This document is an amendment to a solicitation for maintenance dredging services at the Mooring Ballast Point in San Diego, California. The United States Coast Guard is seeking a contractor to dredge up to an estimated 10,700 cubic yards of sediment from the mooring basin and boat house areas to a required depth of -30 feet MLLW plus an additional two feet of overdepth dredging allowed to -32 feet MLLW. Dredged materials will be transported via barge to the disposal site at the Silver Strand Boat Lanes U.S. Navy facility. The amendment provides responses to contractor questions, clarifying that removal of floating docks is optional, correcting the overdepth specification in the pricing sheet, and confirming the estimated dredging quantity is 10,700 cubic yards.

View the file

Other files

File Type Posted
ABSTRACT OF OFFERS-Form 1419-IFB-70Z08824R0000001- DREDGING BALLAST PT.pdf PDF
Amendment 0005 - IFB 70Z08824R0000001_MAINTENANCE DREDGING AT STA HUMBOLDT.pdf PDF
APPENDIX D-WAGE DETERMINATION_ CA20230001-San Diego-17Nov2023.pdf PDF
Amendment 0004 - IFB 70Z08824R0000001_MAINTENANCE DREDGING AT STA HUMBOLDT.pdf PDF
IFB 70Z08824R0000001_MTC DREDGING AT USCG MOORING BALLAST PT-REV_30Nov23.pdf PDF
Amend 2-Attach 1-2022_SURVEY_BALLAST_PT_MOORING.pdf PDF
Amend 2-Attach 2-2022 SURVEY-CAD_BALLAST_PT_MOORING.zip ZIP file
Amendment 0002 - IFB 70Z08824R0000001_MAINTENANCE DREDGING AT STA HUMBOLDT.pdf PDF
Amendment 0001 - IFB 70Z08824R0000001_MAINTENANCE DREDGING AT STA HUMBOLDT.pdf PDF
APPENDIX A-SF1442-24R0000001_StaMooringBallastPt- Dredging.pdf PDF
APPENDIX B1-PERMITS_StaMooringBallastPt- Dredging.pdf PDF
Amendment 0001 - IFB 70Z08824R0000001_MAINTENANCE DREDGING AT STA HUMBOLDT.pdf PDF
APPENDIX B4-MAP_StaMooringBallastPt- Dredging.pdf PDF
APPENDIX B2-HYDRO SURVEY_StaMooringBallastPt- Dredging.pdf PDF
APPENDIX E-Contractor Responsibility.pdf PDF
APPENDIX B3-DRAWINGS_StaMooringBallastPt- Dredging.pdf PDF
IFB 70Z08824R0000001_MTC DREDGING AT USCG MOORING BALLAST PT.pdf PDF
APPENDIX F-Clarification Request Form.docx DOCX document
APPENDIX C-SPECIFICATIONS_StaMooringBallastPt- Dredging_11Oc123.pdf PDF
APPENDIX D-WAGE DETERMINATION_ CA20230001-San Diego-06Oct2023.pdf PDF
APPENDIX G-CERT OF AUTHORIZATION TO BIND CORPORATION FAR 4.pdf PDF
Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. CONTRACT ID CODE PAGE OF PAGES

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1 3

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)

0003 11/30/2023 51290PR240000001 10229158

6. ISSUED BY CODE 51290 7. ADMINISTERED BY (If other than Item 6) CODE

Commanding Officer

CG CEU OAKLAND (CN)

1301 Clay Street 7th Floor, Suite 700N Oakland, CA 94612-5203

Commanding Officer

CG CEU OAKLAND (CN)

1301 Clay Street 7th Floor, Suite 700N Oakland, CA 94612-5203

8. NAME AND ADDRESS OF CONTRACTOR (No. Street, county, State and ZIP: Code) () 9A. AMENDMENT OF SOLICITATION NO.

X IFB 70Z08824R0000001

9B. DATED (SEE ITEM 11)

11/06/2023

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers: is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing Items 8 and 15, and returning one (1) copy of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATA SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and data specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

() A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT/ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.)

SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER: Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return 1 copy to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

IFB 70Z08824R0000001-MAINTENANCE DREDGING AT MOORINGS BALLAST POINT - SAN DIEGO, CA

The purpose of this Amendment No. 0003 is to provide answers to RFI Numbers 6-12 on the following pages.

Except at provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

Travis Cohen Contracting Officer

15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED

(Signature of person authorized to sign)

BY

(Signature of Contracting Officer)

NSN 7540-01-152-8070 30-105 STANDARD FORM 30 (REV. 10-83)

PREVIOUS EDITION UNUSABLE COMPUTER GENERATED Prescribed by

IFB 70Z08824R0000001

MAINTENANCE DREDGING AT MOORINGS BALLAST POINT

RFIs 6-12

Question 6:

Will the Contractor be allowed to perform the required eelgrass survey any time during December or January?

Response 6:

The USCG will coordinate with NMFS to conduct an eelgrass survey outside the growing season once a contractor is awarded the project.

Question 7:

PART 1 GENERAL, 1.01 SCOPE OF WORK states: Provide all labor, materials, and equipment necessary to dredge and dispose of sediment from the mooring basin and boat house areas at U.S.

Coast Guard (USCG) Mooring Ballast Point, located in San Diego, California. Dredge up to 7,800 cubic yards (cy) of sediment by mechanical means to the indicated design depth of -30.0 feet Mean Lower Low Water (MLLW) plus 2 feet over depth allowance.

Please clarify what is the maximum quantity that the Coast Guard will pay for during this dredging episode including the 2’ over depth dredging?

Response 7:

The USCG will pay for over depth.

Question 8:

Will the dredge schedule be impacted by Navy ship movements? If so, when?

Response 8:

Navy ship movements should not be an issue but we will confirm once we have a contractor and confirmed dredge dates.

Question 9:

DIVISION 02 – EXISTING CONDITIONS, 02 41 00 – TEMPORARY REMOVAL AND RE-INSTALLATION OF

FLOATING DOCKS, PART 1 GENERAL 1.01 SECTION INCLUDES (OPTION ITEM): This section applies to all work required for temporary removal and reinstallation of the existing floating concrete dock (measures approximately 250 feet long by 15 feet wide). The scope of work includes disconnecting the existing floating concrete dock, tugging it away temporarily, and reinstalling it in the same original configuration once dredging work is completed.

Since the Schedule of Prices does not include any Option Items – please clarify IF the removal and reinstallation of the existing floating docks is required.

Response 9:

Removal of docks is up to the contractor - if they think they can do a mechanical dredge without moving them while still meeting the depth requirements, they do not need to remove them.

Question 10:

CLIN 002 states: DREDGING AND DISPOSAL: Required Dredging depth is -30.00 ft mean lower low water (MLLW). Two (2) feet of Over-depth is authorized to -10.00 ft.

See Appendix C-SPECS

The Specifications indicate a design depth of -30.00 ft and an overdepth limit of -2’ (overdepth allowance -32.00 ft). The Schedule of Prices, CLIN 002 does not correspond with the Specifications in terms of the total overdepth. CLIN 002 indicates a total overdepth of -10’00 ft.

Should the description for CLIN-002 read:

DREDGING AND DISPOSAL: Required Dredging depth is -30.00 ft mean lower low water (MLLW).

Two (2) feet of Over-depth is authorized to -32.00 ft.

Please revise the Schedule of Prices if necessary.

Response 10:

Yes, should read two feet of over depth is -32 ft not 10. If submitting a bid, please correct (hand-correct acceptable) and/or note the Typo.

Question 11:

The Scope of Work requires that the Contractor is responsible for complying with all permit conditions from the Army Corps of Engineers, U. S. Environmental Protection Agency (EPA) Conditions for use of HOODS, the National Marine Fisheries Service (NMFS) consultation requirements, and conditions required by the State of California Water Quality Control Board and California Coastal Commission.

The Water Certification from the State of California Water Quality Control Board is not included in the Permits appendix. Please provide the Water Cert for review and clarify if water quality monitoring is required as part of the scope of work.

Response 11:

We have confirmation that we do not need a 401 for this episode.

Question 12:

Please clarify if the Estimated Quantity for CLIN-002 should be 10,700 cy instead of 7,800 CY.

DIVISION 01 - GENERAL REQUIREMENTS

01 10 00 - GENERAL PARAGRAPHS

1.02 BASIS FOR BIDS

A. Base Bid

2) Dredging: Dredge the USCG Ballast Point mooring basin by clamshell or backhoe dredge to the indicated design depth of -30.0 feet MLLW plus 2 feet over-depth allowance. Transport the dredged sediment by barge to the sediment placement facility, the Silver Strand Boat Lanes U.S.

Navy site.

The removal, transport and disposal of dredged sediment shall be paid for at the established unit prices per cubic yard (cy) and based on the difference in volume between the pre- and post- dredge hydrographic surveys of the dredge prism. Payment for dredging, including disposal fees, shall not be made for dredging deeper than the allowable overdepth, dredging outside the authorized areas, or dredging and/or disposing of sediment in an unauthorized manner. The estimated unit price dredge quantity is 10,700 cy. This is based upon the volume to dredge to the design depth plus the volume to dredge the allowable over-dredge depths as indicated by the hydrographic survey, dated 8 August 2022.

Response 12:

10,700 is the estimated amount with over dredge.