Amendment 0002 - IFB 70Z08824R0000001_MAINTENANCE DREDGING AT STA HUMBOLDT.pdf

PDF 236 KB Posted

Attached to
MAINTENANCE DREDGING AT MOORINGS BALLAST POINT POINT LOMA - SAN DIEGO, CA
Solicitation number
70Z08824R0000001
Issued by

About this file

This document is an amendment to a solicitation for maintenance dredging services at Mooring Station Ballast Point in San Diego, California. The United States Coast Guard is seeking a contractor to dredge the area to required depths between September 16, 2023 and March 31, 2024, with all work to be completed by the latter date. The amendment provides responses to request for information questions about survey files, security barriers, allowable dredging hours which are limited to daylight due to biological monitoring requirements, and clarifies that liquidated damages do not apply to the contract.

View the file

Other files

File Type Posted
ABSTRACT OF OFFERS-Form 1419-IFB-70Z08824R0000001- DREDGING BALLAST PT.pdf PDF
Amendment 0005 - IFB 70Z08824R0000001_MAINTENANCE DREDGING AT STA HUMBOLDT.pdf PDF
APPENDIX D-WAGE DETERMINATION_ CA20230001-San Diego-17Nov2023.pdf PDF
Amendment 0004 - IFB 70Z08824R0000001_MAINTENANCE DREDGING AT STA HUMBOLDT.pdf PDF
IFB 70Z08824R0000001_MTC DREDGING AT USCG MOORING BALLAST PT-REV_30Nov23.pdf PDF
Amendment 0003 - IFB 70Z08824R0000001_MAINTENANCE DREDGING AT STA HUMBOLDT.pdf PDF
Amend 2-Attach 1-2022_SURVEY_BALLAST_PT_MOORING.pdf PDF
Amend 2-Attach 2-2022 SURVEY-CAD_BALLAST_PT_MOORING.zip ZIP file
Amendment 0001 - IFB 70Z08824R0000001_MAINTENANCE DREDGING AT STA HUMBOLDT.pdf PDF
APPENDIX A-SF1442-24R0000001_StaMooringBallastPt- Dredging.pdf PDF
APPENDIX B1-PERMITS_StaMooringBallastPt- Dredging.pdf PDF
Amendment 0001 - IFB 70Z08824R0000001_MAINTENANCE DREDGING AT STA HUMBOLDT.pdf PDF
APPENDIX B4-MAP_StaMooringBallastPt- Dredging.pdf PDF
APPENDIX B2-HYDRO SURVEY_StaMooringBallastPt- Dredging.pdf PDF
APPENDIX E-Contractor Responsibility.pdf PDF
APPENDIX B3-DRAWINGS_StaMooringBallastPt- Dredging.pdf PDF
IFB 70Z08824R0000001_MTC DREDGING AT USCG MOORING BALLAST PT.pdf PDF
APPENDIX F-Clarification Request Form.docx DOCX document
APPENDIX C-SPECIFICATIONS_StaMooringBallastPt- Dredging_11Oc123.pdf PDF
APPENDIX D-WAGE DETERMINATION_ CA20230001-San Diego-06Oct2023.pdf PDF
APPENDIX G-CERT OF AUTHORIZATION TO BIND CORPORATION FAR 4.pdf PDF
Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. CONTRACT ID CODE PAGE OF PAGES

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1 3

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)

0002 11/16/2023 51290PR240000001 10229158

6. ISSUED BY CODE 51290 7. ADMINISTERED BY (If other than Item 6) CODE

Commanding Officer

CG CEU OAKLAND (CN)

1301 Clay Street 7th Floor, Suite 700N Oakland, CA 94612-5203

Commanding Officer

CG CEU OAKLAND (CN)

1301 Clay Street 7th Floor, Suite 700N Oakland, CA 94612-5203

8. NAME AND ADDRESS OF CONTRACTOR (No. Street, county, State and ZIP: Code) () 9A. AMENDMENT OF SOLICITATION NO.

X IFB 70Z08824R0000001

9B. DATED (SEE ITEM 11)

11/06/2023

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers: is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing Items 8 and 15, and returning one (1) copy of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATA SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and data specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

() A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT/ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.)

SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER: Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return 1 copy to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

IFB 70Z08824R0000001-MAINTENANCE DREDGING AT MOORINGS BALLAST POINT - SAN DIEGO, CA

The purpose of this Amendment No. 0002 is to provide answers to RFI Numbers 2-5 on the following page(s).

Except at provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

Travis Cohen Contracting Officer

15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED

(Signature of person authorized to sign)

BY

(Signature of Contracting Officer)

NSN 7540-01-152-8070 30-105 STANDARD FORM 30 (REV. 10-83)

PREVIOUS EDITION UNUSABLE COMPUTER GENERATED Prescribed by

IFB 70Z08824R0000001

MAINTENANCE DREDGING AT MOORINGS BALLAST POINT

RFIs 2-5

Question 2:

Reference Appendix B2-Survey: It is requested that the electronic xyz files from the most recent survey be provided for review.

Response 2:

Separately attached to this Amendment No. 2 are 2 (two) separate files with the most recent surveys.

One of which is a normal “PDF” file. NOTE: The other file is a “Zipped” CAD specific which you must have a WIN-ZIP type and CAD applications installed to open & view.

Question 3:

Reference Appendix B4-Map: Will the Contractor be required to dredge within the footprint of the

Naval Base Point Loma’s security barrier? The location of the barrier moves in and out with the currents, so the location of this barrier is variable.

Response 3:

The Navy security barrier will not be within the dredge footprint at any time during the planned event.

Question 4:

Reference Specifications 01 10 00-General Paragraphs, 1.10-Continuity of Facilities Operation, Endangered Species Act Section 7(a)(2) Concurrence Letter:

Please clarify the allowable timeframe (hours) to dredge. There is different information within the specifications and permits.

“Appendix C - Specifications

DIVISION 01 - GENERAL REQUIREMENTS

01 10 00 - GENERAL PARAGRAPHS

1.10 CONTINUITY OF FACILITIES OPERATION:

Schedule work to minimize interference with the normal operations at the facility. Notify the Contracting Officer and site contact 3 business days in advance of any shutdowns. Perform all on-site work, including deliveries, between the hours of 7:00 AM and 5:00 PM, Monday through Friday (Federal Holidays excluded), unless otherwise approved by the Contracting Officer and the Unit Commanding Officer.

Appendix B-1 Permits Endangered Species Act Section 7(a)(2) Concurrence Letter and Magnuson-Stevens Fishery

Conservation and Management Act Essential Fish Habitat Conservation Recommendations for Maintenance Dredging at United States Coast Guard Mooring Station Ballast Point.

Proposed Action and Action Area “…Per telephone discussion between NMFS, the USCG, and Wood PLC’s POC, dredging activities may be conducted up to 24 hours per day; however, this is unlikely, but will ultimately be determined once a contractor is selected.”

Response 4:

There is a requirement for a biological monitor for the GST per ESA requirements. That monitoring can only be done during daylight hours and therefore they are limited to daylight hours.

Question 5:

IFB Section I-Contract Clauses: Please provide liquidated damage information – they were not included in the FAR contract clause section.

Response 5:

The Contractor is required to complete all work during the “in-water” work period from 16Sep2023 through 31March2024. All work must be completed by 31March2024. Liquidated Damages do not apply to this Contract.

- END -