This document is a detailed specification for the dockside repair of the USCGC CALHOUN (WMSL-418), a National Security Cutter, for Fiscal Year 2025. The specification outlines 16 specific work items that comprehensively address various ship system maintenance and modification requirements, including inspections, repairs, and replacements for critical shipboard systems such as the cargo handling elevator, davits, folding boom cranes, reverse osmosis systems, fire detection systems, ballast tanks, seawater piping, main propulsion diesel engine, and steering systems.

The work items are comprehensive and technically complex, requiring specialized technical representatives from original equipment manufacturers for many tasks. The repair will involve detailed inspections, replacement of components, system modifications, preservation treatments, and operational testing across multiple ship systems. Critical aspects include renewing flexible hoses, cleaning and inspecting tanks, modifying auxiliary seawater piping, preserving deck coverings, servicing the steering system, and maintaining fire prevention protocols. The specification is associated with Federal Contract Opportunity 70Z08525RLREP0011, issued by the Department of Homeland Security US Coast Guard, with the overall goal of maintaining the operational readiness and structural integrity of the USCGC CALHOUN.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USCGC CALHOUN (WMSL 759)

SPECIFICATION FOR DOCKSIDE REPAIRS

FY2025

(Rev-2, 20 May 2025)

USCGC CALHOUN (WMSL-418) DOCKSIDE AVAILABILITY FY2025

ii (Rev-2)

TABLE OF CONTENTS

Revisions Record ......................................................................................................................................... iii Consolidated List of References ................................................................................................................... iv Consolidated List of Government-furnished Property .............................................................................. viii Consolidated List of Critical Inspection Items .............................................................................................. x Principal Characteristics ............................................................................................................................... xi General Requirements WORK ITEM 1: Cargo Handling Elevator, Annual Inspection and Test, Perform WORK ITEM 2: Dual Point Davit, Biennial Maintenance, Perform WORK ITEM 3: Folding Boom Cranes, Biennial Maintenance, Perform WORK ITEM 4: Reverse Osmosis, System Groom WORK ITEM 5: Reverse Osmosis Flexible Hoses, Renew WORK ITEM 6: Deck Covering (Slip-Resistant) Flight Deck, Renew WORK ITEM 7: Tenting (Flight Deck), Provide WORK ITEM 8: Fire Detection System, Inspect and Test WORK ITEM 9: Tanks (Ballast), Clean and Inspect WORK ITEM 10: Tanks (Ballast), Preserve (100%) - OPTIONAL WORK ITEM 11: Tanks (Ballast), Preserve (Partial) - OPTIONAL WORK ITEM 12: Tanks (MP Fuel Service), Clean and Inspect WORK ITEM 13: TCTO - Auxiliary Seawater Piping, Modify WORK ITEM 14: TCTO - Main Propulsion Diesel Engine, Condensate Drain, Modify WORK ITEM 15: Fire Prevention, Provide WORK ITEM 16: Steering System, Inspect and Service iii (Rev-2)

REVISIONS RECORD

This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.

DATE REV# WORK

ITEM#

CHANGES MADE

15MAY25 1 16 Added Work Item 16 – Steering System, Inspect and Service

20MAY25 2 14 DESCOPE Work Item 14 – TCTO – Main Propulsion Diesel Engine, Condensate Drain, Modify

NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.

iv (Rev-2)

CONSOLIDATED LIST OF REFERENCES

The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at the time of specification writing and during contract execution.

All Coast guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – from links located on the SFLC website. Commercial sites provide access to their respective documents.

COAST GUARD DRAWINGS

Coast Guard Drawing 418A-WMSL 801-001, Rev A, Booklet of General Plans Coast Guard Drawing 418A-WMSL-100-001, Rev B, General Arrangements Coast Guard Drawing 418A-WMSL-100-006, Rev A, Inboard and Outboard Profiles Coast Guard Drawing 418A-WMSL-101-001, Rev B, Compartment & Access Drawing Coast Guard Drawing 418A-WMSL-437-001, Rev B, Electrical Flowmeter Installation Auxiliary

Seawater Coast Guard Drawing 418A-WMSL-801-021 Rev A, Booklet of General Plans Coast Guard Drawing 750 WMSL-520-001, Rev H, Seawater Cooling System Diagram Coast Guard Drawing 750-WMSL-085-052, Rev B, Tank Sounding and Moment of Inertia Tables

(ASC085014K) (WMSL 759 Only) Coast Guard Drawing 750-WMSL-100-039, Rev M, Unit 3140 Structure Mn Dk to 01 Lvl - Fr 64 to Fr

76 (ASC100314)

Coast Guard Drawing 750-WMSL-100-040, Rev M, Unit 3210 Structure – Inner Bottom to 1st Platform –

Fr 76 to Fr 88 (ASC100321) Coast Guard Drawing 750-WMSL-100-043, Rev L, Unit 3240 - Main Deck to 01 Level - Fr 76 to Fr 82

(ASC100324)

Coast Guard Drawing 750-WMSL-100-089, Rev A, Topside Configuration for NSC 8 and Follow

(AS8100004)

Coast Guard Drawing 750-WMSL-100-036, Rev N, Unit 3110 Structure 1st Platform and Below Frs 65-

77 (ASC100311)

Coast Guard Drawing 750-WMSL-114-004, Rev B, Stern Tube Bossing and Shaft Handling Padeyes

(ASC114007)

Coast Guard Drawing 750-WMSL-114-009, Rev A, Rudder and Appendages Drawing (ASC114006E) Coast Guard Drawing 750-WMSL-167-001, Rev J, Manhole List Installation and Fabrication Details Ship

Wide (ASC167001) Coast Guard Drawing 750-WMSL-320-579, Rev -, Electrical Installations Iwo New Aft Folding Cranes Coast Guard Drawing 750-WMSL-436-011, Rev E, Fire Detection Sys Deck Plan (ASC436009) Coast Guard Drawing 750-WMSL-436-013, Rev C, Fire Detection Sys Cable Running Sheets

(ASC436010)

Coast Guard Drawing 750-WMSL-436-014, Rev -, Fire Detection and Control System Schematic

(ASC436028)

v (Rev-2)

Coast Guard Drawing 750-WMSL-485-001, Rev L, Sleeves-Pipe Structure Penetration Coast Guard Drawing 750-WMSL-500-002, Rev E, Resilient Hanger Details & Installation Coast Guard Drawing 750-WMSL-501-14, Rev E, Machinery Arrangements (ASC501001K) Coast Guard Drawing 750-WMSL-508-001, Rev C, Piping and Machinery Insulation Schedule and L/M Coast Guard Drawing 750-WMSL-520-001, Rev H, Seawater Cooling System Diagram (ASC52000) Coast Guard Drawing 750-WMSL-520-010, Rev G, Salt Water Cooling System Unit 2310 Coast Guard Drawing 750-WMSL-520-011, Rev F, Salt Water Cooling Unit 2320 Coast Guard Drawing 750-WMSL-520-016, Rev D, Salt Water Cooling Unit 3130 Coast Guard Drawing 750-WMSL-520-019, Rev B, Salt Water Cooling Unit 3330 Coast Guard Drawing 750-WMSL-520-507, Rev G, Auxiliary Seawater Piping Mods AFT of FR 52 Coast Guard Drawing 750-WMSL-530-001, Rev G, Potable Water Systems Diagram Coast Guard Drawing 750-WMSL-530-019, Rev E, Potable Water Unit 3120 Coast Guard Drawing 750-WMSL-556-22, Rev H, Steering Gear and Stern Gate Hydraulic Piping - Unit

3330 (ASC556333-HY)

Coast Guard Drawing 750-WMSL-556-43, Rev -, Steering Gear Hydraulic Diagram WMSL 752

ONLY(ASC556003)

Coast Guard Drawing 750-WMSL-561-001, Rev D, Steering Gear Foundation (ASC561001) Coast Guard Drawing 750-WMSL-562-002, Rev C, Rudder (ASC562002) Coast Guard Drawing 750-WMSL-562-003, Rev D, Rudder Support System (ASC562003) Coast Guard Drawing 750-WMSL-572-002, Rev D, Elevator Arr & Instl (ASC572002) Coast Guard Drawing 750-WMSL-583-508, Rev -, Installations IWO Aft Folding Cranes Coast Guard Drawing 750-WMSL-612-003, Rev C, Helo Landing Area Safety Nets & Wheel Stops Arr and Details (ASC612003) Coast Guard Fleet Drawing FL-1702-11, Rev -, Inspection of Sheaves NAVAIR Drawing 627927, Rev C, Visual Landing Aids Installation and Clearance Requirements NAVSEA Drawing 803-1385828, Rev P, Nozzles AFFF and Washdown Systems

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3D, Jan 2014, Coatings and Colors

Manual Coast Guard Technical Publication (TP) 7107, SWBS 531, 2022, Reverse Osmosis Water Purifier-

SW6994463CNG

Coast Guard Technical Publication (TP) 7108A, SWBS 573, Jan 2022, Stores Elevator - Model 20833 Coast Guard Technical Publication (TP) 7182, SWBS 561, Feb 2019, Steering Machinery Subsystem –

Operation & Maintenance Manual Coast Guard Technical Publication (TP) 7193, SWBS 561, Oct 2007, Steering System Operations and

Maintenance Manual Coast Guard Technical Publication (TP) 7903, SWBS 583, Oct 2021, Aft Boat Handling System –Model

FB90-28

Coast Guard Technical Publication (TP) 9899 SWBS 583, Apr 2021, Marine Crane – Models

DDP11000CTS & SP2200 (S/N: 2366)

Coast Guard Technical Publication (TP) 9900, SWBS 583, Apr 2021, Marine Crane – Models

DDP11000CTS & SP2200 – S/N 2382

vi (Rev-2)

Coast Guard Technical Publication (TP) 9919, SWBS 436, Feb 2022, Fire and Smoke Detection System (For Hull 757)

Fire Prevention and Response Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General

Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and

Allied Processes Surface Forces Logistics Center Standard Specification 0850 (SFLC Std Spec 0850), 2022, General

Requirements for Drawing Preparation Surface Forces Logistics Center Standard Specification 3041 (SFLC Std Spec 3041), 2022, Shipboard

Electrical Cable Test Surface Forces Logistics Center Standard Specification 3042 (SFLC Std Spec 3042), 2022, Shipboard

Electrical Cable Removal, Relocation, Splice, Repair, and Installation Surface Forces Logistics Center Standard Specification 3100 (SFLC Std Spec 3100), 2022, Inspect, Test and Recondition AC Synchronous Machines In-Place Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2022, Auxiliary

Machine Systems Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), 2022, Fire

Prevention and Response Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures Surface Forces Logistics Center Standard Specification 8636 (SFLC Std Spec 8636), 2022, Temporary

Hull Accesses

OTHER REFERENCES

American Society for Nondestructive Testing (ASNT), Recommended Practice No. SNT-TC-1A, 2020, Personnel Qualification and Certification in Nondestructive Testing American Society for Nondestructive Testing (ASNT), Standard No. ANSI/ASNT CP-189-2020, 2020, ASNT Standard for Qualification and Certification of Nondestructive Testing Personnel American Society of Mechanical Engineers (ASME) A17.2, Guide for the Inspection of Elevators, Escalators and Moving Walks.

ANSI/EASA Standard AR100-2020, Recommended Practice for the Repair of Rotating Electrical

Apparatus ASTM International (ASTM) A53, July 2020, Standard Specification for Pipe, Steel, Black and Hot-

Dipped, Zinc-Coated Welded and Seamless ASTM International (ASTM) F683, Aug 2014, Standard Practice for Selection and Application of

Thermal Insulation for Piping and Machinery ASTM Internationals (ASTM) G46, 2018, Standard Guide for Examination and Evaluation of Pitting

Corrosion Code of Federal Regulations (CFR) Title 29, Part 1910, 2017, Occupational Safety and Health Standards Code of Federal Regulations (CFR) Title 29, Part 1915, 2013, Occupational Safety and Health Standards for Shipyard Employment Code of Federal Regulations (CFR) Title 40, 2013, Protection of the Environment Commercial Item Description (CID) A-A-59588B, 2012, Rubber Silicone Federal Specification (Fed Spec) HH-P-151, July 2020, Packing, Rubber-Sheet, Cloth Insert vii (Rev-2)

International Maritime Organization (IMO) International Convention for the Safety of Life At Sea (SOLAS), 2009 as amended in 2010 and 2011

International Maritime Organization (IMO) International Life Saving Appliances Code (LSA), 2010 edition

International Standard Organization (ISO) 4406, 1999, Hydraulic Fluid Power - Fluids - Method for Coding Level of Contamination by Solid Particles

MIL-A-24179, Jun 1987, Adhesive, Flexible Unicellular-Plastic Thermal Insulation MIL-C-24757, Nov 1990, Cloth, Fiberglass, Coated MIL-DTL-15024, Nov 1997, Plates, Tags and Bands for Identification of Equipment, General

Specification for MIL-DTL-24244, May 2000, Insulation Material, With Special Corrosion, Chloride, and Fluoride

Requirements MIL-DTL-32585, Aug 2017, Insulation, Thermal and Acoustic, Fibrous Glass MIL-PRF-24176C, 2020, Cement, Epoxy, Metal Repair and Hull Smoothing MIL-PRF-24667D, 2021, Coating System, Non-Skid, for Roll, Spray, or Self-Adhering Application MIL-STD-419, Jul 1987, Cleaning and Protecting Piping Tubing, And Fittings for Hydraulic Power

Transmission Equipment MIL-STD-1689A, 1990, Fabrication, Welding, and Inspection of Ships Structure MIL-Y-1140, Sep 1985, Yarn, Cord, Sleeving, Cloth, And Tape- Glass National Fire Protection Association (NFPA) 72, 2022 Edition, National Fire Alarm and Signaling Code Naval Air Systems Command (NAVAIR) SI-ACS-AFB-1P, 2020, Air Capable Ship Aviation Facility

Certification No. 1P Naval Sea Systems Command (NAVSEA) 0640-LP-119-0175, 2019, NAVSEA OP 4 Rev 12, Ammunition and Explosives Safety Afloat NAVSEA Technical Publication T9074-AD-GIB-010/1688, (TP 1688), July 2012, Requirements for

Fabrication, Welding, and Inspection of Submarine Structure Society of Automotive Engineers (SAE) J1942-1, 2008, Qualified Hoses for Marine Applications The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2020, Bare Metal Power Tool Cleaning The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation

Standard SSPC-SP 10 (WAB)/NACE WAB-2, 2015, Near-White Metal Wet Abrasive Blast Cleaning viii (Rev-2)

CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY

The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.

WORK

ITEM

MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED

COST

($/UNIT)

2 Y CB-OTH Mark IV

(Coast Guard Drawing

26B-CB-IV-801-001)

N/A 1 ea. N/A

2 Y Hook Model APR-356-CBH 2 ea. 5000.00 3 Y *CB-OTH Mark IV

(Coast Guard Drawing

26B-CB-IV-801-001)

N/A 1 ea. N/A

3 Y *Long Range Interceptor II (LRI-II)

Cutter Boat (Coast Guard Drawing 35-

LRI-II-801-001)

N/A 1 ea. N/A

4 N Brominator filter cartridge**

PN: MI160102 2 ea. 1,000.00

13 N Strainer 6 Inch IPS, Duplex Basket, Class 150 FF Flanged Ends, Monel Basket 1/8 Inch

Penetration, Manufactured by

Hayward Company

NSN: 4730-01-4332-577 1 52,977

13 N Strainer 4 Inch IPS, Duplex Basket, Class 150 FF Flanged Ends, Monel Basket 1/8 Inch

Penetration, Manufactured by

Hayward Company

PN: ST053040BF11TS 1 23,755

13 N Strainer 2 Inch IPS, Duplex Basket, Class 150 FF Flanged Ends, Monel Basket 1/16 Inch Penetration, Manufactured by

Hayward Company

PN: ST053020BF11TS 1 11,063

13 N Strainer 1-1/2 Inch IPS, Duplex Basket, Class 150 FF Flanged Ends, Monel Basket 1/16 Inch Penetration, Manufactured by

Hayward Company

PN: ST053015BF11TS 2 7,445

ix (Rev-2)

16 N Kongsberg Spare Part Kit

PN:

RRM000445315 NIIN:016990680

1 23,929.00

16 N Kongsberg Seal Kit PN: RRM00044570 NIIN:

016990654

1 1861.16

16 N Heat exchangers PN:2336B009 NIIN 016017921

3 2,000

*Government-loaned property, which shall be returned to the vessel upon completion of the availability.

**New or refurbished equipment that the Government may provide for installation in place of existing equipment.

***Government-furnished property, which is to be supplied by either the vessel or the C4IT ServiceCenter x (Rev-2)

CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS

The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5 (Inspection report particulars)):

Work Item Title

2 Dual Point Davit, Biennial Maintenance, Perform

3 Folding Boom Cranes, Biennial Maintenance, Perform

4 Reverse Osmosis, System Groom

5 Reverse Osmosis Flexible Hoses, Renew

6 Deck Covering (Slip-Resistant) Flight Deck, Renew

7 Tenting (Flight Deck), Provide

8 Fire Detection System, Inspect and Test

9 Tanks (Ballast), Clean and Inspect

13 Auxiliary Seawater Piping, Modify xi (Rev-2)

PRINCIPAL CHARACTERISTICS

418' WMSL

PHYSICAL

Length overall 418' 0" Length between perpendiculars 390' 0" Maximum beam 54' 0" Beam @ 01 level 47' 9-1/8" Depth (01 level @ side to baseline) 39' 2-3/4" 01 deck camber foredeck 1/4" in 1'-0" Minimum berth depth 20' 0" Height of highest projection Approximately 119' Draft, design 14.40' Design displacement 3925 long tons

MACHINERY

Two diesel engines MTU 20V, 20-cylinder 9,730 SHP each One gas turbine General Electric LM2500; 29,500 SHP Type of propulsion CODAG Electrical system 24 Volt DC Two controllable pitch propellers Rolls-Royce 5 blade, 14' 0" diameter; 229 RPM max Two reduction gears RENK One cross connect gear RENK

HULL

Hull material 5086 Aluminum HSLA-80 Steel ABS EH 36 Steel

ABS AH 36

Frame spacing FWD of FR 9 2' 3" FR 9 to FR 10 6' 9" FR 10 to FR 98 4' 1" FR 98 to FR 99 3'-8"

ELECTRICAL

Power Three 1360 kW, 450 V, 60 Hz, 3 Phase, 1800 RPM Caterpillar 3512B diesel engines with Baylor ship service generators Shore tie cable Seven MIL-C-24368/2 (NATO) shore power receptacles, 400 A each

TANK CAPACITIES

Diesel oil 220,359 gal Fresh water 12,454 gal JP-5 Fuel 35,182 gal

1 (Rev-2)

00000_0824_FLT

REC_00000_FLT_Commercial Project @ CG Facility (0121)

General Requirements

1. SCOPE

1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed by commercial contractors at a Coast Guard facility for Coast Guard vessels.

1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'Base Charleston', 'shipyard', 'Base', and 'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.

2. REFERENCES

COAST GUARD DRAWINGS

None

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3D, Jan 2014, Coatings and Colors

Manual Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General

Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and

Allied Processes Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), 2022, Fire

Prevention and Response Fire Prevention and Response Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures

OTHER REFERENCES

Code of Federal Regulations (CFR) Title 29, Part 1915, 2013, Occupational Safety and Health Standards for Shipyard Employment NAVSEA Technical Publication T9074-AD-GIB-010/1688, (TP 1688), July 2012, Requirements for

Fabrication, Welding, and Inspection of Submarine Structure

2 (Rev-2)

3. REQUIREMENTS

3.1 General. The Contractor must conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability. The requirement in this WI applies to all work under the scope of this contract, whether explicitly stated in all following work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.

3.1.1 The Contractor must conform to all requirements specified in SFLC Std Spec 5550 and in the Fire Protection and Response work item, as applicable, during the performance of this availability.

3.1.1.1 Fire Safety Plan submission. The Contractor must submit a copy of the CFR 1915, Subpart P, Fire Safety Plan with the Contractor’s bid when work will be conducted in a Contractor–owned facility. Include any MOA(s) with local firefighting facilities.

3.1.1.2 Fire Plan submission. The Contractor must submit a copy of the developed availability specific fire plan, as requested in the Fire Protection and Response work item, seven (7) days before the Arrival Conference.

NOTE

NAVSEA drawings listed will be available FOR INSPECTION ONLY from the Coast Guard Port Engineer post-award. SFLC will not redistribute NAVSEA documents.

Contractors can apply to NAVSEA headquarters directly for copies.

3.2 Contractor-provided fire watch personnel. The Contractor must provide fire watch personnel and equipment.

3.3 Preservation requirements. The Contractor must accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.

3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec 6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).

3.3.2 Coating colors and system color schemes. The Contractor must obtain a written KO authorization to deviate from any coatings required in SFLC Std Spec 6310 Appendix C before work.

3.3.3 In-process quality control measures. The Contractor must abide by all the safety, preservation, and quality control requirements specified in SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces”).

3.3.3.1 Quality control requirements. The Contractor must abide by the following when performing preservation related inspections. The following measurements must be randomly spaced throughout for the purposes of providing a representation of the entire prepared or coated surface.

3.3.3.1.1 Surface profile measurements. One surface profile measurement must be taken for every 200 square feet for the first 1000 square feet; for each additional 500 square feet or less, one profile measurement must be taken.

Profile measurements must be taken in accordance with SFLC Std Spec 6310, paragraph 3.1.8.3 (Surface profile measurements). A “measurement” for surface profile is defined as follows:

• ASTM D4417, Method B: One profile measurement is the average (mean) of 10 individual readings.

• ASTM D4417, Method C: One profile measurement is the average (mean) of 2 individual readings.

3.3.3.1.2 Soluble salt conductivity measurements. 5 conductivity measurements must be taken every 1000 square feet. For submerged (immersed) applications conductivity measurements must not exceed 30 microsiemens/cm.

3 (Rev-2)

For non-submerged (non-immersed) applications conductivity measurements must not exceed 70 microsiemens/cm. If a conductivity check fails, clean the surface in accordance with SFLC Std Spec 6310, paragraph 3.1.8.5 (Soluble salt removal).

3.3.3.1.3 Coating thickness measurements. Three area measurements must be taken for the first 1000 square feet;

for each additional 1000 square feet, perform an additional area measurement. A “measurement” for coating thickness is defined as follows:

• SSPC-PA 2 defines an area measurement as 5 separate spot measurements randomly spaced throughout a 100 square foot area.

• SSPC-PA 2 defines a spot measurement as 3 gage readings and each new gage reading the probe must be moved to a new location within a 1.5-inch diameter circle defining the spot.

3.4 Welding and brazing requirements. The Contractor must perform all welding and allied processes, and NDE in accordance with SFLC Std Spec 0740.

3.4.1 HY-130 material substitution. The Contractor must be aware that HY-130 steel plating is no longer commercially available. For the purpose of performing flight deck repairs on US Coast Guard WMEC-270 “B- Class” cutters, Weldox 900 steel plating has been approved as a replacement for HY-130. Due to the similarity in material properties and weldability of HY-130 and Weldox 900, all welding procedures and welder qualifications for welding Weldox 900 must be the same as those outlined in NAVSEA TP 1688 as applicable for welding HY- 130.

3.4.2 Standard spec modification. For any welding involving HY-130 on the flight deck of WMEC-270 “B-Class” cutters, perform all welding and allied processes, and non-destructive evaluation (NDE) in accordance with NAVSEA TP 1688. The Contractor must be aware that the welding requirements specified in this document take precedence over paragraph 3.3.6 of SFLC Standard Spec 0000 for the purpose of welding involving HY-130.

3.4.3 Approval to weld HY-130. To obtain Coast Guard approval to weld on HY-130 steel for WMEC-270 “B- Class” cutters, the Contractor must provide written Performance Qualification Records (PQR’s) for each process to be used. The PQR’s must be approved by one of the regulatory agencies affirming that the WPS meets the welding requirements of NAVSEA TP 1688. In addition, the Contractor must ensure that all subcontractors, prior to performing welding operations, have qualified procedures by meeting all the requirements set forth in this document.

NOTE

NAVSEA approval is NOT required for welding procedures submitted but the procedures must be reviewed and shown to satisfy the requirements set forth in NAVSEA TP 1688, by a welding regulatory agency. The requirements for welding Weldox 900 are considered the same as those for welding HY-130.

3.5 Environmental protection requirements. The Contractor must adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:

3.5.1 USCG facilities. The Contractor must provide and maintain environmental protection as defined in SFLC Std Spec 0000 Appendix B, Requirements for Environmental Protection at USCG Facilities, during the performance of this availability. Contractor must plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor must comply with applicable Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific

4 (Rev-2) portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item must not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.

3.5.1.1 USCG Generator status. The EPA ID for the Coast Guard facility is SCR000005389. This number can only be used to for the generator status. The transporter and designated facility must have their own EPA ID numbers and cannot use this one.

3.5.1.2 Plans and permits. The CG Facility has unit specific permits including the following:

• Spill Prevention Control and Countermeasures (SPCC) Plan: Unit has a SPCC Plan which requires certain unit-specific procedures be followed for the storage, inspection, and transfer of petroleum products in containers 55 gallons or greater.

3.5.2 Test and procedures. The Contractor is required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work must be done by qualified laboratories; and where required by law, the laboratories must be certified.

3.5.3 Regulatory notifications. The Contractor is responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The Contractor must submit copies of all regulatory notifications to the Contracting Officer and the local Facility Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications must be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System (NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.

3.5.4 Environmental manager. The Contractor must appoint in writing an Environmental Manager for the project, who is responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager must ensure compliance with Hazardous Waste Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the Contractors’ Environmental Management Plan; ensure that all environmental permits are obtained, maintained, and closed out;

ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas; ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the Environmental Records binder and required documentation, including environmental permits compliance and close-out.

3.5.5 HW disposal. Contractor must comply with SFLC Std Spec 0000 Appendix B, Requirements For Environmental Protection At USCG Facilities for HW disposal, and ensure that waste removals are conducted during normal business hours (0800-1600) on Monday through Friday (excluding holidays).

3.5.6 Additional Requirements. The Contractor must be aware of the following:

3.5.6.1 No Contractor or Subcontractor must have the authority to sign a Hazardous Waste Manifest using the Coast Guard facility’s EPA Generator ID Number or remove contract generated hazardous waste from the Coast Guard facility without COR or KO-approval.

3.5.6.2 Local environmental regulations at the Government facilities may be more stringent. As with all

5 (Rev-2) environmental regulations, the Contractor must prepare for and comply with local and state regulations.

3.5.6.3 Coast Guard facilities do not maintain Facilities Response Plans (FRPs) per 33 CFR 154. Contractor must furnish the FRP when required for over-the-water liquids transfers to and from vessels, and is required for oil/fuel transfers to/from vessels for 250 barrels (10,500 gallons) or more.

3.6 Local Policy. The Contractor must refer to site (e.g., Base) Regulations and Instructions for details regarding local policies (e.g., crane services, parking, or facility usage).

3.7 SFLC Standard Specification approved changes. Approved updates to the 2022 SFLC Standard Specifications will appear here.

4. NOTES

4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.

6 (Rev-2)

QA-1 - QUALITY ASSURANCE INSPECTION FORM

(PRESERVATION CHECKLIST)

VESSEL NAME HULL # WORK

ITEM #

WORK ITEM TITLE

LOCATION OF WORK (INCL. FRAME #’S) AREA (SQFT)

CHECKPOINT 1 – COATING SYSTEM COMPLIANCE

Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.

CHECKPOINT 2 - PAINT STORAGE

Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfg.

CHECKPOINT 3 - AMBIENT CONDITIONS

Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).

Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).

Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfg.

CHECKPOINT 4 - PRE-SURFACE PREPARATION

Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.

Verify equipment setup, blast media, and surface preparation methods match designated test coupon.

CHECKPOINT 5 - SURFACE PREPARATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).

Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.

Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).

CHECKPOINT 6 - PRIMER COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Verify proper mixing and stand-in (induction) times.

Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.

Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).

Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.

Brush out all runs, sags, drips, and puddles.

Perform visual inspection for holidays and other defects.

CHECKPOINT 7 – STRIPE COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).

CHECKPOINT 8 – TOP COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

Verify proper mixing and stand-in (induction) times, as applicable.

Verify wet film thickness at random, to prevent under or over application.

Brush out all runs, sags, drips, and puddles.

CHECKPOINT 9 – FINAL INSPECTION

Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.

Ensure that system cure is in accordance with manufacturer's recommendation for intended service.

Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.

For immersion coatings (including tank U/W body), record date and time of the following events:

Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____

CHECKPOINT 10 – RECORD KEEPING

Complete, sign, and submit all provided QA Inspection Forms.

NAME OF QP-1/AMPP INSPECTOR SIGNATURE CERT. # DATE / TIME

NAME OF CG REPRESENTATIVE SIGNATURE UNIT DATE/TIME

7 (Rev-2)

QA-2 - QUALITY ASSURANCE INSPECTION FORM

(ENVIRONMENTAL READINGS)

VESSEL NAME HULL # WORK

ITEM # WORK ITEM TITLE

Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.

DATE

TIME

ACTIVITY (SURFACE

PREPARATION, PRIMER

COAT, BARRIER COAT, TOP

COAT, ETC…)

LOCATION (FRAME &

DECK, RELATION TO

EQUIPMENT, ETC.)

TEMPERATURE % REL.

HUMID-

ITY

DEW

PT.

SURFAC

E

AMBIEN

T

ΔT

| DP -

SURFACE |

8 (Rev-2)

QA-3a - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)

VESSEL NAME HULL # WORK ITEM

LOCATION OF WORK (FRAME REFERENCES) AREA (SQFT)

SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)

MIN MAX MEAN

SSPC-SP-10/AMPP No. 2

SSPC-SP WJ-2/AMPP WJ-2

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)

ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:

PLACE SURFACE PROFILE REPLICA TAPES IN THE SPACES PROVIDED BELOW, TO SERVE AS

PERMANENT QA RECORD. MAINTAIN A SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS

DIVIDED INTO SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

MEAN MIL READING (IAW ASTM D4417-METHOD C) FOR ABOVE 15 READINGS:

NAME OF QP-1/AMPP INSPECTOR SIGNATURE CERT. # DATE /

TIME

9 (Rev-2)

QA-3b - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)

VESSEL NAME HULL # WORK ITEM

SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)

MIN MAX MEAN

SSPC-SP-10/AMPP No. 2

SSPC-SP WJ-2/AMPP WJ-2

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)

ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:

RECORD MEASUREMENTS TAKEN IN THE SPACES PROVIDED BELOW, TO SERVE AS PERMANENT

QA RECORD. MAINTAIN SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS DIVIDED INTO

SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Mean Mils Reading (IAW ASTM D4417-Method B for above 10 readings (by column):

Mean Reading (mils)

10 (Rev-2)

QA-4 - QUALITY ASSURANCE INSPECTION FORM

(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)

VESSEL NAME HULL # WORK

ITEM #

SOLUBLE SALT CONDUCTIVITY MEASUREMENTS IAW SSPC-GUIDE 15.

DATE TEST LOCATIONS CONDUCTIVITY (MICROSIEMENS/CM)

11 (Rev-2)

QA-5 - QUALITY ASSURANCE DATA FORM

(COATING THICKNESS)

(Use one sheet for each sequence)

VESSEL NAME HULL # WORK ITEM

# WORK ITEM TITLE

COATING MFG PRODUCT NAME BATC

H #

INDUCTI

ON TIME

COATING SYSTEM

SEQUENCE

(PRIMER/TOUCHUP/3RD

COAT, ETC.)

DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC-PA 2.

SPOT 1 2 3 4 5 AVERAGE

VALUE

*BASE METAL READING

(BMR)

*Required, If Magnetic Pull-Off (Type I/Banana) Gauge Is Used.

LOCATION (FRAME REFERENCE):

SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS

1 AVG. BMR DEVIATION

3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS

AVG.

LOCATION (FRAME REFERENCE):

SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS

1 AVG. BMR DEVIATION

3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS

AVG.

LOCATION (FRAME REFERENCE):

SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS

1 AVG. BMR DEVIATION

3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS

AVG.

APPLICATION METHOD (AIRLESS,

CONVENTIONAL SPRAY, ROLLED)

AVERAGE DFT

12 (Rev-2)

4.2 Tank and Void Assessment form.

13 (Rev-2)

14 (Rev-2)

57301_RTK_0323_418

WORK ITEM 1: Cargo Handling Elevator, Annual Inspection and Test, Perform

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to inspect and perform annual preventive maintenance on the cargo handling elevator.

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 750-WMSL-572-002, Rev D, Elevator Arr & Instl (ASC572002)

COAST GUARD PUBLICATIONS

Coast Guard Technical Publication (TP) 7108A, SWBS 573, Jan 2022, Stores Elevator - Model

20833 Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements Surface Forces Logistics Center Standard Specification 3042 (SFLC Std Spec 3042), 2022, Shipboard Electrical Cable Removal, Relocation, Splice, Repair, And Installation Surface Forces Logistics Center Standard Specification 3100 (SFLC Std Spec 3100), 2022, Inspect, Test and Recondition AC Synchronous Machines In-Place Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2022, Auxiliary Machine Systems Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures

OTHER REFERENCES

American Society of Mechanical Engineers (ASME) A17.2, Guide for the Inspection of

Elevators, Escalators and Moving Walks.

3. REQUIREMENTS

3.1 General.

15 (Rev-2)

3.1.1 CIR.

None.

3.1.2 Tech Rep. The Contractor must provide the services of a qualified Tech Rep, who is familiar with the Jered Industries Cargo Elevator (i.e. Model 20833) to accomplish the following, on site:

• Advise on manufacturer's proprietary information pertinent to the system.

• Assist with repair and renewing the Cargo Elevator parts.

• Ensure compliance with manufacturer's procedures and standards during disassembly, inspection, and reassembly of the system.

3.1.2.1 Ensure the Tech Rep has experience with the system/equipment stated above and demonstrated on their résumé.

3.1.2.2 Submit the name and résumé of the Tech Rep to the COR at the Arrival Conference.

3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).

3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the following:

• Electrical wiring

CAUTION

See Coast Guard Technical Publication 7108A Safety summary for specific warnings and caution notes to ensure safety of personnel and equipment.

WARNING

The work and inspections specified require that the elevator doors be opened and that the inspector examine items located within the trunk. Failure to observe/implement safety precautions could result in personnel injury/death.

NOTE

Coast Guard personnel will operate all shipboard machinery and equipment.

3.2 Operational test, initial. Prior to commencement of work, the Contractor must witness Coast Guard personnel perform an initial operational test of the Jered Industries (i.e. Model 20833) cargo handling elevator to demonstrate existing operational condition. Submit a CFR.

3.3 Cargo handling elevator inspection. The Contractor must inspect the elevator mechanical and electrical components for proper condition. See Coast Guard Drawing 750-WMSL-572-002 and Coast Guard TP 7108A for elevator details, and follow the guidance in the applicable sections of ASME A17.2, Guide for the Inspection of Elevators, Escalators and Moving Walks. If components are damaged or exhibit abnormal wear, document condition and submit a CFR.

• Hoist machinery assemblies

• Doors and interlocks

• Platform assembly, rails, guides, and rollers

• Sheave Assembly

16 (Rev-2)

• Limit switches

• Level and Master control stations

• Overspeed governor and wire rope assembly

• Slack Rope assemblies

• Brake

• 90-Degree gear Reducer

3.4 Elevator wire rope inspection. The Contractor must inspect and measure the elevator wire ropes, in accordance with Coast Guard TP 7108A, paragraph 4.4.1. Ensure there is equal tension between each of the elevator wire ropes. Submit a CFR.

3.5 Overspeed governor wire rope inspection. The Contractor must inspect and measure the overspeed governor wire rope, in accordance with Coast Guard TP 7108A, paragraph 4.4.1. Adjust the tension arm as close to horizontal as possible in accordance with Coast Guard TP 7108A, Appendix C and ensure there is equal tension throughout the rope. Submit a CFR.

3.6 Gear box oil and component lubrication. The Contractor must perform the Semi-Annual Maintenance Requirements for the tension sheaves, hoist wire ropes, motor couplings, guide rails, slack rope assembly, and door fittings in accordance with Coast Guard TP 7108A, paragraph 4.2.2.

3.7 Electric motor inspection. The Contractor must take insulation resistance readings on the motor in accordance with SFLC Std Spec 3100. Disconnect and reinstall cables in accordance with SFLC Std Spec 3042. Readings must be taken with power removed from the motors. Readings must be above 2 Megaohms for continued operation. Submit a CFR.

3.8 Brake inspection. The Contractor must inspect the friction brake discs and verify proper settings of the electric brake in accordance with Appendix B of Coast Guard Tech Pub 7108A. Submit a CFR with inspection results and any recommendations for required repairs.

3.9 Hoist controller inspection. The Contractor must open the motor controller and inspect for loose wires, loose components, charred or burned components, dirt or other abnormal conditions. Submit a CFR if abnormal conditions requiring repair are observed, otherwise return motor controller to original condition.

NOTE

Coast Guard personnel will operate all shipboard machinery and equipment.

3.10 Operational test, post repairs. After completion of work, the Contractor must thoroughly test, in the presence of the Coast Guard Inspector and demonstrate all items or shipboard devices that have been disturbed, used, repaired, altered, or installed to be in satisfactory operating condition. Thoroughly test and prove all functions and safety features of the cargo handling elevator to be in a satisfactory operating condition. Submit a CFR.

3.10.1 No-load test. The Contractor must witness Coast Guard personnel operate the elevator in normal mode, and verify safety devices, emergency stop, and interlocks are properly installed and operational.

As the car travels, observe the equipment to detect any unusual noise or vibration. The motor should start immediately when the power is applied and the drum should stop within 0.5 seconds after power is removed. Carefully observe the hoist motor, bearing, and brake for any signs of overheating.

17 (Rev-2)

3.11 Touch-up preservation. The Contractor must prepare and coat all new and disturbed surfaces to match existing adjacent surfaces in accordance with SFLC Std Spec 6310, paragraph 3.1.13 (Touch-ups and minor coating repairs).

4. NOTES

This section is not applicable to this work item.

18 (Rev-2)

58300_RTK_1223_418

WORK ITEM 2: Dual Point Davit, Biennial Maintenance, Perform

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to perform Biennial Maintenance on Dual Point Davit listed in Table 1.

TABLE 1 – DUAL POINT DAVIT NAMEPLATE DATA

DESCRIPTION LOCATION DAVIT TOTAL

GROSS WEIGHT

Allied Systems Dual Point Davit with Control Console Models: DDP11000CTS & SP2200

Weather Deck, STBD Side, Frame 47 29,000 lbs

1.2 Government-furnished property.

MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED

COST ($/UNIT)

Y CB-OTH Mark IV (Coast Guard Drawing 26B-CB-IV-801-001) N/A 1 ea. N/A

Y Hook Model APR-356- CBH 2 ea. 5000.00

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 418A-WMSL-100-001, Rev B, General Arrangements Coast Guard Drawing 418A-WMSL 801-001, Rev A, Booklet of General Plans

COAST GUARD PUBLICATIONS

Coast Guard Technical Publication (TP) 9899 SWBS 583, Apr 2021, Marine Crane – Models

DDP11000CTS & SP2200 (S/N: 2366)

Coast Guard Technical Publication (TP) 9900, SWBS 583, Apr 2021, Marine Crane – Models

DDP11000CTS & SP2200 – S/N 2382

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2022, Auxiliary Machine Systems Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures

19 (Rev-2)

OTHER REFERENCES

International Maritime Organization (IMO) International Convention for the Safety of Life At

Sea (SOLAS), 2009 as amended in 2010 and 2011 International Maritime Organization (IMO) International Life Saving Appliances Code (LSA), 2010 edition ANSI/EASA Standard AR100-2020, Recommended Practice for the Repair of Rotating Electrical

Apparatus

3. REQUIREMENTS

3.1 General.

3.1.1 CIR. The Contractor must submit a CIR for the inspections listed in the following paragraph(s):

• 3.2 Biannual maintenance inspection and repair task particulars (Task #1 and #2)

• 3.2.1 Hook certification.

3.1.2 Tech Rep. The Contractor must provide the services of a Qualified Technical Representative who is familiar with the Dual Point Davit (i.e. Allied System Co. Model No. DDP11000CTS) to accomplish the following on site:

• Advise on manufacturer's proprietary system information.

• Ensure compliance with manufacturer's procedures and standards during system disassembly, inspection, repair, reassembly, and testing as applicable.

3.1.2.1 Ensure the Tech Rep has experience with the system/equipment stated above and demonstrated on their résumé.

3.1.2.2 Submit the name and résumé of the Tech Rep to the COR at the Arrival Conference.

3.1.2.3 Point of contact:

• Heath Munger

• Heath.munger@alliedsystems.com

• Allied Systems Company

• (503) 825-3366

3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).

3.1.3.1 Protection of fine surfaces. The Contractor must protect all fine surfaces in accordance with SFLC Std. Spec 5000.

3.1.3.2 Hydraulic system contamination protection. The Contractor must maintain existing hydraulic cleanliness in accordance with SFLC Std. Spec 5000.

3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the following:

20 (Rev-2)

• Piping

• Electrical Cables

• Capstan

NOTE

Coast Guard personnel will operate all shipboard machinery and equipment.

3.1.5 Operational test, initial. Prior to commencement of work, the Contractor must witness Coast Guard personnel perform an initial operational test of all items or shipboard devices to be disturbed, used, repaired, or altered, to demonstrate existing operational condition. Submit a CFR.

3.1.6 Materials. The Contractor must furnish and install parts listed in Table 2.

TABLE 2 – LIST OF PARTS

QUANTITY PART NUMBER DESCRIPTION SOURCE OF

SUPPLY

1 593533 Kit, Element Replacement

Allied System Co.

214 S.W. Oregon Street, Sherwood

OR 97140

1 593532 Kit, Element Replacement 2 70196 Return Filters 2 74130 Seal Kits 2 71975 Filter Breather 1 71754 Tank Cover Gasket 2 71042 Wire Rope 2 73441 Hub

3.2 Biannual maintenance inspection and repair task particulars. The Contractor with Tech Rep support must perform the tasks designated in Table 3 below and Figure 1 in accordance with SFLC Std Spec 5000 and CG Tech Pub as applicable.

TABLE 3 – RECURRING MAINTENANCE TASK

ADDITION…