, while the highest was Seacoast Construction, Inc. at $2,252,000. All bidders provided a 20% bid security and acknowledged two amendments to the solicitation. The contract requires furnishing labor, materials, equipment, and supervision for maintenance dredging of the boat basin and entrance channel, in accordance with detailed specifications and drawings.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ABSTRACT OF OFFERS - CONSTRUCTION

1. SOLICITATION NUMBER

70Z0G125BSLIS00152

2. DATE ISSUED

6/18/2025

DATE OPENED

7/22/2025

PAGE OF PAGES

1 2

4. ISSUING OFFICE

USCG CEU PROVIDENCE

475 KILVERT STREET SUITE 100

WARWICK, RI 02886

I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation.

NAME AND TITLE OF CERTIFYING OFFICIAL (TYPE)

Simon W. Leung, USCG Contracting Officer

SIGNATURE DATE SIGNED

5. PROJECT TITLE

DREDGE – U.S. COAST GUARD, STATION

SHINNECOCK

HAMPTON BAYS, NY, PSN 24008351

8. GOVERNMENT ESTIMATE

(Check A, B or C and complete D, E, and F)

9. OFFERS

NO. 1 NO. 2

A. HIRED LABOR

A. OFFEROR

Terry Contracting & Materials, Inc.

A. OFFEROR

Land Mediation, Inc.

B. REASONABLE

CONTRACT

(Without Profit)

B. BID SECURITY (Type and amount)

20%

B. BID SECURITY (Type and amount)

20%

6. NUMBER OF AMENDMENTS ISSUED

00009 X

C. REASONABLE

CONTRACT

(Including profit)

C. AMENDMENTS ACKNOWLEDGED

0001, 0002

C. AMENDMENTS ACKNOWLEDGED

0001, 0002 7A.

ITEM

NO.

7B. DESCRIPTION OF OFFERED ITEM

7C. EST.

QUANTITY

D.

UNIT

E. UNIT

PRICE

F. ESTIMATED

AMOUNT

D. UNIT

PRICE

E. ESTIMATED

AMOUNT

D. UNIT

PRICE

E. ESTIMATED

AMOUNT

0001A 5,800 Cubic Yards X __________ 1 CY $166.00 $962,800.00 $203.00 $1,177,400.00 $175.00 $1,015,000.00

0001B Pre & Post Dredge Surveys 1 LS $12,000.00 $22,260.00 $30,000.00

0001C Other Costs (Mob/Demob.

Progress Schedule, Constr Submittals and Env. Controls

1 LS $605,200.00 $536,291.00 $935,000.00

Total Bid Price 1 LS $1,580,000.00 $1,735,951.00 $1,980,000.00

07/23/2025

ABSTRACT OF OFFERS – CONSTRUCTION

CONTINUATION SHEET

1. SOLICITATION NUMBER

70Z0G125BSLIS00152

PAGE OF PAGES

2 2

INSTRUCTIONS – Attach this form to OF-1419, Abstract of Offers – Construction, when more than 2 offers are received on a construction project. Each Continuation Sheet will accommodate 14 contract items to conform to the number of items which can be entered on the OF-1419. Use additional OF-1419’s for contract items in excess of 14 and attach additional Continuation Sheets (OF-1419A) as needed.

5. PROJECT TITLE

DREDGE – U.S. COAST GUARD,

STATION SHINNECOCK

HAMPTON BAYS, NY, PSN 24008351

4. OFFERS (Continued)

NO. 3 NO. 4 NO. 5 NO. 6

A. OFFEROR

Seacoast Construction, Inc.

A. OFFEROR

Galvin Bros. & Madhue Contracting JV

A. OFFEROR

Chesterfield Associates, Inc.

A. OFFEROR

Spectraserv, Inc.

B. BID SECURITY (Type and amount)

20% B. BID SECURITY (Type and amount)

20% B. BID SECURITY (Ty20%pe and amount)

20% B. BID SECURITY (Type and amount)

20%

3. CONTRACT ITEMS

C. AMENDMENTS ACKNOWLEDGED

0001, 0002

C. AMENDMENTS ACKNOWLEDGED

0001, 0002

C. AMENDMENTS ACKNOWLEDGED

0001, 0002

C. AMENDMENTS ACKNOWLEDGED

0001, 0002 A.

ITEM

NO.

C.

UNIT

D. UNIT

PRICE

E. ESTIMATED

AMOUNT

D. UNIT

PRICE

E. ESTIMATED

AMOUNT

D. UNIT

PRICE

E. ESTIMATED

AMOUNT

D. UNIT

PRICE

E. ESTIMATED

AMOUNT

0001A 5,800 Cubic Yards X

1 CY $1,102,000.00 $270.00 $1,566,000.00 $238.35 $1,382,430.00 $290.43 $1,684,494.00

0001B Pre & Post Dredge Surveys

1 LS $50,000.00 $36,800.00 $11,290.00 $18,000.00

0001C

Other Costs (Mob/Demob.

Progress Schedule, Constr Submittals and Env. Controls

1 LS $1,100,000.00 $381,400.00 $214,510.00 $252,671.86

Total Bid Price 1 LS $2,252,000.00 $1,984,200.00 $1,608,203.00 $1,955,165.86