Spec_Section_for_Amendment_0002_09_97_13_Rev_01.pdf

PDF 80 KB Posted

Attached to
USCG STATION PT ALLERTON REPLACE FLOATING DOCK Federal contract opportunity
Solicitation number
70Z0G118QPRV25000
Issued by
Department of Homeland Security US Coast Guard

About this file

Rev Spec section for 70Z0G118QPRV25000

View the file

Other files for this federal contract opportunity

Other files attached to USCG STATION PT ALLERTON REPLACE FLOATING DOCK, newest first.
File Type Posted
Wage_Rate_MA13_Rev_81718.docx DOCX document
SF30_Amendment_00002.pdf PDF
SF30_Amendment_00001.pdf PDF
RFQ_PRV250.pdf PDF
P3534557SPEC.pdf PDF
P3534557DWGS.pdf PDF
Wage_Rate_MA13.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Replace Inboard Floating Docks 3534557

Revised 9/6/2018

Section 09 97 13 Page 1

SECTION 09 97 13

COATING OF STEEL WATERFRONT STRUCTURES

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM C920 (2014a) Standard Specification for

Elastomeric Joint Sealants

ASTM D3276 (2015; E 2016) Standard Guide for Painting

Inspectors (Metal Substrates)

ASTM D3335 (1985a; R 2014) Low Concentrations of Lead, Cadmium, and Cobalt in Paint by Atomic

Absorption Spectroscopy

ASTM D3718 (1985a; R 2015) Low Concentrations of

Chromium in Paint by Atomic Absorption

Spectroscopy

ASTM D3925 (2002; R 2015) Sampling Liquid Paints and

Related Pigmented Coatings

ASTM D4285 (1983; R 2012) Indicating Oil or Water in

Compressed Air

ASTM D7091 (2013) Standard Practice for Nondestructive

Measurement of Dry Film Thickness of

Nonmagnetic Coatings Applied to Ferrous

Metals and Nonmagnetic, Nondestructive

Coatings Applied to Non-Ferrous Metals

INTERNATIONAL ORGANIZATION FOR STANDARDIZATION (ISO)

ISO 9001 (2008; Corr 1 2009) Quality Management

Systems- Requirements

NACE INTERNATIONAL (NACE)

NACE WJ-1 (2012) Waterjet Cleaning of Metals—Clean to

Bare Substrate

SOCIETY FOR PROTECTIVE COATINGS (SSPC)

SSPC 7/NACE No.4 (2007; E 2004) Brush-Off Blast Cleaning

SSPC AB 1 (2015; E 2017) Mineral and Slag Abrasives

Section 09 97 13 Page 2

SSPC AB 2 (2015; E 2016) Cleanliness of Recycled

Ferrous Metallic Abrasive

SSPC AB 3 (2003; E 2004) Ferrous Metallic Abrasive

SSPC Guide 10 (1994; E 2001) Guide to Specifying Coatings

Conforming to Volatile Organic Compound (VOC)

Content Requirements

SSPC Guide 12 (1998; E 2004) Guide for Illumination of

Industrial Painting Projects

SSPC Guide 15 (2013) Field Methods for Extraction and

Analysis of Soluble Salts on Steel and Other

Nonporous Substrates

SSPC Guide 6 (2015) Guide for Containing Surface

Preparation Debris Generated During Paint

Removal Operations

SSPC PA 1 (2016) Shop, Field, and Maintenance Coating of Metals

SSPC PA 17 (2012; E 2012) Procedure for Determining

Conformance to Steel Profile/Surface

Roughness/Peak Count Requirements

SSPC PA 2 (2015; E 2017) Procedure for Determining

Conformance to Dry Coating Thickness

Requirements

SSPC QP 1 (2012; E 2012) Standard Procedure for

Evaluating Painting Contractors (Field

Application to Complex Industrial Structures)

SSPC QP 2 (2009; E 2013) Standard for Evaluating

Painting Contractors (Removal of Hazardous

Coatings from Industrial/Marine Structures)

SSPC QP 3 (2010) Standard Procedure for Evaluating

Qualifications of Shop Painting Applicators

SSPC QP 5 (2012) Standard Procedure for Evaluating the

Qualifications of Coating and Lining

Inspection Companies

SSPC QS 1 (2015) Standard Procedure for Evaluating a

Contractor's Advanced Quality Management

System

SSPC SP 1 (2015) Solvent Cleaning

SSPC SP 10/NACE No. 2 (2007) Near-White Blast Cleaning

SSPC SP 6/NACE No.3 (2007) Commercial Blast Cleaning

Section 09 97 13 Page 3

SSPC SP COM (2016; E 2017) Surface Preparation Commentary for Steel and Concrete Substrates

SSPC VIS 1 (2002; E 2004) Guide and Reference

Photographs for Steel Surfaces Prepared by

Dry Abrasive Blast Cleaning

U.S. GENERAL SERVICES ADMINISTRATION (GSA)

FED-STD-595 (Rev C; Notice 1) Colors Used in Government

Procurement

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

29 CFR 1910.1000 Air Contaminants

29 CFR 1910.134 Respiratory Protection

29 CFR 1926.59 Hazard Communication

1.2 DEFINITIONS

Definitions are provided throughout this Section, generally in the paragraph where used, and denoted by capital letters.

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-05 Design Data

Containment System

SD-06 Test Reports

Coatings Qualification Test Reports

Non-metallic Abrasive Qualification Test Reports; G

Metallic Abrasive Qualification Test Reports

Coating Sample Test Reports

Waste Materials Analysis Test Report

Abrasive Sample Test Reports

Inspection Report Forms

Daily Inspection Reports

Recycled Metallic Abrasive Field Test Reports (Daily and Weekly)

SD-07 Certificates

Section 09 97 13 Page 4

Contract Errors, Omissions, and Other Discrepancies

Corrective Action Procedures

Implement Corrective Action

Coating Work Plan

Coating Materials

Non-metallic Abrasive

Metallic Abrasive

Qualifications of Certified Industrial Hygienist (CIH)

Qualifications Of Individuals Performing Abrasive Blasting

Qualifications of Certified Protective Coatings Specialist (PCS)

Qualifications of Individuals Applying Coatings

Qualifications of Individuals Operating Plural Component Equipment

Qualifications of Coating Inspection Company

Qualifications of QC Specialist Coating Inspector

Qualifications of Testing Laboratory for Coatings

Qualifications of Testing Laboratory for Abrasive Media

Qualifications of Coating Contractors

Joint Sealant Materials

Pre-Application Meeting

SD-08 Manufacturer's Instructions

Joint Sealant Instructions

Coating System Instructions; G

SD-11 Closeout Submittals

Disposal of Used Abrasive; G

Inspection Logbook; G

1.4 QUALITY ASSURANCE

1.4.1 Corrective Action (CA)

CA must be included in the Quality Control Plan.

Section 09 97 13 Page 5

1.4.1.1 Corrective Action Procedures

Develop procedures for determining the root cause of each non-compliance, developing a plan to eliminate the root cause so that the non-compliance does not recur, and following up to ensure that the root cause was eliminated. Develop Corrective Action Request (CAR) forms for initiating

CA, and for tracking and documenting each step.

1.4.1.2 Implement Corrective Action

The Contractor must take action to identify and eliminate the root cause of each non-compliance so as to prevent recurrence. These procedures must apply to non-compliance in the work, and to non-compliance in the QC System.

Corrective actions must be appropriate to the effects of the non-compliance encountered. Each CAR must be tracked in a Log to completion and acceptance by the Contracting Officer, and retained in project records. A CAR may be initiated by either the Contractor or the Contracting Officer. The

Contracting Officer must approve each CAR at the root cause identification stage, the plan for elimination stage, and the close out stage after verification that the root cause has been eliminated.

1.4.2 Coating Work Plan

a. This work plan must be considered as part of the Quality Control Plan.

b. Provide procedures for reviewing contract documents immediately after award to identify errors, omissions, and discrepancies so that any such issues can be resolved prior to project planning and development of detailed procedures.

c. Provide procedures for verification of key processes during Initial

Phase to ensure that contract requirements can be met. Key processes must include surface preparation, coating application and curing, inspection, and documentation, and any other process that might adversely impact orderly progression of work.

d. Provide procedures for all phases of coating operations, including planned work, rework, repair, inspection, and documentation. Address mobilization and setup, surface preparation, coating application, coating initial cure, tracking and correction of non-compliant work, and demobilization. Coordinate work processes with health and safety plans and confined space entry plans. For each process, provide procedures that include appropriate work instructions, material and equipment requirements, personnel qualifications, controls, and process verification procedures. Provide procedures for inspecting work to verify and document compliance with contract requirements, including inspection forms and checklists, and acceptance and rejection criteria.

e. Provide procedures for determining the existing surface profile under paint, and procedures for ensuring that the profile is not increased beyond the maximum profile specified herein.

f. Provide procedures for correcting non-compliant work. Detailed procedures are required in advance to avoid delays in meeting overcoat windows as well as to avoid delays in production. Provide procedures for repairing defects in the coating film, such as runs, drips, sags, holidays, overspray, as well as how to correct coating thickness non-

Section 09 97 13 Page 6 compliance, any other areas of repair or rework that might be adversely affected by delays in preparing and approving new procedures.

g. If a procedure is based on a proposed or approved request for deviation, the deviation must be referenced. Changes to procedures must be noted by submittal number and date approved, clearly delineating old requirements and new requirements, so that the records provide a continuous log of requirements and procedures.

1.4.3 Design Data

1.4.3.1 Containment System

Submit complete design drawings and calculations for the scaffolding and containment system, including an analysis of the loads which will be added to the structure by the containment system and waste materials. A registered engineer must approve calculations and scaffold system design.

1.4.4 Test Reports

1.4.4.1 Metallic Abrasive Qualification Test Reports

Submit results for abrasive as required in paragraph 4 REQUIREMENTS of SSPC

AB 3. Submit test results from independent laboratory of representative samples of each abrasive to be used on the jobsite. Samples must have been tested within the last three years. Note that this testing is for the purpose of prequalifying the abrasive.

1.4.4.2 Recycled Metallic Abrasive Field Test Reports (Daily and Weekly)

Submit test results from independent laboratory of daily and weekly Quality

Control testing required by SSPC AB 2, as modified in paragraph ABRASIVE.

1.4.4.3 Non-metallic Abrasive Qualification Test Reports

Submit results for abrasive as required in paragraph 4 REQUIREMENTS of SSPC

AB 1. Submit test results from independent laboratory of representative samples of each abrasive to be used on the jobsite. Samples must have been tested within the last three years. Note that this testing is for the purpose of prequalifying the abrasive.

1.4.5 Qualifications

1.4.5.1 Qualifications of Certified Protective Coatings Specialist (PCS)

Submit name, address, telephone number, FAX number, and e-mail address of the independent third party PCS. Submit documentation that specialist is certified by SSPC: The Society for Protective Coatings (SSPC) as a PCS, including certification number and date of certification/recertification.

If the PCS is employed by the same coating inspection company to which the coating inspector is employed, this does not violate the independent third-party requirements. The PCS must remain certified during the entire project, and the Contracting Officer must be notified of any change in certification status within 10 days of the change. The PCS must not be the designated coating inspector.

Section 09 97 13 Page 7

1.4.5.2 Qualifications of Coating Inspection Company

Submit documentation that the coating inspection company performing all coating inspection functions is certified by SSPC to the requirements of

SSPC QP 5 prior to contract award. The coating inspection company submitted and approved must remain and not changed through completion of the contract.

The coating inspection company must remain so certified for the duration of the project. If a coating inspection company's certification expires, the firm will not be allowed to perform any inspection functions, and all surface preparation and coating application work must stop, until the certification is reissued. Requests for extension of time for any delay to the completion of the project due to an inactive certification will not be considered and liquidated damages will apply. Notify the Contracting

Officer of any change in coating inspection company certification status.

Notify the Contracting Officer of all scheduled and unannounced on site inspections from SSPC and furnish a copy of all inspection reports.

1.4.5.3 Qualifications of QC Specialist Coating Inspector

Submit documentation that each coating inspector is employed, and qualified to SSPC QP 5, Level III, by the selected coating inspection company. Each inspector must remain employed by the coating inspection company while performing any coating inspection functions. In addition to the handwritten records, the inspector must employ the electronic reporting program TruQC or equivalent. The Administrator must be the designated Government

Representative for the project.

1.4.5.4 Qualifications Of Individuals Performing Abrasive Blasting

Submit name, address, and telephone number of each person that will be performing abrasive blasting. Submit documentation that each blaster is qualified by SSPC to the SSPC C 7 Abrasive Blaster or the SSPC CAS Coating

Application Specialist Level 2 Certification Program (Interim Status. Each blaster must remain certified during the entire period of abrasive blasting, and the Contracting Officer must be notified of any change in qualification status.

1.4.5.5 Qualifications of Individuals Applying Coatings

Submit name, address, telephone number, of each person that will be operating plural component equipment. Submit documentation that each operator is qualified by SSPC to the SSPC C 12 Spray Application

Certification meeting the NAVSEA 009-32 requirements or the SSPC CAS Coating

Application Specialist Level 2 Certification Program (Interim Status). Each operator must remain certified during the entire period of coating application and the Contracting Officer must be notified of any change in qualification status.

1.4.5.6 Qualifications of Testing Laboratory for Abrasive Media

Submit name, address, telephone number, FAX number, and e-mail address of the independent third party laboratory selected to perform testing of abrasive for compliance with specification requirements. Submit documentation that laboratory has experience in testing samples of abrasive for conformance with specifications, and that persons performing analyses are qualified.

Section 09 97 13 Page 8

1.4.5.7 Qualifications of Coating Contractors

All Contractors and Subcontractors that perform surface preparation or coating application must be certified to SSPC QP 1 and SSPC QS 1 for field application prior to contract award and must remain certified while accomplishing any surface preparation or coating application. The painting

Contractors, painting Subcontractors or Shop must remain so certified for the duration of the project. If a Contractor's, Subcontractor's or Shop's certification expires, the firm will not be allowed to perform any work until the certification is reissued. Requests for extension of time for any delay to the completion of the project due to an inactive certification will not be considered and liquidated damages will apply. Notify the Contracting

Officer of any change in Contractor or Shop certification status. Notify the

Contracting Officer of all scheduled and unannounced on site audits from

SSPC and furnish a copy of all audit reports.

1.4.5.8 Joint Sealant Materials

Provide manufacturer's certification of conformance to contract requirements.

1.4.5.9 Coating Materials

Provide manufacturer's certification of conformance to contract requirements.

1.4.5.10 Non-metallic Abrasive

Provide manufacturer's certification that the materials are currently approved by the Naval Sea Systems Command and listed on the Qualified

Products Lists (QPL) for the specified materials.

1.4.5.11 Metallic Abrasive

Provide manufacturer's certification of conformance to contract requirements and provide copies of test results.

1.4.6 Protective Coating Specialist (PCS)

The PCS must be considered a QC Specialist and must report to the QC

Manager. The PCS must approve all submittals prior to submission to the QC

Manager for approval or submission to the government for approval.

1.4.7 Pre-Application Meeting

After approval of submittals but prior to the initiation of coating work, Contractor representatives, including at a minimum, project superintendent and QC manager, paint foreman, coating inspector, and PCS must have a pre-application coating preparatory meeting. This meeting must be in addition to the pre-construction conference. Specific items addressed must include:

corrective action requirements and procedures, coating work plan, safety plan, coordination with other Sections, inspection standards, inspection requirements and tools, test procedures, environmental control system, and test logs. Notify Contracting Officer at least ten days prior to meeting.

1.5 PRODUCT DATA

Section 09 97 13 Page 9

1.5.1 Joint Sealant Instructions

Submit manufacturer's printed instructions including detailed application procedures, minimum and maximum application temperatures, and curing procedures. Include materials safety data sheets (MSDS) for materials to be used at the job site in accordance with 29 CFR 1926.59.

1.5.2 Coating System Instructions

Submit manufacturer's printed instructions including detailed mixing and application procedures, number and types of coats required, minimum and maximum application temperatures, and curing procedures. Include materials safety data sheets (MSDS) for materials to be used at the job site in accordance with 29 CFR 1926.59.

1.6 DELIVERY AND STORAGE

Ship, store, and handle materials in accordance with SSPC PA 1, and as modified in this Section. Maintain temperature in storage spaces between 40 and 100 degrees F, and air temperature more than 5 degrees F above the dew-point at all times. Inspect materials for damage prior to use and return non-compliant materials to manufacturer. Remove materials with expired shelf life from government property immediately and notify the Contracting

Officer.

If materials are approaching shelf life expiration and an extension is desired, samples may be sent to the manufacturer, along with complete records of storage conditions, with a request for shelf life extension. If the manufacturer finds the samples and storage data suitable for shelf life extension, the manufacturer may issue an extension, referencing the product evaluation and the review of storage records. Products may not be extended longer than allowed in the product specification.

1.7 COATING HAZARDS

Ensure that employees are trained in all aspects of the safety plan.

Specified coatings may have potential health hazards if ingested or improperly handled. The coating manufacturer's written safety precautions must be followed throughout mixing, application, and curing of the coatings.

During all cleaning, cleanup, surface preparation, and paint application phases, ensure that employees are protected from toxic and hazardous chemical agents which exceed concentrations in 29 CFR 1910.1000. Comply with respiratory protection requirements in 29 CFR 1910.134. The CIH must approve work procedures and personal protective equipment.

1.8 JOB SITE REFERENCES

Make available to the Contracting Officer at least one copy each of ASTM

D3276, ASTM D3925, ASTM D4285, ASTM D7091, FED-STD-595, ISO 9001, SSPC AB

2, SSPC AB 3, SSPC Guide 6, SSPC Guide 10, SSPC Guide 12, SSPC Guide 15, SSPC PA 1, SSPC PA 2, SSPC PA 17, SSPC QP 1, SSPC QP 2, SSPC QP 3, SSPC QP

5, SSPC QS 1, SSPC SP COM, SSPC SP 1, SSPC SP 6/NACE No.3, SSPC 7/NACE No.4, SSPC SP 10/NACE No. 2, NACE WJ-1, SSPC VIS 1, and an SSPC Certified

Contractor Evaluation Form at the job site.

PART 2 PRODUCTS

Section 09 97 13 Page 10

2.1 JOINT SEALANT

ASTM C920, Type M, Grade NS, Class 25, Use NT, I, M, G, A, O. Must be manufactured or supported by the coating system manufacturer.

2.2 COATING SYSTEM

2.2.1 Urethane Coating System

Coating system shall be a 3 part system as follows:

1. Primer coat -zinc rich, moisture cure Urethane

2. Intermediate coat- Coal Tar moisture cure Urethane or MIO moisture cure

Urethane

3. Top coat - Coal Tar moisture cure Urethane

4. Color shall be black.

The following are Pre-approved coating systems:

1. Wasser High Tech Coatings Inc.

Primer coat - MC Miozinc 100 @ 3.0 - 5.0 mils dft

Intermediate Coat - MC Tar @ 5.0 - 7.0 mils dft

Top coat - MC Tar @ 5.0 - 7.0 mils dft

Total system dft :13.0 - 19.0 mils

Average dft shall be 16 mils

2. Sherwin-Williams Company

Primer coat - Corothane I Mio-Zinc Primer @ 3.0 - 4.0 mils dft

Intermediate Coat - Corothane I Coal Tar @ 5.0 - 7.0 mils dft

Top coat - Corothane I Coal Tar @ 5.0 - 7.0 mils dft

Total system dft :13.0 - 18.0 mils

3. Tnemec Co. Inc.

6800 Corporate Drive, Kansas City, MO 64120

Primer Coat- Series I Primer @ 2.5 - 3.5 mils dft

Intermediate Coat - Series 446 @ 6 - 8 mils dft

Top coat - Series 446 @ 6 - 8 mils dft

Total system dft: 14.5 - 19.5 mils

Contractor may submit other paint systems for approval if the contractor can demonstrate that they are equivalent in formulation and performance to those listed above.

2.3 TEST KITS

2.3.1 Test Kit for Measuring Chloride, Sulfate and Nitrate Ions on Steel and Coated Surfaces

Provide test kits called CHLOR*TEST CSN Salts, as manufactured by CHLOR*RID

International Inc. of Chandler, Arizona (www.chlor-rid.com) or equal. An

"equal" test kit must meet the following requirements:

a. Kit contains all materials,supplies, tools and instructions for field testing and on-site quantitative evaluation of chloride, sulfate and nitrate ions;

Section 09 97 13 Page 11

b. Kit extract solution is acidic, factory pre-measured, pre-packaged, and of uniform concentration;

c. Kit components and solutions are mercury free and environmentally friendly;

d. Kit contains new materials and solutions for each test extraction;

e. Extraction test container (vessel or sleeve or cell) creates a sealed, encapsulated environment during salt ion extraction;

f. Test extract container is suitable for testing the following steel surfaces: horizontal (up/down configuration), vertical, flat, curved, smooth, pitted, and rough;

g. All salt ion concentrations are directly measured in micrograms per square centimeter.

2.3.2 Test Kit for Measuring Chlorides in Abrasives

Provide test kits called CHLOR*TEST-A, as manufactured by CHLOR*RID

International Inc. of Chandler, Arizona (www.chlor-rid.com), or equal. To be considered for approval as an "equal" test kit, each proposed test kit must:

a. Be a completely self-contained test kit with all materials, supplies, tools and instructions to take tests and identify results;

b. Use identifiable, consistent, factory pre-measured test extract solution;

c. Provide for testing equal volumes of abrasive and test solution;

d. Provide for taking direct measurements of the chloride ion in parts per million (PPM), without using conversion charts or tables;

e. Provide all new components for extraction and titration for each test;

f. Provide a factory sealed titration device for each test;

g. Use the extract sampling container as the titration container.

2.4 ABRASIVE

The referenced abrasive specifications have maximum limits for soluble salts contamination, however, this maximum level of contamination does not guarantee that contamination will not be transferred to the steel surface during abrasive blasting. Other factors such as on-site handling and recycling can allow contamination of abrasive. Contractors are cautioned to verify that the chosen abrasive, along with work and storage processes, allow the final surface cleanliness requirements to be achieved. Successful testing of chlorides in abrasive does not negate the final acceptance testing of steel surfaces.

2.4.1 Non-metallic Abrasive

Section 09 97 13 Page 12

Conform to SSPC AB 1, Class A except that:

a. The gross gamma radioactivity must not exceed 5 picocuries per gram.

b. The maximum allowable chloride content is 7 parts per million (ppm) as measured with the test kit described in the paragraph TEST KIT FOR

MEASURING CHLORIDES IN ABRASIVES. Modify the requirements of SSPC AB

2to substitute requirement for one chloride test for each "WATER

SOLUBLE CONTAMINANTS" test required.

c. The maximum allowable Chromium and Cadmium content of the work mix must be less than 0.1 percent by wt. when tested in accordance with ASTM

D3718 for Chromium and ASTM D3335 for Cadmium. Modify the requirements of SSPC AB 2 to add requirement for one Chromate test and one Cadmium test for each "LEAD" test required.

Use abrasive that is specifically selected and graded to provide a sharp, angular profile to the specified depth. Do not use ungraded abrasive. Make adjustments to processes or abrasive gradation to achieve specified surface profile. Recycled non-metallic abrasive must meet all requirements of the specification each time that it is placed in the blast pot.

2.4.2 Metallic Abrasive

2.4.2.1 New and Remanufactured Steel Grit

Conform to the chemical and physical properties of SSPC AB 3 Class 1 (Steel) only. Class 2 (Iron) abrasive must not be used.

To develop a suitable work mix from new steel abrasive, a minimum of 200 -

400 recycles is required, therefore, it is advantageous for a Contractor to use remanufactured steel grit or grit reclaimed from a previous project.

Such grit must be considered to conform if it can be traced to new grit conforming to SSPC AB 3 Class 1 and it meets all cleanliness requirements of

SSPC AB 3 Class 1 when brought to the current jobsite. Submit one representative sample of this work mix to the laboratory for testing, along with samples of new material. Acceptance and use of this work mix must not be used to justify any deviation from surface preparation requirements.

2.4.2.2 Recycled Steel Grit

Abrasive media must conform to the chemical and physical properties of SSPC

AB 2 except that:

a. The maximum allowable chloride content is 7 parts per million (ppm) as measured with the test kit described in the paragraph TEST KIT FOR

MEASURING CHLORIDES IN ABRASIVES. Modify the requirements of SSPC AB

2to substitute requirement for one chloride test for each "WATER

SOLUBLE CONTAMINANTS" test required.

b. The maximum allowable Chromium and Cadmium content of the work mix must be 0.1 percent by wt. when tested in accordance with ASTM D3718 for

Chromium and ASTM D3335 for Cadmium. Modify the requirements of SSPC

AB 2 to add requirement for one Chromate test and one Cadmium test for each "LEAD" test required.

Section 09 97 13 Page 13

PART 3 EXECUTION

Perform all work, rework, and repair in accordance with approved procedures in the Coating Work Plan.

3.1 SURFACES TO BE COATED

Coat exterior surfaces of guide piles from 2’ above low water to the top as indicated on the plans.

3.2 LIGHTING

Provide lighting for all work areas as prescribed in SSPC Guide 12.

3.3 ENVIRONMENTAL CONDITIONS

3.3.1 Containment

Design and provide a containment system for the capture, containment, collection, storage and disposal of the waste materials generated by the work under this Section, to meet the requirements of SSPC Guide 6, Class 3.

Vapor concentrations must be kept at or below 10 percent of Lower Explosive

Limit (LEL) at all times. Containment may be designed as fixed containment for complete structure or portable containment for sections of structure, however, containment must remain in any one place from beginning of abrasive blasting through initial cure of coating. Collection and disposal of waste materials shall be in compliance with all federal, state and local regulations. See Appendix B for limited paint chip analysis.

It is the Contractors responsibility to insure the feasibility and workability of the containment system. The Contractor must perform his operations and work schedule in a manner as to minimize leakage of the containment system. The containment system must be properly maintained and must not deviate from the approved drawings. If the containment system fails to function satisfactorily, the Contractor must suspend all operations, except those required to minimize adverse impact on the environment or government property. Operations must not resume until modifications have been made to correct the cause of the failure.

3.3.2 Automated Monitoring Requirements, Field and Shop Applications

Provide continuous monitoring of temperature, relative humidity, and dew point data at pertinent points on the structure, during surface preparation, coating application, and initial cure. Locate sensors to provide pertinent data for the surface preparation and coat application being performed.

Monitor any heating, cooling, or dehumidification equipment used. Make data available to the Contracting Officer through Internet access. Provide monitoring equipment to perform as follows:

a. Data is collected in the field unit in one minute increments, and available for download or viewing (on-site) in a standard format.

Contractor must collect this data and make available to the Contracting

Officer;

b. Monitoring equipment must have backup power such that data collection and transmission to web server will be uninterrupted during the entire period of the dehumidification requirement;

Section 09 97 13 Page 14

c. Monitoring equipment must have capability to measure surface temperatures at a minimum of four locations;

d. Monitoring equipment must have capability to measure dry bulb temperature (DB), relative humidity (RH), and dewpoint temperature

(DP);

3.4 SURFACE PREPARATION

3.4.1 Abrasive Blasting Equipment

Use abrasive blasting equipment of conventional air, force-feed, or pressure type. Maintain a minimum pressure of 95 psig at nozzle. Confirm that air supply for abrasive blasting is free of oil and moisture when tested in accordance with ASTM D4285. Test air quality at each startup, but in no case less often than every five operating hours.

3.4.2 Operational Evaluation of Abrasive

Test abrasive for salt contamination and oil contamination as required by the appropriate abrasive specification daily at startup and every five operating hours thereafter.

3.4.3 Surface Standard

Inspect surfaces to be coated, and select plate with similar properties and surface characteristics for use as a surface standard. Blast clean one or more 1 foot square steel panels as specified in paragraph SURFACE

PREPARATION. Record blast nozzle type and size, air pressure at nozzle and compressor, distance of nozzle from panel, and angle of blast to establish procedures for blast cleaning. Measure surface profile in accordance with

SSPC PA 17 using Rmax as the measure of profile height. When the surface standard complies with all specified requirements, seal with a clearcoat protectant. Use the surface standard for comparison to abrasive blasted surfaces throughout the course of work.

3.4.4 Pre-Preparation Testing for Surface Contamination

Perform testing, abrasive blasting, and testing in the prescribed order.

3.4.4.1 Pre-Preparation Testing for Oil and Grease Contamination

Inspect all surfaces for oil and grease contamination using two or more of the following inspection techniques: 1) Visual inspection, 2) WATER BREAK

TEST, 3) CLOTH RUB TEST. Reject oil or grease contaminated surfaces, clean using a water based pH neutral degreaser in accordance with SSPC SP 1, and recheck for contamination until surfaces are free of oil and grease.

WATER BREAK TEST - Spray atomized mist of distilled water onto surface, and observe for water beading. If water "wets" surface rather than beading up, surface can be considered free of oil or grease contamination. Beading of water (water forms droplets) is evidence of oil or grease contamination.

CLOTH RUB TEST - Rub a clean, white, lint free, cotton cloth onto surface and observe for discoloration. To confirm oil or grease contamination in lightly stained areas, a non-staining solvent may be used to aid in oil or

Section 09 97 13 Page 15 grease extraction. Any visible discoloration is evidence of oil or grease contamination.

3.4.4.2 Pre-Preparation Testing for Soluble Salts Contamination

Test surfaces for soluble salts, and wash as required, prior to abrasive blasting. Soluble salt testing is also required in paragraph PRE-

APPLICATION TESTING FOR SOLUBLE SALTS CONTAMINATION as a final acceptance test of prepared surfaces after abrasive blasting, and successful completion of this phase does not negate that requirement. This phase is recommended since pre-preparation testing and washing are generally more advantageous than attempting to remove soluble salt contamination after abrasive blasting. Effective removal of soluble salts will require removal of any barrier to the steel surface, including rust. This procedure may necessitate combinations of wet abrasive blasting, high pressure water rinsing, and cleaning using a solution of water washing and soluble salts remover. The soluble salts remover must be acidic, biodegradable, nontoxic, noncorrosive, and after application, will not interfere with primer adhesion. Delays between testing and preparation, or testing and coating application, may allow for the formation of new contamination. Use potable water, or potable water modified with soluble salt remover, for all washing or wet abrasive blasting. Test methods and equipment used in this phase are selected at the Contractor's discretion.

3.4.5 Water Jetting and Abrasive Blasting

On previously coated and prepared surfaces Waterjet all steel surfaces to a

NACE WJ-1, NV-3 condition employing Ultrahigh-Pressure Waterjetting (UHP WJ) at more than 30,000 psi. If mutually agreed upon by the government and contractor at the pre-application meeting, waterjetting must be followed by abrasive blasting the steel surfaces to near-white metal in accordance with

SSPC SP 10/NACE No. 2. Provide a 1 to 2 mil surface profile. Reject profile greater than 5 mils, discontinue abrasive blasting, and modify processes and materials to provide the specified profile. Prepared surfaces must conform to SSPC VIS 1 and must match the prepared test-panels. Measure surface profile in accordance with SSPC PA 17, using Rmax as the measure of profile height. Record all measurements required in this standard. Measure profile at rate of three test areas for the first 1000 square feet plus one test area for each additional 1000 square feet or part thereof. Provide two additional measurements for each non-compliant measurement. When surfaces are reblasted for any reason, retest profile as specified. Following abrasive blasting, remove dust and debris by vacuum cleaning. Do not attempt to wipe surface clean.

On field applications of new surfaces provide a 1 to 2 mil surface profile.

Reject profile greater than 3 mils, discontinue abrasive blasting, and modify processes and materials to provide the specified profile. Prepared surfaces must conform to SSPC VIS 1 and must match the prepared test-panels.

Measure surface profile in accordance with SSPC PA 17, using Rmax as the measure of profile height. Record all measurements required in this standard. Measure profile at rate of three test areas for the first 1000 square feet plus one test area for each additional 1000 square feet or part thereof. Provide two additional measurements for each non-compliant measurement. When surfaces are reblasted for any reason, retest profile as specified. Following abrasive blasting, remove dust and debris by vacuum cleaning. Do not attempt to wipe surface clean.

Section 09 97 13 Page 16

3.4.6 Disposal of Used Abrasive

Dispose of used abrasive off Government property in accordance with Federal, State, and Local mandated regulations.

3.4.7 Pre-Application Testing For Surface Contamination

3.4.7.1 Pre-Application Testing for Oil and Grease Contamination

Ensure surfaces are free of contamination as described in paragraph PRE-

PREPARATION TESTING FOR OIL AND GREASE CONTAMINATION, except that only questionable areas need be checked for beading of water misted onto surface.

3.4.7.2 Pre-Application Testing for Soluble Salts Contamination

Test surfaces for chloride contamination using the Test Kit described in

TEST KIT FOR MEASURING CHLORIDE, SULFATE AND NITRATE IONS ON STEEL AND

COATED SURFACES. Test all surfaces at rate of three tests for the first 1000 square feet plus one test for each additional 2000 square feet or part thereof. Concentrate testing of bare steel at areas of coating failure to bare steel and areas of corrosion pitting. One or more readings greater than 3 micrograms per square centimeter of chlorides or 10 micrograms per square centimeter of sulfates or 5 micrograms per square centimeter of nitrates is evidence of soluble salt contamination. Reject contaminated surfaces, wash as discussed in paragraph PRE-PREPARATION TESTING FOR SOLUBLE

SALTS CONTAMINATION, allow to dry, and re-test until all required tests show allowable results. Reblast tested and cleaned areas as required. Label all test tubes and retain for test verification.

3.4.7.3 Pre-Application Testing for Surface Cleanliness

Apply coatings to dust free surfaces. To test surfaces, apply strip of clear adhesive tape to surface and rub onto surface with finger. When removed, the tape should show little or no dust, blast abrasive, or other contaminant. Reject contaminated surfaces and retest. Test surfaces at rate of three tests for the first 1000 square feet plus one test for each additional 1000 square feet or part thereof. Provide two additional tests for each failed test or questionable test. Attach test tapes to Daily

Inspection Reports.

3.5 MIXING AND APPLICATION OF SEALANT AND COATING SYSTEM

3.5.1 Preparation of Coating Materials for Application

3.5.1.1 Mixing Materials

Mix in accordance with manufacturer's instructions, which may differ for each product and manufacturer. Do not mix partial kits, or alter mix ratios. Mix materials in same temperature and humidity conditions specified in paragraph DELIVERY AND STORAGE. DO NOT ADD SOLVENT without specific written recommendation from the manufacturer.

3.5.1.2 Application Conditions and Recoat Windows

Plan coating application to ensure that coating manufacturers temperature, humidity, and condensation conditions are met. If conditions do not allow for orderly application of the coating system use appropriate means of

Section 09 97 13 Page 17 controlling air and surface temperatures, as required. Partial or total enclosures, insulation, heating or cooling, or other appropriate measures may be required to control conditions to allow for orderly application of all required coats.

3.5.2 Application of Coating System, Joint Sealant and Stripe Coat

Apply coatings in accordance with SSPC PA 1 and as specified herein. Apply coatings to surfaces that meet all stated surface preparation requirements.

Prior to application coatings perform testing prescribed in paragraph PRE-

APPLICATION TESTING FOR SURFACE CONTAMINATION, as necessary, to ensure minimal contamination. If contamination is found, revert to the specified testing rate. Such atmospheric events as a coastal storm blowing onshore can bring unusual chloride contamination. Concern for contamination should be continually prevalent, and spot testing should be accomplished to verify satisfactory conditions. Where visual examination or spot testing indicates contamination, perform sufficient testing to verify non-contamination, or to define extent of contamination for appropriate treatment.

Apply coatings in a consistent wet film in a continuous half lapped spray coat, overlapping 50 percent of the previous spray pass. In multiple coat applications apply two coats at 90 degree application patterns. Ensure that

"cold joints" are no less than six inches from welds. Apply stripe coat by brush. For convenience, stripe coat material may be delivered by spray if followed immediately with brush-out and approved procedures include appropriate controls on thickness. Apply all other coats by spray application. Use appropriate controls to prevent airborne coating fog from drifting beyond 10 feet from the structure or containment perimeter]. Cover or protect all surfaces that will not be coated. The cleanliness, temperature, recoat windows, and airborne paint containment requirements may necessitate the use of enclosures, portable shelters, or other appropriate controls.

3.5.2.1 Application of Coating Material

Apply all field applications of coating materials in accordance with manufacturer's printed instructions and literature. Test in accordance with

SSPC PA 2, Appendix 1 and 3 for conformance.

3.5.2.2 Application of Stripe Coat

Apply stripe coat in hard to access areas. Apply by brush, working material into corners, crevices, angles, and welds, and onto outside corners and angles.

3.5.2.3 Procedure for Holiday and Spot Repairs of Newly Applied Coating

Repair coating film defects at the earliest practicable time, preferably before application of the succeeding coat. Observe all requirements for soluble salts contamination, cleanliness between coats, and application conditions. Prepare defective area in accordance with SSPC SP 10/NACE No.

2, and feather coating as required to leave 6 inches of the coating feathered and abraded. Protect adjacent areas from damage and overspray.

Remove dust and solvent wipe the prepared area plus an additional 6 inches beyond the prepared area with clean denatured alcohol. Prepare repairs and apply coating within 48 hours of the general application coat of coating.

Section 09 97 13 Page 18

Apply each repair coat to approximate thickness of surrounding coating material.

3.6 PROJECT IDENTIFICATION

At the completion of the work, attach a prepared panel with the following information on the structure in 3/4 inch to 1 inch Helvetica style letters:

Date Coated:

Project Number:

Contractor:

Address:

Coating Material and Manufacturer

Surface Prep: SSPC SP ____ Profile: ______

Coating Average Application Thickness: ____

3.7 FIELD QUALITY CONTROL

For marking of surfaces, use chalk for marking bare steel, and water based markers for marking coated surfaces, and remove marks prior to coating. Do not use any wax or grease based markers, or any other markers that leave a residue or stain.

3.7.1 Coating Inspector

The coating inspector must be considered a QC Specialist and must report to the QC Manager. The Coating Inspector must be present during all pre-preparation testing, surface preparation, coating application, initial cure of the coating system, during all coating repair work, and during completion activities. The Coating Inspector must provide complete documentation of conditions and occurrences on the job site, and be aware of conditions and occurrences that are potentially detrimental to the coating system. The requirements for inspection listed in this Section are in addition to the QC inspection.

3.7.2 Field Inspection

3.7.2.1 Inspection and Documentation Requirements

a. Perform field inspection in accordance with ASTM D3276 and the approved

Coating Work Plan. Document Contractor's compliance with the approved

Coating Work Plan.

b. Provide all tools and instruments required to perform the required testing, as well as any tools or instruments that the inspector considers necessary to perform the required inspections and tests.

Document each inspection and test, including required hold points and other required inspections and tests, as well as those inspections and tests deemed prudent from on-site evaluation to document a particular process or condition, as follows:

(1) Location or area;

(2) Purpose (required or special);

(3) Method;

(4) Criteria for evaluation;

(5) Results;

(6) Determination of compliance;

Section 09 97 13 Page 19

(7) List of required rework;

(8) Observations.

c. Collect and record Environmental Conditions as described in ASTM D3276 on a 24 hour basis, as follows:

(1) During surface preparation, every hour or when changes occur;

(2) During coating application and the first four days of initial cure, every hour or when changes occur;

(3) Note location, time, and temperature of the highest and lowest surface temperatures each day;

(4) Use a non-contact thermometer to locate temperature extremes, then verify with contact thermometers.

d. NOTE: Data collected on Environmental conditions in paragraph AUTOMATED

MONITORING REQUIREMENTS may be used for overnight data, however, the data must be constantly verified as to location of sensors and validity of data with respect to the coating work being accomplished.

e. Document all equipment used in inspections and testing, including manufacturer, model number, serial number, last calibration date and future calibration date, and results of on-site calibration performed.

Work documented using data from equipment found to be out of calibration must be considered as non-compliant since last calibration or calibration check, as required.

3.7.2.2 Inspection Report Forms

Develop project-specific report forms as required to report measurement and test results and observations being complete and compliant with contract requirements. This includes all direct requirements of the contract documents and indirect requirements of referenced documents. Show acceptance criteria with each requirement and indication of compliance of each inspected item. Annotation of non-compliance must be conspicuous so as to facilitate identification and transfer to the Rework Log. Report forms must include requirements and acceptance and rejection criteria, and must be legible and presented so that entered data can be quickly compared to the appropriate requirement.

3.7.2.3 Daily Inspection Reports

Submit one copy of daily inspection report completed each day when performing work under this Section, to the Contracting Officer. Note all non-compliance issues, and all issues that were reported for rework in accordance with QC procedures. Each report must be signed by the coating inspector and the QC Manager. Submit report within 24 hours of date recorded on the report.

3.7.2.4 Inspection Logbook

A continuous record of all activity related to this Section must employ the electronic reporting program TruQC or equivalent. The computer / software package must be used to record all information provided in the Daily

Inspection Reports, as well as other pertinent observations and information including photo documentation where appropriate. The designated Government

Representative for the project is assigned the highest level Administrator privilages and only the Administrator must be able to modify reports.

Section 09 97 13 Page 20

3.7.2.5 Inspection Equipment

All equipment must be in good condition, operational within its design range, and calibrated as required by the specified standard for use of each device.

3.7.2.6 Black Light

Use a black light having a 365 nanometer intensity of 4,000 microwatts per square centimeter minimum at 15 inches. The Spectroline BIB-150P from

Spectronics Corporation satisfies this requirement.

3.8 FINAL CLEANUP

Following completion of the work, remove debris, equipment, and materials from the site. Remove temporary connections to Government or Contractor furnished water and electrical services. Restore existing facilities in and around the work areas to their original condition.

-- End of Section --

File details come from the government source that posted it.