Limited_Pre-Renovation_Hazardous_Building_Materials_Survey_Report.pdf
PDF 3 MB Posted
- Solicitation number
- 70Z0G118BPRV08900
About this file
Addendum 1 Hazardous Building Materials
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid_Abstract_70Z0G118BPRV08900.pdf | ||
| Amendment_00002_70Z0G118BPRV08900.pdf | ||
| Addendum-1.pdf | ||
| A-801_Finish_Schedule.pdf | ||
| Amendment_0001_to_18BPRV089.pdf | ||
| P2763063Spec.pdf | ||
| General_Decision_No.NY180012_2.9.18.pdf | ||
| P2763063Dwgs.pdf | ||
| P2763063Addendum.pdf | ||
| SF24_Bid_Bond_Form.pdf | ||
| IFB_70Z0G118BPRV08900.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
LIMITED PRE-RENOVATION HAZARDOUS
BUILDING MATERIALS
SURVEY REPORT
For
U.S. Coast Guard Eatons Neck
Station Housing, Units #1-#11
And Galley Storage Shed
12 Lighthouse Road
Prepared For:
Mr. Glenn W. Pellet, AIA Vice President
Ronald Schmidt & Associates, P.A.
222 Grand Avenue
Englewood, New Jersey 07631
Prepared By:
Langan Engineering, Environmental, Surveying and Landscape Architecture, D.P.C.
555 Long Wharf Drive
New Haven, Connecticut 06511
Matthew Myers
Senior Hazmat Specialist
Report Completion: 21 September 2016
Langan Project No. 140149801
FOR INFORMATION ONLY
P2763063 - AMENDMENT 1AMENDMENT
Limited Pre-Renovation Hazardous Building Materials Survey Report
U.S. Coast Guard Eatons Neck Station Housing, Units #1-#11
And Gallery Storage Shed
Newport, New York
Langan Project No.: 140149801
21 Septeber 2016
And Gallery Storage Shed
Newport, New York
TOC-i
TABLE OF CONTENTS
Page No.
ACRONYMS .............................................................................................................................. ii
EXECUTIVE SUMMARY
1.0 INTRODUCTION
2.0 SITE DESCRIPTION
3.0 SURVEY METHODOLOGY
4.0 ASBESTOS CONTAINING MATERIALS
4.1 Terminology
4.2 Observations and Findings
5.0 LEAD-BASED PAINT
6.0 RADON
7.0 UNIVERSAL/HAZARDOUS WASTE
8.0 CONCLUSIONS AND RECOMMENDATIONS
8.1 Asbestos Containing Materials
8.2 Lead Based Paint
8.3 Radon
8.4 Universal/Hazardous Waste
9.0 LIMITATIONS, EXCEPTIONS AND ASSUMPTIONS
TABLES
Table 1 Summary of Asbestos Survey Findings
Table 2 Lead Based Paint XRF Screening Results
DRAWINGS
ASL-1 & 2 Asbestos Sampling Locations – Eaton’s Neck Housing Units
APPENDICES
Appendix A Asbestos Laboratory Testing Results and Chain of Custody Documentation
Appendix B Radon Laboratory Testing Results
Appendix C Langan’s Certifications
And Gallery Storage Shed
Newport, New York
TOC-ii
ACRONYMS
USEPA United States Environmental Protection Agency
NYSDOL New York State Department of Labor
NYCDEP New York City Department of Environmental Protection
AHERA Asbestos Hazard Emergency Response Act
OSHA Occupational Safety and Health Administration
CAA Clean Air Act
CFR Code of Federal Regulation
EPA United States Environmental Protection Agency
HEPA High Efficiency Particulate Air
HUD Housing and Urban Development
NESHAPS National Standards for Hazardous Air Pollutants
RCRA Resource Conservation and Recovery Act
PLM Polarized Light Microscopy
TEM Transmission Electron Microscopy
ACM Asbestos-Containing Materials
LBP Lead-Based Paint
PCB Polychlorinated Biphenyls (PCB)
SF Square Feet
LF Linear Feet mg/cm2 Milligrams per square centimeter
XRF X-ray Fluorescence
AAS Atomic Absorption Spectrometry
TCLP Toxicity Characteristic Leaching Procedure
FOR INFORMATION ONLY
And Gallery Storage Shed
Newport, New York
EXECUTIVE SUMMARY
Langan Engineering, Environmental, Surveying and Landscape Architecture, D.P.C. prepared this Limited Pre-Renovation Hazardous Building Materials (Hazmat) Survey Report for six residential buildings (Units #1-#11) and the galley storage shed located at 12 Lighthouse Road, Northport, New York. Langan was given access for asbestos and lead XRF screening in units
#1-#4 and #6-#8 and to units #1-#11 for radon testing. All of the residential construction appears to be similar and uniform. The objective of this Limited Hazmat Survey was to identify the presence or absence of asbestos-containing materials (ACM), lead-based paint (LBP), radon and universal or hazardous waste articles prior to performing activities that would disturb them.
The planned renovations consist of the following and the survey was limited to accessible materials possibly to be disturbed by the planned work: replacing boilers, heaters, windows and doors and basement/crawl space fiberglass insulation.
PROJECT INFORMATION:
Client Name:
Ron Schmidt &
Associates and United
States Coast Guard
Survey Dates: 25 August 2016
Professional’s
Project #:
140149801
Construction
Dates:
Housing – 1969
Galley Storage Shed - 1936
Professional’s
Project Manager:
Matthew Myers No. Buildings:
(2) Single Family Homes
(3) Duplex
(1) Triplex
(1) Storage Shed
Phone No.: 203-562-5771 No. of Stories:
Two stories plus attics and basement/crawl spaces
Email: mmyers@langan.com Estimated Bldg.
Gross Footage:
(2) Single Family Homes – 2,200 SF each
(3) Duplex – 4,000 SF each
(1) Triplex – 6,300 SF
(does not include basement/crawl space or attic spaces)
(1) Storage Shed – 150 SF
Property Address: 12 Lighthouse Road Basement and
Crawl Space:
Each of the units has a basement or crawl space. Shed is slab-on-grade
Property Town, County, State:
Northport, New York Property Use: USCG Housing
The following summarizes our findings of ACM, LBP, Radon and universal/miscellaneous hazmat materials identified in the buildings:
FOR INFORMATION ONLY
And Gallery Storage Shed
Newport, New York
Asbestos-Containing Materials (ACM)
Residential Buildings
Material Location % Asbestos and
Sample ID Estimated Quantity
Wall Adhesives –
Miscellaneous Material
Assumed Throughout
Utility Rooms and
Possibly Other Locations -
Inaccessible
1.7% Chrysotile
082513A
Unknown – Only
Accessible and
Sampled in Unit #2 –
Unknown if will be disturbed by planned renovations
Yellow/Tan Sheetrock Taping
Compound – Miscellaneous
Material
Throughout
1.26%
Chrysotile
082517A
Material is <1%
Chrysotile when analyzed with sheetrock as a composite
White Sheetrock
Taping
Compound was found to be
0.25%
Chrysotile
Unknown –
Sheetrock is
Multiple Layers in some locations.
Floor Tile – Miscellaneous
Material
Unit #2 Kitchen –
Assumed Throughout all
Kitchens and Possibly
Bathrooms
1.9% Chrysotile
082521A
Unknown – Only
Accessible for
Sampling in Unit #2
– Unknown if will be disturbed by planned renovations
Due to occupancy of the structure, a destructive survey throughout was not possible;
therefore, suspect materials noted below may exist concealed and are assumed to be ACM.
Material Location
Survey Results Estimated
Quantity
Boiler Units – Interior
Materials and Visible Gaskets
Utility Rooms
Throughout Assumed ACM 11 Units
All asbestos containing materials, assumed asbestos containing materials and materials not sampled for asbestos content must be removed by a properly licensed asbestos abatement
FOR INFORMATION ONLY
And Gallery Storage Shed
Newport, New York contractor if they are to be disturbed by planned renovation activities. A licensed asbestos abatement project designer and abatement project monitors/air sampling technicians will also be required if abatement is necessary. The sheetrock and taping compound will be disturbed by the planned renovation work. This material when analyzed as a composite is less than one percent asbestos, therefore not regulated by EPA or New York State, however OSHA regulations are applicable and proper engineering controls should be in place to prevent visible emissions and possible exposure to workers and building occupants. The boilers should be sampled at a later date to confirm if the interior and exterior materials contain asbestos. This testing should occur after the unit(s) are no longer functional since testing will damage the units.
Lead Based Paint (LBP)
Based on the limited testing XRF screening data and comparison of the data to the Housing and
Urban Development (HUD) guidelines (1.0 mg/cm2), the paint on following building components was identified as LBP:
Residential Units
None Detected
Shed
Concrete Base
Interior Wood Door Trim
Interior Wood Walls
Interior Wood Window Components
The paint on the concrete base, interior door trim, walls and interior window components should be considered to contain lead based paint as defined by HUD. A TCLP sample will be required if the shed is to be demolished in order to properly classify the waste (lead waste versus regular construction debris). OSHA regulations will apply to the work and the contractor must follow all applicable HUD, NY State and local health department regulations as well as ground surface protection from possible lead contamination during work/demolition. This survey did not include full HUD testing that encompasses comprehensive XRF sampling, lead in water, soil and dust sampling.
And Gallery Storage Shed
Newport, New York
Radon
Passive radon detection canisters were placed in the first floors of Units #1 - #11 and the radon results for all of the residential units were all below the EPA action guideline of 4.0 pCi/L.
Universal and Hazardous Waste Articles
Universal and other Hazmat waste articles consisting of light bulbs (possibly ballasts), batteries, possible mercury containing thermostats, smoke detectors, air conditioning units, unit heaters, electric motors, wall mounted electronic devices with circuit boards, transformers, computer equipment, paints, refrigerants, fire extinguishers, chemicals, gasoline, oils, etc. were identified throughout the interior and exterior of the buildings. Universal/hazardous waste articles affected by planned work will need to be properly removed, recycled, and/or disposed of at a landfill permitted to accept such waste. The removal, handling, recycling, and disposal shall be performed in accordance with applicable Federal, State, and local regulations.
Please see section 9.0 of the report for known limitations, exceptions and assumptions for this limited survey.
1.0 INTRODUCTION
Langan Engineering, Environmental, Surveying and Landscape Architecture, D.P.C.
prepared this limited Pre-renovation Hazardous Building Materials (Hazmat) Survey
Report for six residential buildings (Units #1-#11) located at 12 Lighthouse Road, Northport, New York. The objective of this Hazmat Survey was to identify the presence/absence of asbestos-containing materials (ACM), screening for lead-based paint (LBP), radon and universal/hazardous waste articles prior to performing renovation activities. The planned renovations consist of the following and the survey was limited to accessible materials possibly to be disturbed by the planned work: replacing boilers, heaters, windows and doors and basement/crawl space fiberglass insulation.
The remainder of this Report presents our observations, findings, laboratory test results of samples collected, and plans showing sampling locations.
2.0 SITE DESCRIPTION
The portion of the Subject Property planned for renovations is currently improved with six residential buildings (one-triplex, three-duplex, and two-single family houses), playground, lighthouse, four additional buildings, a tennis court, and multiple out-
FOR INFORMATION ONLY
And Gallery Storage Shed
Newport, New York buildings and sheds. This survey is limited to the six residential buildings built in 1969 and one galley storage shed built in 1936. The two sections of this survey include:
Six Residential Buildings – Each unit (#1-11) is of similar construction and consists of: lower level crawl space or basement, 1st Floor living room, kitchen, dining room, toilet room, utility/boiler room, and garage, 2nd Floor multiple bedrooms and bathrooms and attic space.
Shed – Slab-on-grade one room storage area.
Langan was allowed entry to units 1-3 (triplex), 4 (duplex), 6 (single family house), and 7-
8 (duplex) for asbestos sampling and lead XRF screening. Radon testing occurred throughout every unit.
FOR INFORMATION ONLY
And Gallery Storage Shed
Newport, New York
3.0 SURVEY METHODOLOGY
Asbestos-Containing Materials
The asbestos survey was conducted in accordance with EPA protocol outlined in the
EPA publication “Asbestos in Buildings”. Suspect ACM to be disturbed by planned renovations was visually identified during a room-by-room, floor-by-floor survey of the building. Suspect ACM was categorized into various homogeneous materials and types, and sampled and analyzed for asbestos content. Sampling and analysis was conducted in accordance with EPA protocol 600/M4-82-020 per 40 CFR 763. Samples collected were properly packaged in individual containers, sealed; catalogued and chain-of-custody documentation was completed. Quantities of suspect materials were recorded and observations such as physical condition and friability of the materials were also noted. Samples were analyzed by EMSL of Cinnaminson, NJ. This survey was as a
“limited” pre-renovation NESHAP survey. Additional surveys may be required once the spaces have been vacated to access inaccessible areas and areas/materials that could not be sampled due to current occupancy/use.
Lead-Based Paint Screening
A Niton XL300 X-Ray Fluorescence (XRF) Spectrum Analyzer was used to survey the subject building for the presence of lead-based paint (LBP). The Niton analyzer uses a cadmium 109 radioactive source and an advanced solid-state radiation detector to generate an x-ray fluorescence spectrum of a painted surface. During the analysis, the intensity of the x-rays is converted by the instrument’s internal software into an estimate of the concentration of lead in the substance being analyzed. The results are interpreted as concentrations of lead in milligrams per square centimeter. This device is a field-screening tool, used to collect multiple readings in a short period of time. The method of measurement is based on spectrometric analysis of lead x-ray fluorescence within a controlled depth of interrogation. The reading is an estimate of lead content in all layers of paint. The results are displayed in milligrams per square centimeter
(mg/cm2). This survey included an XRF screening of representative accessible painted surfaces only. The lead based paint screening only included accessible painted materials known to probably be disturbed by planned renovations/demolition. This survey did not include full HUD testing that encompasses comprehensive XRF sampling, lead in water, soil and dust sampling.
And Gallery Storage Shed
Newport, New York
Radon
Passive radon detection canisters were placed on the first floors of Units #1 - #11. The detection canisters were placed in accordance to EPA recommended guidelines and
1993 EPA publication “Protocols for Radon and Radon Decay Product Measurements in
Homes”: at least twenty inches from the floor, twelve inches away from exterior walls, away from HVAC intakes and returns, doors and at least thirty six inches from windows.
Closed building conditions (at least 12 hours prior to test) were recommended for the testing.
Universal and Hazardous Waste Articles
Langan performed a walkthrough of the accessible areas and noted universal and possible hazardous waste materials.
4.0 ASBESTOS CONTAINING MATERIALS
4.1 Terminology
Suspect Asbestos-Containing Materials
Asbestos was used in certain types of construction and building materials. Until a material is examined using light microscopy or a similar technique, the building material is considered as a suspect asbestos-containing material. A few examples of these materials include floor tiles, ceiling panels, thermal system insulation, fireproofing insulation, roofing materials, etc. Any suspect ACM of unknown asbestos content (that is not tested) should be handled as if it were an asbestos containing material.
Asbestos–Containing Material
A material with an asbestos concentration greater than one percent by weight is considered to be asbestos-containing by the United States Environmental
Protection Agency (USEPA). Thus, a material which contains asbestos in concentrations greater than 1% by weight is considered as “positive” while materials that do not contain asbestos or asbestos is detected in concentrations less than one percent by weight are considered as “negative”.
FOR INFORMATION ONLY
And Gallery Storage Shed
Newport, New York
4.2 Observations and Findings
The field survey of the subject buildings was conducted on 25 August 2016 by
Langan’s Matthew Myers. During the survey, suspect materials observed in the buildings were documented, assessed, quantified, and sampled as necessary.
As required by the USEPA, samples were analyzed by individual layer (i.e., floor tile & the associated mastic were analyzed as two (2) separate samples). Bulk samples of the suspect ACM were analyzed using the Polarized Light
Microscopy (PLM) analytical methodology in accordance with 40CFR 763 and
NESHAP regulations. Non-friable organically bound (NOB) material samples which tested negative via PLM were reanalyzed using transmission electron microscopy (TEM). Some suspect materials were identified as having asbestos content greater than one percent by weight and are considered to be “positive” for asbestos in accordance with the EPA definition of an asbestos-containing material. Langan had to assume the boiler materials located in the utility rooms of each unit have asbestos containing materials. These materials could not be sampled on the date of inspection because the boilers are functional and sampling would damage them.
Refer to Table 1 for a detailed summary of asbestos survey findings. Refer to
Appendix A for the analytical test results and chain of custody documentation.
Sampling locations are depicted on Drawing ASL-1 and 2.
5.0 LEAD-BASED PAINT
The limited XRF LBP screening was conducted on 25 August 2016 by Langan’s Adem
Bajrami, a USEPA-accredited lead inspector. The locations screened primarily consisted of paint on walls, window and door components. The building components were observed to have mostly similar color surface paint.
The definition of lead based paint as per the Housing and Urban Development (HUD) guidelines was used to compare and evaluate painted surfaces. According to HUD, an
XRF reading below 1.0 mg/cm2 would designate paint as non-LBP, while a reading of
1.0 mg/cm2 or greater would designate paint as LBP.
The lead paint screening of the six residential buildings did not identify lead in excess of
1.0 mg/cm2. A summary of XRF screening data is provided in Table 2. The lead paint screening on the galley storage shed did identify lead in excess of 1.0 mg/cm2 on the
FOR INFORMATION ONLY
And Gallery Storage Shed
Newport, New York interior wood door trim, window components, walls, and exterior concrete base/foundation.
6.0 RADON
Passive radon detection canisters were placed on 25 August 2016 in the first floors of
Units #1 - #11 and picked up on 29 August 2016. The sampling was performed by
NEHA radon certified tester, CT Basement Systems Radon, Inc. The detection canisters were placed in accordance to EPA recommended guidelines and 1993 EPA publication “Protocols for Radon and Radon Decay Product Measurements in Homes”:
at least twenty inches from the floor, twelve inches away from exterior walls, away from HVAC intakes and returns, doors and at least thirty six inches from windows.
Closed building conditions (at least 12 hours prior to test) were recommended for the testing. Results can be found in Appendix B.
USEPA has an action guideline of 4.0 pCi/L and recommends taking further action if results are at or over 4.0 pCi/L. The radon results for all of the residential units were all below the EPA action guideline of 4.0 pCi/L.
7.0 UNIVERSAL/HAZARDOUS WASTE
As mandated by Subtitle C of the Resource Conservation and Recovery Act (RCRA), EPA promulgated hazardous waste regulations in 1980 to ensure that wastes which pose a threat to human health and the environment should be managed safely.
Hazardous waste is a waste with properties that makes it potentially harmful to human health or the environment. Hazardous waste are divided into listed wastes, characteristic wastes, universal wastes, and mixed wastes.
During Langan’s survey, a visual inventory of articles which could potentially become hazardous waste was performed which included light bulbs (possibly ballasts), batteries, possible mercury containing thermostats, smoke detectors, air conditioning units, unit heaters, electric motors, wall mounted electronic devices with circuit boards, transformers, computer equipment, paints, refrigerants, fire extinguishers, chemicals, gasoline, oils, etc. For the purpose of this report, ballasts associated with the lamp fixtures may contain PCBs or other regulated materials; smoke detectors are assumed to contain radioactive materials; and air conditioners and heat transformer systems are assumed to contain CFCs and/or HCFCs.
FOR INFORMATION ONLY
And Gallery Storage Shed
Newport, New York
8.0 CONCLUSIONS AND RECOMMENDATIONS
8.1 Asbestos Containing Materials
Regulatory Guidelines and Requirements
Federal
In accordance with the Clean Air Act (CAA), the U.S. Environmental Protection
Agency (EPA) established National Emission Standards for hazardous Air
Pollutants (NESHAP) to protect the public from exposure to airborne pollutants.
Asbestos was one of the air pollutants, which was addressed under the
NESHAP 40 CFR Part 61. The purpose of asbestos NESHAP regulations is to protect the public health by minimizing the release of asbestos when facilities, which contain ACM, are being renovated or demolished. EPA is responsible for enforcing regulations related to asbestos during renovations and demolition, however, the CAA allows the EPA to delegate this authority to State and Local
Agencies. Even after EPA delegate’s responsibility to a state or Local agency, EPA retains the authority to oversee agency performance and to enforce
NESHAP regulations as appropriate.
State
Asbestos in New York State is regulated under the Labor Law Section 906, Part
56 of Title 12 of the Official Compilation of Codes, Rules, and Regulations.
Within the department and for the purpose of the Department of Labor, this part
(rule) is known as Industrial Code Rule No. 56 (ICR 56) relating to hazards to the public safety and health, during the removal, encapsulation, or disturbance of friable asbestos, or any handling of ACM that may result in the release of asbestos fiber.
Asbestos containing materials were identified in the buildings surveyed. Refer to
Table 1 for a summary of asbestos survey findings.
All confirmed ACM will need to be removed prior to any building renovation activities. The removal and disposal of ACM must be performed by a NYS-DOL licensed asbestos handling contractor in accordance with Federal, state, and local regulations. Proper notifications must be filed with the US-EPA, NYS-DOL and other regulatory agencies prior to performing such activities. Langan
FOR INFORMATION ONLY
And Gallery Storage Shed
Newport, New York recommends having abatement specifications completed by a licensed asbestos abatement designer.
As required by the NYS-DOL regulations, the abatement project must be monitored by a NYS-DOL certified project monitor. The project monitor oversees contractor’s work practices and also performs pre, during, and final clearance post abatement air sampling in accordance with the state regulations.
The sheetrock and taping compound will be disturbed by the planned renovation work. This material when analyzed as a composite is less than one percent asbestos, therefore not regulated by EPA or New York State, however OSHA regulations are applicable and proper engineering controls should be in place to prevent visible emissions and possible exposure to workers and building occupants. The boilers should be sampled at a later date to confirm if the interior and exterior materials contain asbestos. This testing should occur after the unit(s) are no longer functional since testing will damage the units.
8.2 Lead Based Paint
Based on the limited XRF screening data and comparison of the results to the
HUD guidelines, the paint on several building components was identified as LBP.
Refer to Table 2 for the XRF screening data. This survey did not include full HUD testing that encompasses comprehensive XRF sampling, lead in water, soil and dust sampling.
Please note that although the HUD defines lead based paint as paint having lead concentrations equal or greater than 1.0 mg/cm2, the Occupational Safety and
Health Administration (OSHA) considers any concentration of lead in paint to be lead containing paint. Regardless of the lead concentrations in paint, the contractor shall comply with 29 CFR 1926.62, OSHA regulations, and take precautionary measures for dust control and limit employee exposure to lead dust during the renovations.
Painted surfaces that would be impacted by planned activities such as drilling, cutting, welding, scrapping, etc. and create dust should be properly addressed by following safe work practices, good housekeeping procedures and/or following proper abatement procedures. Grinding and sanding of paint without
HEPA filter exhaust, open flame gas fired torch, unconfined abrasive blasting, FOR INFORMATION ONLY
And Gallery Storage Shed
Newport, New York and chemical strippers containing methylene chloride or other human carcinogenic chemicals are not recommended.
The Federal Resource Conservation and Recovery Act (RCRA) regulation governs the handling, transportation, and disposal of hazardous materials. Every demolition/renovation debris generator has the responsibility to determine whether the debris exhibits one or more of the characteristic wastes listed in subpart C of 40 CFR Part 261.
Metal objects painted with LBP are exempt from disposal regulations applicable to lead, provided they are properly recycled. All metal objects that are painted with LBP should be sent to a certified recycling facility.
The paint on the galley storage shed concrete base, interior door trim, walls and interior window components should be considered to contain lead based paint as defined by HUD. A TCLP sample will be required if the shed is to be demolished in order to properly classify the waste (lead waste versus regular construction debris). OSHA regulations will apply to the work and the contractor must follow all applicable HUD, NY State and local health department regulations as well as ground surface protection from possible lead contamination during work/demolition.
8.3 Radon
The radon results for all of the residential units were all below the EPA action guideline of 4.0 pCi/L.
8.4 Universal/Hazardous Waste
Miscellaneous and universal wastes consisting of but not limited to light bulbs
(possibly ballasts), batteries, possible mercury containing thermostats, smoke detectors, air conditioning units, unit heaters, electric motors, wall mounted electronic devices with circuit boards, transformers, computer equipment, paints, refrigerants, fire extinguishers, chemicals, gasoline, oils, etc. were noted during the visual survey. For the purpose of this report, ballasts associated with the lamp fixtures may contain mercury/PCBs or other regulated materials; smoke detectors are assumed to contain radioactive materials; and air conditioners and heat transformer systems are assumed to contain CFCs and/or HCFCs.
FOR INFORMATION ONLY
And Gallery Storage Shed
Newport, New York
Universal/hazardous waste articles affected by planned work will need to be properly removed, recycled, and/or disposed of at a landfill permitted to accept such waste. The removal, handling, recycling, and disposal shall be performed in accordance with applicable Federal, State, and local regulations.
9.0 LIMITATIONS, EXCEPTIONS AND ASSUMPTIONS
Opinions and recommendations presented in this report apply to site conditions and features as they existed at the time of Langan’s site visit, and those reasonably foreseeable. They cannot necessarily apply to conditions and features of which Langan is unaware and has not had the opportunity to evaluate.
Any suspect building material that is not listed in this report must be assumed to be
ACM and treated as such unless otherwise confirmed by laboratory testing. Additional suspect asbestos containing materials could be present behind wall/ceiling
/floor/component surfaces (pipe/duct insulation, wall and floor damp-proofing and tars/adhesives, multiple layers of flooring/walls/ceilings, paper under wood flooring), materials underneath asphalt, concrete and other ground surfaces (foundation damp-proofing, transite piping, etc.), hidden older caulking and glazing compounds
(inaccessible – possibly behind newer windows and doors – would need to demolish windows/doors to investigate), light backing insulation, interior components of crawl space heaters, sink undercoating, transite cement board (under newer siding and soffits), and fire door insulation (entry doors, door into utility room, etc – need to damage door to investigate). The roofing materials (except for storage shed) were not included as part of this survey. Langan was only allowed to obtain asbestos samples and perform lead based paint screening from a limited number of units. The units appear to be similar in appearance, have similar building history and building materials.
PCB sampling of caulking/glazing/sealant compounds, paints, tars, mastics, etc. was not performed as part of this survey.
The conclusions presented in this report are professional opinions based solely upon
Langan’s visual observations of accessible areas, laboratory test data and current regulatory requirements. These conclusions are intended exclusively for the purpose stated herein, at the site indicated, and for the project indicated.
It is important to recognize that even the most comprehensive scope of services may fail to detect all asbestos containing materials that may be associated with the property.
Langan cannot, therefore, act as insurers and cannot “certify” that all asbestos
FOR INFORMATION ONLY
And Gallery Storage Shed
Newport, New York containing materials associated with the property have been identified, and no expressed or implied representation or warranty is included or intended in our report, except that our services were performed, within the limits prescribed by our client, with the customary thoroughness and competence of our profession.
\\langan.com\data\NHV\data8\140149801\Engineering Data\Environmental\Hazmat\Pre-Renovation NY Hazmat Survey Report -
Eaton's Neck.doc
TABLES
FOR INFORMATION ONLY
Material Sample ID Location Friable
Yes/No Notes/Comments
Wall Adhesives 082513A Assumed Throughout Utility Rooms ACM CHRY 1.70% No Unknown SF
Only visible in Unit #2, may exist in other locations. Unknown if planned work will disturb material.
Sheetrock Taping Compound 082515B, 082517A Throughout ACM CHRY
0.25-
1.26% Yes Unknown SF
The yellow/tan taping compound was found to contain 1.26% ACM. The white taping compound was found to contain 0.25% ACM. These may exist in multiple layers on walls and ceilings.
Sheetrock/Taping Compound - Composite 082519, 082520 Throughout Non-ACM CHRY <1% Yes
Sheetrock and taping compound composites are
<1% ACM and can be removed using engineering controls or as an abatement.
Floor Tile 082521A
Kitchen - Unit #2 - Assumed
Throughout and possibly in Bathrooms also
ACM CHRY 1.9% No Unknown SF
Mulitple layers of flooring materials were noted in
Unit #2 Kitchen and are assumed in the bathrooms throughout. Unit #2 was undergoing renovations on the date of inspection and Langan was allowed to sample the kitchen flooring materials. One floor tile layer was found to contain asbestos and it maybe present in other locations but due to the destructive sampling required to access materials, Langan was not given authorization to sample additional areas/materials.
Unknown if planned work will disturb flooring materials.
Black Mastic on Floor Hatches 082518A,B Access to Basements/Crawl Spaces Non-ACM CHRY <1% No
Boiler Units - Interior Materials and Visible Gaskets - Utility Rooms Throughout Assumed
ACM
Yes -
Assume Unknown SF
Boilers were functional on the date of inspection and Langan was not authorized to sample hidden materials. Sampling may have permanently damaged the boilers.
Fiberglass Insulation Backing 082501A,B -
02A,B Throughout - Attic and Basements Non-ACM ND - _ -- -
Chimney Flue Cement 082503A-F Utility Rooms Throughout Non-ACM ND - -- -- -
Black Window Screen Glazing 082504A,B Throughout Non-ACM ND - -- -- -
Window Caulking Compound 082505A-C Throughout Non-ACM ND - -- -- -
Door Caulking Compound 082506A-C Throughout Non-ACM ND - -- -- -
Garage Door Caulking Compound 082507A-C Throughout Non-ACM ND - -- -- -
Silver/Black Paper on Foam Behind Siding 082508A-C Throughout Non-ACM ND - -- -- -
Interior Window Caulking 082510A,B Throughout Non-ACM ND - -- -- -
Ceiling Tiles 082511A,B -
12A,B Utility Rooms Throughout Non-ACM ND - -- -- -
Sheetrock 082514A,B
082516A,B Throughout Non-ACM ND - -- -- -
Flooring Materials - Tiles, Adhesives, Ceramic Tiles
Mud Bed and Grout and Concrete Floor Board
(except as noted above)
082522A,B -
27A,B Throughout Non-ACM ND - -- -- -
Window Glazing 082528A,B Exterior Non-ACM ND - -- -- -
Black/Brown Paper Behind Wood Siding 082529A,B Exterior Non-ACM ND - -- -- -
Roofing Materials 082530A,B -
31A-F Roof Non-ACM ND - -- -- -
1 A material with asbestos content greater than one percent (>1.0%) is considered as an asbestos-containing material (ACM). Concentrations in weight percent.
2 ND = “None Detected” – Asbestos not detected in sampled material.
3 CHRY = Chrysotile Asbestos
Table -T1 - SUMMARY OF ASBESTOS SURVEY FINDINGS
US Coast Guard - Eaton's Neck Units #1-#11
Northport, New York
Estimated Quantity of ACM/ Assumed Survey Results
Residential Units #1-#11
Storage Shed
FOR INFORMATION ONLY
Project Name: Action Level: 1.0 mg/cm
Survey Date: 8/25/2016 Total Assays Reported: 119
Survey Component Substrate Color Test Location Total Lead Results Comments
ID# mg/cm
1 N/A
2 1.0
3 0.9
4 Window Casing Wood White Unit 1 Living Room <LOD NEGATIVE ---
5 Window Casing Wood White Unit 1 Living Room <LOD NEGATIVE ---
6 Window Sash Wood White Unit 1 Living Room 0.01 NEGATIVE ---
7 Window Sill Wood White Unit 1 Living Room <LOD NEGATIVE ---
8 Radiator Metal White Unit 1 Living Room 0.01 NEGATIVE ---
9 Wall Sheetrock White Unit 1 Living Room <LOD NEGATIVE ---
10 Wall Sheetrock White Unit 1 Dining Room <LOD NEGATIVE ---
11 Baseboard Wood White Unit 1 Dining Room <LOD NEGATIVE ---
12 Stair Wood White Unit 1 Stair <LOD NEGATIVE ---
13 Door Front Wood White Unit 1 Living Room <LOD NEGATIVE ---
14 Door Trim Wood White Unit 1 Living Room <LOD NEGATIVE ---
15 Ceiling Sheetrock White Unit 1 Living Room <LOD NEGATIVE ---
16 Wall Sheetrock White Unit 1 Kitchen <LOD NEGATIVE ---
17 Wall Sheetrock White Unit 1 Bathroom <LOD NEGATIVE ---
18 Door Metal White Unit 1 Kitchen <LOD NEGATIVE ---
19 Wall Sheetrock White Unit 1 Utility Room 0.04 NEGATIVE ---
20 Door Metal White Unit 1 Utility Room <LOD NEGATIVE ---
21 Door Trim Wood White Unit 1 Utility Room <LOD NEGATIVE ---
22 Window Casing Wood White Unit 1 Utility Room <LOD NEGATIVE ---
23 Window Sill Wood White Unit 1 Utility Room <LOD NEGATIVE ---
24 Wall Sheetrock White Unit 1 Bedroom <LOD NEGATIVE ---
25 Window Casing Wood White Unit 1 Bedroom <LOD NEGATIVE ---
26 Window Sill Wood White Unit 1 Bedroom <LOD NEGATIVE ---
27 Window Sash Wood White Unit 1 Bedroom <LOD NEGATIVE ---
28 Ceiling Sheetrock White Unit 1 Bedroom <LOD NEGATIVE ---
29 Door Wood Green Exterior Units 1-3 0.3 NEGATIVE ---
30 Door Trim Wood White Exterior Units 1-3 0.25 NEGATIVE ---
31 Door Trim Metal White Exterior Units 1-3 0.6 NEGATIVE ---
32 Screen Door Metal White Exterior Units 1-3 <LOD NEGATIVE ---
33 Handrail Metal Black Exterior Units 1-3 0.01 NEGATIVE ---
34 Window Vinyl White Exterior Units 1-3 <LOD NEGATIVE ---
35 Wall Vinyl Gray Exterior Units 1-3 0.01 NEGATIVE ---
36 Garage Door Metal White Exterior Units 1-3 <LOD NEGATIVE ---
37 Garage Door Trim Metal White Exterior Units 1-3 0.5 NEGATIVE ---
Door Threshold Entry
Step Wood White Exterior Units 1-3 0.9 NEGATIVE ---
Door Threshold Entry
Riser Wood White Exterior Units 1-3 0.11 NEGATIVE ---
40 Garage Door Metal White Exterior Units 7-8 <LOD NEGATIVE ---
41 Garage Door Trim Metal White Exterior Units 7-8 0.5 NEGATIVE ---
42 Window Vinyl White Exterior Units 7-8 <LOD NEGATIVE ---
43 Wall Vinyl Gray Exterior Units 7-8 <LOD NEGATIVE ---
Door Threshold Entry
Step Wood White Exterior Units 7-8 0.03 NEGATIVE ---
Door Threshold Entry
Riser Wood White Exterior Units 7-8 <LOD NEGATIVE ---
46 Screen Door Metal White Exterior Units 7-8 <LOD NEGATIVE ---
47 Door Trim Wood White Exterior Units 7-8 0.11 NEGATIVE ---
48 Door Wood Green Exterior Units 7-8 0.01 NEGATIVE ---
Table -T2 - XRF SCREENING RESULTS
US Coast Guard - Eaton's Neck Units #1-#11
Northport, New York
Site
Address:
Northport, NY
US Coast Guard - Eaton's Neck Units #1-#11
Calibration
Calibration
Calibration
Residential Units
FOR INFORMATION ONLY
Survey Date: 8/25/2016 Total Assays Reported: 119
Survey Component Substrate Color Test Location Total Lead Results Comments
ID# mg/cm
Table -T2 - XRF SCREENING RESULTS
US Coast Guard - Eaton's Neck Units #1-#11
Northport, New York
Site
Address:
Northport, NY
US Coast Guard - Eaton's Neck Units #1-#11
49 Door Trim Entry Wood White Unit 8 Living Room <LOD NEGATIVE ---
50 Entry Door Wood White Unit 8 Living Room <LOD NEGATIVE ---
51 Door Wood White Unit 8 Living Room <LOD NEGATIVE ---
52 Wall Sheetrock White Unit 8 Living Room <LOD NEGATIVE
53 Window Casing Wood White Unit 8 Living Room <LOD NEGATIVE ---
54 Window Sill Wood White Unit 8 Living Room <LOD NEGATIVE ---
55 Window Well Metal White Unit 8 Living Room <LOD NEGATIVE ---
56 Window Apron Wood White Unit 8 Living Room <LOD NEGATIVE ---
57 Window Mullion Wood White Unit 8 Living Room <LOD NEGATIVE ---
58 Radiator Metal White Unit 8 Kitchen <LOD NEGATIVE ---
59 Radiator Side Metal White Unit 8 Kitchen <LOD NEGATIVE ---
60 Small Radiator Metal White Unit 8 Kitchen <LOD NEGATIVE ---
61 Baseboard Wood White Unit 8 Dining Room <LOD NEGATIVE ---
62 Baseboard Wood White Unit 8 Dining Room <LOD NEGATIVE ---
63 Ceiling Sheetrock White Unit 8 Living Room <LOD NEGATIVE ---
64 Sideboard Wood White Unit 8 Stair <LOD NEGATIVE ---
65 Riser Wood White Unit 8 Stair <LOD NEGATIVE ---
66 Handrail Metal Black Unit 8 Stair 0.01 NEGATIVE ---
Wall Sheetrock White
Unit 8 2 nd
Floor
Bathroom
<LOD NEGATIVE ---
Window Casing Wood White
Unit 8 2 nd
Floor
Bathroom
<LOD NEGATIVE ---
Window Sill Wood White
Unit 8 2 nd
Floor
Bathroom
<LOD NEGATIVE ---
Window Apron Wood White
Unit 8 2 nd
Floor
Bathroom
<LOD NEGATIVE ---
Window Well Metal White
Unit 8 2 nd
Floor
Bathroom
<LOD NEGATIVE ---
72 Wall Sheetrock White Unit 6 Kitchen <LOD NEGATIVE ---
73 Window Casing Wood White Unit 6 Kitchen <LOD NEGATIVE ---
74 Window Sash Wood White Unit 6 Kitchen <LOD NEGATIVE ---
75 Window Apron Wood White Unit 6 Kitchen <LOD NEGATIVE ---
76 Radiator Metal White Unit 6 Kitchen 0.05 NEGATIVE ---
77 Baseboard Wood White Unit 6 Kitchen <LOD NEGATIVE ---
78 Ceiling Sheetrock White Unit 6 Living Room 0.02 NEGATIVE ---
79 Wall Sheetrock White Unit 6 Dining Room <LOD NEGATIVE ---
80 Window Casing Wood White Unit 6 Dining Room <LOD NEGATIVE ---
81 Window Sill Wood White Unit 6 Dining Room <LOD NEGATIVE ---
82 Window Sash Wood White Unit 6 Dining Room <LOD NEGATIVE ---
83 Window Apron Wood White Unit 6 Dining Room <LOD NEGATIVE ---
84 Wall Sheetrock White Unit 6 Bedroom <LOD NEGATIVE ---
85 Window Casing Wood White Unit 6 Bedroom 0.03 NEGATIVE ---
86 Window Sill Wood White Unit 6 Bedroom <LOD NEGATIVE ---
87 Window Apron Wood White Unit 6 Bedroom <LOD NEGATIVE ---
88 Door Metal White Unit 6 Living Room <LOD NEGATIVE ---
89 Door Metal Green Exterior Unit 6 <LOD NEGATIVE ---
90 Door Trim Wood White Exterior Unit 7 <LOD NEGATIVE ---
91 Door Threshold Entry RiserMetal White Exterior Unit 8 <LOD NEGATIVE ---
92 Wall Vinyl Gray Exterior Unit 9 <LOD NEGATIVE ---
93 Window Vinyl White Exterior Unit 10 <LOD NEGATIVE ---
94 Wall Wood White Exterior 0.22 NEGATIVE ---
95 Wall Wood White Exterior 0.02 NEGATIVE ---
96 Bottom Trim Metal White Exterior 0.03 NEGATIVE ---
97 Upper Trim/Roof Wood White Exterior 0.4 NEGATIVE ---
Shed
FOR INFORMATION ONLY
Survey Date: 8/25/2016 Total Assays Reported: 119
Survey Component Substrate Color Test Location Total Lead Results Comments
ID# mg/cm
Table -T2 - XRF SCREENING RESULTS
US Coast Guard - Eaton's Neck Units #1-#11
Northport, New York
Site
Address:
Northport, NY
US Coast Guard - Eaton's Neck Units #1-#11
98 Upper Trim/Roof Wood White Exterior <LOD NEGATIVE ---
99 Door Trim Wood Green Exterior 0.03 NEGATIVE ---
100 Door Frame Wood Green Exterior 0.18 NEGATIVE ---
101 Door Wood Green Exterior 0.01 NEGATIVE ---
102 Wall Wood White Exterior 0.19 NEGATIVE ---
103 Wall Trim Wood White Exterior 0.3 NEGATIVE ---
104 Base Concrete Gray Exterior 2.0 POSITIVE
105 Window Casing Wood Green Exterior 0.17 NEGATIVE
106 Window Sash Wood Green Exterior 0.8 NEGATIVE
107 Window Sill Wood Green Exterior 0.16 NEGATIVE
108 Door Trim Wood White Interior 2.0 POSITIVE
109 Door Wood White Interior <LOD NEGATIVE
110 Wall Wood White Interior 13.8 POSITIVE
111 Ceiling Wood White Interior <LOD NEGATIVE
112 Wall Wood White Interior 16.4 POSITIVE
113 Floor Concrete Gray/Red Interior 0.13 NEGATIVE
114 Window Casing Wood White Interior 3.2 POSITIVE
115 Window Sill Wood White Interior 2.1 POSITIVE
116 Window Sash Wood White Interior 1.7 POSITIVE
117 Window Apron Wood White Interior 2.2 POSITIVE
118 1.1
119 1.1
NEGATIVE = Negative Lead Result <LOD = Less than level of detection
POSITIVE = Positive Lead Result
DAILY CALIBRATIONS
Date: 8/25/2016
Calibration Check
Good
Calibration
Calibration
FOR INFORMATION ONLY
DRAWINGS
FOR INFORMATION ONLY
APPENDIX A
Asbestos Laboratory Testing Results and Chain of Custody Documentation
FOR INFORMATION ONLY
APPENDIX B
Radon Laboratory Testing Results
APPENDIX C
Langan’s Certifications
File details come from the government source that posted it.