This document is a comprehensive specification for dockside repairs for the USCGC MUNRO (WMSL 755) for Fiscal Year 2025, developed by David A. Robbins on June 4, 2025. The specification contains 16 detailed work items covering various ship systems and maintenance requirements, including cleaning and inspecting fuel tanks, renewing flexible hoses for air conditioning and oil purification systems, performing maintenance on equipment such as the cargo handling elevator, dual point davit, folding boom cranes, incinerator, sewage holding tanks, oily water separator, and reverse osmosis system, as well as installing deck drains, renewing fuel oil piping, and providing fire prevention services.
The specification provides extensive technical details for each work item, including specific components to be serviced, reference drawings, technical publications, and precise maintenance procedures. Government-furnished property is listed for several work items, and critical inspection requirements are outlined. The work is to be performed at a Coast Guard facility, with contractors required to follow detailed standard specifications for tasks such as welding, surface preservation, electrical work, and system testing. The document emphasizes compliance with Coast Guard technical publications, safety standards, and environmental regulations throughout the maintenance and repair processes.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SF30 Amendment 1 with QA.pdf | ||
| Solicitation 70Z08525QLREP0007 USCG MUNRO DS FY25.pdf | ||
| Attachment 1 Price Schedule.xlsx | XLSX spreadsheet | |
| Attachment 3 Past Performance Information Form.docx | DOCX document | |
| Attachment 2 Specification.pdf | ||
| Solicitation 70Z08525QLREP0007 USCG MUNRO DS FY25.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USCGC MUNRO (WMSL 755)
SPECIFICATION FOR DOCKSIDE REPAIRS
FY2025
Developed By: David A Robbins
(Rev-1, 04 June 2025)
USCGC MUNRO (WMSL-418) DOCKSIDE AVAILABILITY FY2025
ii (Rev-1)
TABLE OF CONTENTS
Revisions Record ...............................................................................................................................iii Consolidated List of References ..........................................................................................................iv Consolidated List of Government-furnished Property ..........................................................................vii Consolidated List of Critical Inspection Items ......................................................................................ix Principal Characteristics ...................................................................................................................... x General Requirements WORK ITEM 1: Tanks (Aviation Fuel Stowage and Overflow), Clean and Inspect WORK ITEM 2: Tanks (MP Fuel Service), Clean and Inspect WORK ITEM 3: Air Conditioning Units Flex Hoses And Expansion Joints, Renew WORK ITEM 4: Fuel Oil Purifier Flexible Hoses, Renew WORK ITEM 5: Lube Oil Purifier Flexible Hoses, Renew WORK ITEM 6: Cargo Handling Elevator, Inspect and Repair WORK ITEM 7: Dual Point Davit, Biennial Maintenance, Perform WORK ITEM 8: Stern Boat Launch and Recovery, Level II Inspect and Repair WORK ITEM 9: Folding Boom Cranes, Biennial Maintenance, Perform WORK ITEM 10: Incinerator, Inspect and Test WORK ITEM 11: Sewage Holding Tank(s), Clean and Inspect WORK ITEM 12: Oily Water Separator (OWS) System, Inspect and Groom WORK ITEM 13: Reverse Osmosis, System Groom WORK ITEM 14: Deck Drain, Install WORK ITEM 15: Fuel Oil Piping, Renew WORK ITEM 16: Fire Prevention, Provide iii (Rev-1)
REVISIONS RECORD
This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-1) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.
DATE
REV# WORK
ITEM#
CHANGES MADE
6/4/2025 1 8 CIR added to the consolidated list of critical inspection items
6/4/2025 1 8 Updated multiple sections in Para 3.7 Remove the Port and Starboard Carriage Winches
6/4/2025 1 12 CIR 3.1.1 corrected to “none” and removed from consolidated list
6/4/2025 1 5 Table 1 provided data for hoses LOP-LO-001 & LOP-LO-002 Length 50”, Size 2”, Fitting Union
6/4/2025 1 7 3.6 Note regarding Sea Trial changed to anticipated date of
24SEP2025
NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.
iv (Rev-1)
CONSOLIDATED LIST OF REFERENCES
The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at the time of specification writing and during contract execution.
All Coast guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – from links located on the SFLC website. Commercial sites provide access to their respective documents.
COAST GUARD DRAWINGS
Coast Guard Drawing 26B-CB-OTH-IV-801-001, Rev -, Booklet of General Plans Coast Guard Drawing 35-LRI-II-801-001, Rev -, General Arrangement Coast Guard Drawing 418A-WMSL 801-001, Rev A, Booklet of General Plans Coast Guard Drawing 418A-WMSL-100-001, Rev B, General Arrangements Coast Guard Drawing 418A-WMSL-101-001, Rev B, Compartment & Access Drawing Coast Guard Drawing 418A-WMSL-526-001, Rev A, Weather Deck Drains Diagram Coast Guard Drawing 418A-WMSL-540-001, Rev C, Fuel Oil Diagram Coast Guard Drawing 418A-WMSL-540-002, Rev A, Diesel Engine and Gas Turbine LO Fill, Trans, &
Service System Coast Guard Drawing 418A-WMSL-593-001, Rev A, Bilge & Oil Pollution Control System Diagram Coast Guard Drawing 418A-WMSL-593-002, Rev B, Sewage System Diagram Coast Guard Drawing 418A-WMSL-801-001 Rev A, Booklet of General Plans Coast Guard Drawing 750-WMSL_100_43, Rev L, Unit 3240 – Main Deck To 01 Level – Fr 76 To Fr 82
(ASC100324)
Coast Guard Drawing 750-WMSL_520_001, Rev H, Seawater Cooling System (ASC520001) Coast Guard Drawing 750-WMSL-085-039, Rev -, Tank Sounding and Moment of Inertia Tables
(ASC085014F) (WMSL 755 Only) Coast Guard Drawing 750-WMSL-085-039, Rev -, Tank Sounding and Moment of Inertia Tables
(ASC085014F) (WMSL 755 Only) Coast Guard Drawing 750-WMSL-100-023, Rev J, Unit 2120 Structure – 1st Pltf to 2nd Deck Fr 35 to Fr
44 (ASC100212)
Coast Guard Drawing 750-WMSL-100-036, Rev N, Unit 3110 Structure 1st Platform and Below Frs 65-
77 (ASC100311)
Coast Guard Drawing 750-WMSL-100-083, Rev A. General Arrangements NSC 5 & Follow (AS510001) Coast Guard Drawing 750-WMSL-167-001, Rev J, Manhole List Installation and Fabrication Details Ship
Wide (ASC167001) Coast Guard Drawing 750-WMSL-300-024, Rev C, Unit 2240 - Main Dk Fr 44 to Fr 52 Arr of Elect Eqpt
(ASC300224)
Coast Guard Drawing 750-WMSL-320-039, Rev D. Electrical One-Line Diagram (NSC2 – SRD)
(ASC320001B),
v (Rev-1)
Coast Guard Drawing 750-WMSL-320-579, Rev -, Electrical Installations Iwo New Aft Folding Cranes Coast Guard Drawing 750-WMSL-505-006, Rev D, List of Hoses (ASC505006) Coast Guard Drawing 750-WMSL-516-001, Rev E, A/C & Refrigeration Piping Diagram (ASC516001) Coast Guard Drawing 750-WMSL-516-002, Rev K, Chilled Water System Diagram (ASC516002) Coast Guard Drawing 750-WMSL-516-006, Rev F, Chilled Water & Refrigeration Piping Unit 1320
(ASC516132-CW)
Coast Guard Drawing 750-WMSL-520-004, Rev E, Salt Water Cooling Unit 1320 (ASC520132-SW) Coast Guard Drawing 750-WMSL-526-504, Rev -, Gas Turbine Exhaust Space 02-49-01-Q Deck Drain
Install Coast Guard Drawing 750-WMSL-530-001, Rev G, Potable Water Systems Diagram Coast Guard Drawing 750-WMSL-530-019, Rev E, Potable Water Unit 3120 Coast Guard Drawing 750-WMSL-572-002, Rev D, Elevator Arr & Instl (ASC572002) Coast Guard Drawing 750-WMSL-583-004, Rev K, Stern Launch & Recovery Arrangement & Details
(ASC583004)
Coast Guard Drawing 750-WMSL-583-004, Stern Launch & Recovery, Arrangement & Details
(ASC583004), Rev. K Coast Guard Drawing 750-WMSL-583-508, Rev -, Installations IWO Aft Folding Cranes Coast Guard Drawing 750-WMSL-593-011, Rev B, Solid Waste System Schematic (ASC593026) Coast Guard Drawing 750-WMSL-593-027, Rev D, Sewage System Unit 2120 Coast Guard Drawing FL-1702-11, Rev -, Inspection of Sheaves
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3D, Sep 2020, Coatings and Colors
Manual Coast Guard Technical Publication (TP) 7107, SWBS 531, 2022, Reverse Osmosis Water Purifier-
SW6994463CNG
Coast Guard Technical Publication (TP) 7108A, SWBS 573, Jan 2022, Stores Elevator – Model 20833 –
Operation & Maintenance Manual Coast Guard Technical Publication (TP) 7184, SWBS 593, Jan 2022, Vacuum Sewage System –
Operation, Maintenance & Parts List Coast Guard Technical Publication (TP) 7346A, SWBS 593, Mar 2022, Bilge Water Separator Ultra-Sep Coast Guard Technical Publication (TP) 7797, SWBS 540, Nov 2017, Lube Oil Treatment Plant Model
LO
Coast Guard Technical Publication (TP) 7798, SWBS 541, Aug 2022, Fuel Oil Treatment Plant Model
DO
Coast Guard Technical Publication (TP) 7809, SWBS 583, Apr 2023, Boat Retrieval Equipment – Boat
Hoist, Centerline & Carriage Winches Coast Guard Technical Publication (TP) 7903, SWBS 583, Oct 2021, Aft Boat Handling System –Model
FB90-28
Coast Guard Technical Publication (TP) 7946, SWBS 593, May 2021, Incineration Plant - Installation, Operation, Maintenance & Spare Parts Coast Guard Technical Publication (TP) 9899 SWBS 583, Apr 2021, Marine Crane – Models
DDP11000CTS & SP2200 (S/N: 2366) (Hull 755) Surface Force Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General
Requirements vi (Rev-1)
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and Allied Processes
Surface Forces Logistics Center Standard Specification 3020 (SFLC Std Spec 3020), 2022, Overhaul AC Electrical Motors
Surface Forces Logistics Center Standard Specification 3041 (SFLC Std Spec 3041), 2022, Shipboard Electrical Cable Test
Surface Forces Logistics Center Standard Specification 3042 (SFLC Std Spec 3042), 2022, Shipboard Electrical Cable Removal, Relocation, Splice, Repair, and Installation
Surface Forces Logistics Center Standard Specification 3100 (SFLC Std Spec 3100), 2022, Inspect, Test and Recondition AC Synchronous Machines In-Place
Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2022, Auxiliary Machine Systems
Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), 2022, Fire Prevention and Response
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures
OTHER REFERENCES
American Society of Mechanical Engineers (ASME) A17.2, Guide for the Inspection of Elevators, Escalators and Moving Walks ANSI/EASA Standard AR100-2020, Recommended Practice for the Repair of Rotating Electrical
Apparatus Code of Federal Regulations (CFR) Title 29, Part 1915, Occupational Safety and Health Standards for
Shipyard Employment International Maritime Organization (IMO) International Convention for the Safety of Life At Sea
(SOLAS), 2009 as amended in 2010 and 2011 International Maritime Organization (IMO) International Life Saving Appliances Code (LSA), 2010 edition Manufacturers Standardization Society of the Valve and Fittings Industry (MSS), SP-58, 2009, Pipe
Hangers and Supports – Materials, Design, Manufacture, Selection, Application and Installation MIL-C-24757, Nov 1990, Cloth, Fiberglass, Coated NAVSEA Technical Publication T9074-AD-GIB-010/1688, (TP 1688), July 2012, Requirements for
Fabrication, Welding, and Inspection of Submarine Structure Society of Automotive Engineers J1942 (SAE J1942), March 2019, Hose and Hose Assemblies for
Marine Applications The Society for Protective Coatings (SSPC) Surface Preparation Specification No. 1 (SSPC-SP 1), 2016, Solvent Cleaning The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2020, Power Tool Cleaning to Bare Metal US Environmental Protection Agency Method 1664, Feb 1999, N-Hexane Extractable Material and Silica
Gel Treated N-Hexane Extractable Material by Extraction and Gravimetry.
vii (Rev-1)
CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY
The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.
WORK
ITEM
MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED
COST
($/UNIT)
6 N Guide Roller PN: J184796 NSN: 3990-01-
686-7227 4 ea. 2,800.00
6 N Wire Rope PN: J188017 NSN: 4140-01- 686-9981
1 ea. 2,000.00
6 N Wire Rope PN: 188005 NSN: 4010-01- 561-8614
4 ea. 702.00
6 N Proximity Level Switch
PN: 185088 NSN: 5930-01-
633-3706
2 ea. 780.00
6 N Door Interlock Switch PN: 199177 2 ea. 1,000.00 7 Y CB-OTH Mark IV
(Coast Guard Drawing
26B-CB-OTH-IV-801-
001)
N/A 1 ea. N/A
7 Y Hook: Model APR-
356-CBH
CAGE: S7651, NIIN:
014671005
2 ea. 5000.00
8 N Spring, Sheave NSN: 5360-01-672-8829 PN:
P2-965-0024
8 ea. 185.00
8 N Pins, Spring NSN: 5315-01-672-8220 PN:
B2-066-0056
8 ea. 400.00
8 N Pins, Cotter NSN: 5315-01-672-8187 PN:
81-E-0628
8 ea. 1.50
8 N Flat Washer, 2 ½ Nominal, TY A 5” OD x 2 5/8” ID x 0.238”
THK
NSN: 5310-01-672-8737 PN:
61-E-16
8 ea. 1.50
8 N Jacking Bolt, Sheave NSN: 5306-01-672-9033 PN:
B2-033-0026
8 ea. 275.00
8 Y *CB-OTH Mark IV N/A 1 ea. N/A 8 Y *Long Range
Interceptor II N/A 1 ea. N/A
9 Y *CB-OTH Mark IV (Coast Guard Drawing
26B-CB-OTH-IV-801-
001)
N/A 1 ea. N/A
9 Y *Long Range Interceptor II (LRI-II)
Cutter Boat (Coast Guard Drawing 35-
LRI-II-801-001)
N/A 1 ea. N/A
11 N Check Valve NSN: 4820-01-541-5446 PN:
5500447
2 ea. 1,964
12 Y Monitor, Smart Bilge NSN: 2040-01-600-0112 1 ea. 4,700.00 viii (Rev-1)
13 N Brominator filter cartridge** PN: MI160102 2 ea. 1,000.00
*Government-loaned property, which shall be returned to the vessel upon completion of the availability.
**New or refurbished equipment that the Government may provide for installation in place of existing equipment.
***Government-furnished property, which is to be supplied by either the vessel or the C4IT ServiceCenter ix (Rev-1)
CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS
The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5 (Inspection report particulars)):
Work Item Title
1 Tanks (Aviation Fuel Stowage and Overflow), Clean and Inspect
3 Air Conditioning Units Flex Hoses and Expansion Joints, Renew
4 Fuel Oil Purifier Flexible Hoses, Renew
7 Dual Point Davit, Biennial Maintenance, Perform
8 Stern Boat Launch and Recovery, Level II Inspect and Repair
9 Folding Boom Cranes, Biennial Maintenance, Perform
13 Reverse Osmosis, System Groom x (Rev-1)
PRINCIPAL CHARACTERISTICS
418' WMSL
PHYSICAL
Length overall 418' 0" Length between perpendiculars 390' 0" Maximum beam 54' 0" Beam @ 01 level 47' 9-1/8" Depth (01 level @ side to baseline) 39' 2-3/4" 01 deck camber foredeck 1/4" in 1'-0" Minimum berth depth 20' 0" Height of highest projection Approximately 119' Draft, design 14.40' Design displacement 3925 long tons
MACHINERY
Two diesel engines MTU 20V, 20-cylinder 9,730 SHP each One gas turbine General Electric LM2500; 29,500 SHP Type of propulsion CODAG Electrical system 24 Volt DC Two controllable pitch propellers Rolls-Royce 5 blade, 14' 0" diameter; 229 RPM max Two reduction gears RENK One cross connect gear RENK
HULL
Hull material 5086 Aluminum
HSLA-80 Steel ABS EH 36 Steel
ABS AH 36
Frame spacing FWD of FR 9 2' 3" FR 9 to FR 10 6' 9" FR 10 to FR 98 4' 1" FR 98 to FR 99 3'-8"
ELECTRICAL
Power Three 1360 kW, 450 V, 60 Hz, 3 Phase, 1800 RPM Caterpillar 3512B diesel engines with Baylor ship service generators Shore tie cable Seven MIL-C-24368/2 (NATO) shore power receptacles, 400 A each
TANK CAPACITIES
Diesel oil 220,359 gal Fresh water 12,454 gal JP-5 Fuel 35,182 gal
1 (Rev-1)
00000_0824_FLT
REC_00000_FLT_Commercial Project @ CG Facility (0121)
General Requirements
1. SCOPE
1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed by commercial contractors at a Coast Guard facility for Coast Guard vessels.
1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and 'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.
2. REFERENCES
None
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Latest Version, General Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), Latest Version, Welding and Allied Processes Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), Latest Version, Fire Prevention and Response Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), Latest Version, Requirements for Preservation of Ship Structures
OTHER REFERENCES
Code of Federal Regulations (CFR) Title 29, Part 1915, Occupational Safety and Health Standards for
Shipyard Employment NAVSEA Technical Publication T9074-AD-GIB-010/1688, (TP 1688), July 2012, Requirements for
Fabrication, Welding, and Inspection of Submarine Structure
2 (Rev-1)
3. REQUIREMENTS
3.1 General. The Contractor must conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability. The requirement in this WI applies to all work under the scope of this contract, whether explicitly stated in all following work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.
3.1.1 The Contractor must conform to all requirements specified in SFLC Std Spec 5550 and in the Fire Protection and Response work item, as applicable, during the performance of this availability.
3.1.1.1 Fire Safety Plan submission. The Contractor must submit a copy of the CFR 1915, Subpart P, Fire Safety Plan at the arrival conference. Include any MOA(s) with local firefighting facilities.
3.1.1.2 Fire Plan submission. The Contractor must submit a copy of the developed availability specific fire plan, as requested in the Fire Protection and Response work item, at the Arrival Conference.
3.2 Contractor-provided fire watch personnel. The Contractor must provide fire watch personnel and equipment.
3.3 Preservation requirements. The Contractor must accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.
3.3.1 Coating approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec 6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).
3.3.2 Coating colors and system color schemes. The Contractor must obtain a written CFR to the COR for authorization to deviate from any coatings required in SFLC Std Spec 6310 Appendix C before work.
3.3.3 In-process quality control measures. The Contractor must abide by all the safety, preservation, and quality control requirements specified in SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces”).
3.3.3.1 Quality control requirements. The Contractor must abide by the following when performing preservation related inspections. The following measurements must be randomly spaced throughout for the purposes of providing a representation of the entire prepared or coated surface.
3.3.3.1.1 Surface profile measurements. One surface profile measurement must be taken for every 200 square feet for the first 1000 square feet; for each additional 500 square feet or less, one profile measurement must be taken.
Profile measurements must be taken in accordance with SFLC Std Spec 6310, paragraph 3.1.8.3 (Surface profile measurements). A “measurement” for surface profile is defined as follows:
• ASTM D4417, Method B: One profile measurement is the average (mean) of 10 individual readings.
• ASTM D4417, Method C: One profile measurement is the average (mean) of 2 individual readings.
NOTE
NAVSEA drawings listed will be available FOR INSPECTION ONLY from the Coast Guard Port Engineer post-award. SFLC will not redistribute NAVSEA documents.
Contractors can apply to NAVSEA headquarters directly for copies.
3 (Rev-1)
3.3.3.1.2 Soluble salt conductivity measurements. 5 conductivity measurements must be taken every 1000 square feet. For submerged (immersed) applications conductivity measurements must not exceed 30 microsiemens/cm.
For non-submerged (non-immersed) applications conductivity measurements must not exceed 70 microsiemens/cm. If a conductivity check fails, clean the surface in accordance with SFLC Std Spec 6310, paragraph 3.1.8.5 (Soluble salt removal).
3.3.3.1.3 Coating thickness measurements. Three area measurements must be taken for the first 1000 square feet;
for each additional 1000 square feet, perform an additional area measurement. A “measurement” for coating thickness is defined as follows:
• SSPC-PA 2 defines an area measurement as 5 separate spot measurements randomly spaced throughout a 100 square foot area.
• SSPC-PA 2 defines a spot measurement as 3 gage readings and each new gage reading the probe must be moved to a new location within a 1.5-inch diameter circle defining the spot.
3.4 Welding and brazing requirements. The Contractor must perform all welding and allied processes, and NDE in accordance with SFLC Std Spec 0740.
3.4.1 HY-130 material substitution. The Contractor must be aware that HY-130 steel plating is no longer commercially available. For the purpose of performing flight deck repairs on US Coast Guard WMEC-270 “B- Class” cutters, Weldox 900 steel plating has been approved as a replacement for HY-130. Due to the similarity in material properties and weldability of HY-130 and Weldox 900, all welding procedures and welder qualifications for welding Weldox 900 must be the same as those outlined in NAVSEA TP 1688 as applicable for welding HY- 130.
3.4.2 Standard spec modification. For any welding involving HY-130 on the flight deck of WMEC-270 “B-Class” cutters, perform all welding and allied processes, and non-destructive evaluation (NDE) in accordance with NAVSEA TP 1688. The Contractor must be aware that the welding requirements specified in this document take precedence over paragraph 3.3.6 of SFLC Standard Spec 0000 for the purpose of welding involving HY-130.
3.4.3 Approval to weld HY-130. To obtain Coast Guard approval to weld on HY-130 steel for WMEC-270 “B- Class” cutters, the Contractor must provide written Performance Qualification Records (PQR’s) for each process to be used. The PQR’s must be approved by one of the regulatory agencies affirming that the WPS meets the welding requirements of NAVSEA TP 1688. In addition, the Contractor must ensure that all subcontractors, prior to performing welding operations, have qualified procedures by meeting all the requirements set forth in this document.
3.5 Environmental protection requirements. The Contractor must adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:
3.5.1 USCG facilities. The Contractor must provide and maintain environmental protection as defined in SFLC Std Spec 0000 Appendix B, Requirements for Environmental Protection at USCG Facilities, during the performance of this availability. Contractor must plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor must comply with applicable
NOTE
NAVSEA approval is NOT required for welding procedures submitted but the procedures must be reviewed and shown to satisfy the requirements set forth in NAVSEA TP 1688, by a welding regulatory agency. The requirements for welding Weldox 900 are considered the same as those for welding HY-130.
4 (Rev-1)
Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item must not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.
3.5.1.1 USCG Generator status. The activity Generator Status for the Coast Guard Facility is 7690390037. The EPA ID for the Coast Guard Facility is CA7690390037.
3.5.1.2 Plans and permits. The CG Facility has unit specific permits including the following:
• Spill Prevention Control and Countermeasures (SPCC) Plan: Unit has a SPCC Plan which requires certain unit-specific procedures be followed for the storage, inspection, and transfer of petroleum products in containers 55 gallons or greater.
• National Pollutant Discharge Elimination System (NPDES) Storm Water (SW) Permit: Unit has an NPDES SW permit which requires unit-specific procedures be followed for the storage and inspection of equipment and materials which may contribute contaminants to storm water discharges.
• Air Emission Permit: Unit has an Air Emission Permit which requires unit-specific procedures be followed for the emissions of VOCs and hazardous air pollutants.
3.5.2 Test and procedures. The Contractor is required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work must be done by qualified laboratories; and where required by law, the laboratories must be certified.
3.5.3 Regulatory notifications. The Contractor is responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the COR, if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The Contractor must submit copies of all regulatory notifications to the COR and the local Facility Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications must be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System (NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.
3.5.4 Environmental manager. The Contractor must appoint in writing an Environmental Manager for the project, who is responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager must ensure compliance with Hazardous Waste Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the Contractors’ Environmental Management Plan; ensure that all environmental permits are obtained, maintained, and closed out;
ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas; ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the Environmental Records binder and required documentation, including environmental permits compliance and close-out.
3.5.5 HW disposal. Contractor must comply with SFLC Std Spec 0000 Appendix B, Requirements For Environmental Protection At USCG Facilities for HW disposal, and ensure that waste removals are conducted during normal business hours (0800-1600) on Monday through Friday (excluding holidays).
3.5.6 Additional Requirements. The Contractor must be aware of the following:
5 (Rev-1)
3.5.6.1 No Contractor or Subcontractor must have the authority to sign a Hazardous Waste Manifest using the Coast Guard facility’s EPA Generator ID Number or remove contract generated hazardous waste from the Coast Guard facility without COR approval.
3.5.6.2 Local environmental regulations at the Government facilities may be more stringent. As with all environmental regulations, the Contractor must prepare for and comply with local and state regulations.
3.5.6.3 Coast Guard facilities do not maintain Facilities Response Plans (FRPs) per 33 CFR 154. Contractor must furnish the FRP when required for over-the-water liquids transfers to and from vessels, and is required for oil/fuel transfers to/from vessels for 250 barrels (10,500 gallons) or more.
3.6 Local Policy. The Contractor must refer to site (e.g., Base) Regulations and Instructions for details regarding local policies (e.g., crane services, parking, or facility usage).
3.7 SFLC Standard Specification approved changes. Approved updates to the 2022 SFLC Standard Specifications will appear here.
3.7.1 None.
4. NOTES
4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.
QA-1 - QUALITY ASSURANCE INSPECTION FORM
6 (Rev-1)
(PRESERVATION CHECKLIST)
VESSEL NAME HULL # WORK
ITEM #
WORK ITEM TITLE
LOCATION OF WORK (INCL. FRAME #’S) AREA (SQFT)
CHECKPOINT 1 – COATING SYSTEM COMPLIANCE
Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.
CHECKPOINT 2 - PAINT STORAGE
Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfg.
CHECKPOINT 3 - AMBIENT CONDITIONS
Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).
Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).
Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfg.
CHECKPOINT 4 - PRE-SURFACE PREPARATION
Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.
Verify equipment setup, blast media, and surface preparation methods match designated test coupon.
CHECKPOINT 5 - SURFACE PREPARATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).
Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.
Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).
CHECKPOINT 6 - PRIMER COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Verify proper mixing and stand-in (induction) times.
Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.
Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).
Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.
Brush out all runs, sags, drips, and puddles.
Perform visual inspection for holidays and other defects.
CHECKPOINT 7 – STRIPE COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).
CHECKPOINT 8 – TOP COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
Verify proper mixing and stand-in (induction) times, as applicable.
Verify wet film thickness at random, to prevent under or over application.
Brush out all runs, sags, drips, and puddles.
CHECKPOINT 9 – FINAL INSPECTION
Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.
Ensure that system cure is in accordance with manufacturer's recommendation for intended service.
Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.
For immersion coatings (including tank U/W body), record date and time of the following events:
Final coat application: / ; Return to service or removal from environment controls: /
CHECKPOINT 10 – RECORD KEEPING
Complete, sign, and submit all provided QA Inspection Forms.
NAME OF QP-1/AMPP INSPECTOR SIGNATURE CERT. # DATE / TIME
NAME OF CG REPRESENTATIVE SIGNATURE UNIT DATE/TIME
QA-2 - QUALITY ASSURANCE INSPECTION FORM
7 (Rev-1)
(ENVIRONMENTAL READINGS)
VESSEL NAME
HULL #
WORK
Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.
DATE
TIME
ACTIVITY (SURFACE
PREPARATION, PRIMER
COAT, BARRIER COAT, TOP
COAT, ETC…)
LOCATION (FRAME &
DECK, RELATION TO
EQUIPMENT, ETC.)
TEMPERATURE % REL.
HUMID-
ITY
DEW
PT.
SURFAC
E
AMBIEN
T
ΔT
| DP -
SURFACE |
8 (Rev-1)
QA-3a - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)
VESSEL NAME HULL # WORK ITEM
LOCATION OF WORK (FRAME REFERENCES) AREA (SQFT)
SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)
MIN MAX MEAN
SSPC-SP-10/AMPP No. 2
SSPC-SP WJ-2/AMPP WJ-2
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area)
Brush-blasting (non-metallic substrate)
ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:
PLACE SURFACE PROFILE REPLICA TAPES IN THE SPACES PROVIDED BELOW, TO SERVE AS
PERMANENT QA RECORD. MAINTAIN A SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS
DIVIDED INTO SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
MEAN MIL READING (IAW ASTM D4417-METHOD C) FOR ABOVE 15 READINGS:
NAME OF QP-1/AMPP INSPECTOR SIGNATURE CERT. # DATE /
TIME
9 (Rev-1)
QA-3b - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)
VESSEL NAME HULL # WORK ITEM
SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)
MIN MAX MEAN
SSPC-SP-10/AMPP No. 2
SSPC-SP WJ-2/AMPP WJ-2
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area)
Brush-blasting (non-metallic substrate)
ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:
RECORD MEASUREMENTS TAKEN IN THE SPACES PROVIDED BELOW, TO SERVE AS PERMANENT
QA RECORD. MAINTAIN SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS DIVIDED INTO
SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Mean Mils Reading (IAW ASTM D4417-Method B for above 10 readings (by column):
Mean Reading (mils)
10 (Rev-1)
QA-4 - QUALITY ASSURANCE INSPECTION FORM
(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)
VESSEL NAME HULL # WORK
SOLUBLE SALT CONDUCTIVITY MEASUREMENTS IAW SSPC-GUIDE 15.
DATE TEST LOCATIONS CONDUCTIVITY (MICROSIEMENS/CM)
11 (Rev-1)
(Use one sheet for each sequence)
QA-5 - QUALITY ASSURANCE DATA FORM
(COATING THICKNESS)
VESSEL NAME
HULL # WORK ITEM
COATING MFG
PRODUCT NAME
BATC
H #
INDUCTI
ON TIME
COATING SYSTEM
SEQUENCE
(PRIMER/TOUCHUP/3RD
COAT, ETC.)
DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC-PA 2.
SPOT 1 2 3 4 5 AVERAGE
VALUE
*BASE METAL READING
(BMR)
*Required, If Magnetic Pull-Off (Type I/Banana) Gauge Is Used.
LOCATION (FRAME REFERENCE):
SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS
1 AVG. BMR DEVIATION
3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS
AVG.
LOCATION (FRAME REFERENCE):
SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS
1 AVG. BMR DEVIATION
3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS
AVG.
LOCATION (FRAME REFERENCE):
SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS
1 AVG. BMR DEVIATION
3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS
AVG.
APPLICATION METHOD (AIRLESS,
CONVENTIONAL SPRAY, ROLLED)
AVERAGE DFT
12 (Rev-1)
4.2 Tank and Void Assessment form.
13 (Rev-1)
SFLC.aESD-45, PRINT
TA KAND VOID ASSESSl\1ENT
SHEET
StruoturaJ FntC1l'lirtv llitn E tim",ted Tomi Li.nea r Feet of Structure Requir.ing Repc1ir: I Estima ted Tota l Squa re F'eet of Pl ting Requiring Repllllir:
Cracks/ Fractures Present: ffel; ll\o I Buckling/Delleotionsl Di tortious Present I J Yi;;s No I-Ioles Pre ent: ':]Yes - No I Material Wnstnge iP:res.ent IOYes .No All \Velds. lnitacl; ffes No I Strncl.ura l E1.1f1lu ti011Recommended; I 1 yl;."/:l No
PHOTOGRAPHS
Pitt Taken {cnlCT (l llmnlily);
Note: To a,ld pict111res to this f@rm, Wark Station must h_m,,e Adob,e A.uoliat foot Readem-) ims.taJiled.
Add all photos and \oto co1mnen1i. to a \.W1rd document and save file. 011en thi f(l!1l1 and click "Combine Fil ", Add I.he document with photos ·',-ou.'ve im4 sawd and sav,c as a new combin d ,pdf file,:;, Additional Commrol±1:
Page2o,f 2 18MIA!R2016
14 (Rev-1)
12300_ESD_1023_FLT
REC_12311_FLT_418’ WMSL (755 CGC MUNRO) (1124)
WORK ITEM 1: Tanks (Aviation Fuel Stowage and Overflow), Clean and Inspect
1.1 Intent. This work item describes the requirements for the Contractor to clean and inspect the following tank(s):
TABLE 1 – LIST OF TANKS
TYPE OF TANK LOCATION CAPACITY - 95%
(GALLONS)
TANK CONTENT
DISPOSAL (GALLONS)
JP-5 Storage 5-70-0-J 13,124 691 JP-5 Drain 4-67-2-J 455 24
JP-5 Overflow 4-70-2-J 827 44
1.2 Government-furnished property.
None.
Coast Guard Drawing 418A-WMSL-100-001, Rev B, General Arrangements Coast Guard Drawing 750-WMSL-085-039, Rev -, Tank Sounding and Moment of Inertia Tables
(ASC085014F) (WMSL 755 Only) Coast Guard Drawing 750-WMSL-100-036, Rev N, Unit 3110 Structure 1st Platform and Below
Frs 65-77 (ASC100311) Coast Guard Drawing 750-WMSL-167-001, Rev J, Manhole List Installation and Fabrication
Details Ship Wide (ASC167001)
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and Allied Processes Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures
15 (Rev-1)
OTHER REFERENCES
3.1 General.
None.
3.1.1 CIR. The Contractor must submit a CIR for the inspections listed in the following paragraph(s):
• 3.7 Inspection
3.1.2 Tech Rep.
None.
3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).
3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the following:
• TLIs
• Piping
• Residual tank contents/fluids
3.2 Operational test, initial. Prior to commencement of work, the Contractor must witness Coast Guard personnel perform an initial operational test of all items or shipboard devices to be disturbed, used, repaired, or altered, to demonstrate existing operational condition. Submit a CFR.
3.2.1 Perform an initial operational test of each tank TLIs to demonstrate that each radar head/sensor is functional (i.e., Digital readout is displayed).
3.2.2 Ensure that there is interface/communication between the TLI sensor and the Machinery Control and Monitoring System (i.e. Digital readout at the TLI is identical to that displayed).
3.3 Tank opening. The Contractor must remove the tank manhole cover(s) and ventilate the confined spaces in accordance with SFLC Std Spec 0000, Paragraphs 3.3.1.1 and 3.3.1.2. The Contractor must provide fall protection to cover tank manhole cover when opened for ventilation/work.
NOTE
Coast Guard personnel will operate all shipboard machinery and equipment.
WARNING
Do not use the Fuel Service or Transfer systems to drain the water from the tank. Excessive fuel contamination will result.
16 (Rev-1)
3.4 Tank content and waste disposal. The Contractor must dispose of residual tank contents listed in Table 1 and any cleaning fluids in compliance with all applicable Federal, state, and local laws, ordinances and regulations. Notify the COR (in writing) at least 48 hours prior to removal of wastes and fluids. Document a complete chain of custody record of the removed tank contents and generated wastes, from the vessel to the point of final destination or delivery. Submit document to the COR upon completion of work.
3.5 Temporary plugs. The Contractor must plug all inlet and outlet piping in the tank to prevent contaminants from entering the tank or piping system. Use plugs with an attached lanyard, ring or other system that will ensure plugs are not lost in the pipe openings.
3.5.1 Plug log. The Contractor must keep a written record of all installed plugs. Keep a separate list for each tank. Maintain a plug accountability log posted immediately outside the tank to prevent any of the installed temporary plugs from being lost inside the tank or left behind inside at tank closure. The log must include the type and size of each plug, installation date, and removal date. Submit this log to the COR after completion of work item via a CFR.
3.5.2 The Contractor must ensure that all plugs are removed from each tank upon completion of work in the tank.
3.6 Tank cleaning. The Contractor must clean all designated tank interior surfaces free of all foreign materials, such as residual water, sediment, sludge, rust, or biological growth, taking care not to damage the coating system (if applicable).
3.6.1 The Contractor must accomplish all requirements of SFLC Std Spec 6310, 3.1.6.4 (Surface contaminant removal) to achieve the cleanliness requirements of SSPC-SP 1, including a low-pressure (maximum 5,000 psi) freshwater wash down of the surfaces.
3.6.2 Remove cleaning media and residues continuously from the tank during the washing process.
Remove any residual wash media and wipe up residual moisture with clean lint-free cloths. Wipe the interior tank structure dry and free of all cleaning agents.
3.7 Inspection. The Contractor must visually inspect all tank interior surfaces, including, but not limited to bulkheads, floor and overhead plating, structural members, manhole cover surfaces, fasteners and gasket seating surfaces. Submit a CIR with a description of the following, as applicable:
• Tank structural condition.
• Inaccessible areas.
• Condition of tank coating, including measurements taken, percentage, location, and type of coating failure.
• Tank level indicator (TLI) and/or float switch condition.
• Sounding/vent tube and striker plate condition.
• Suction and discharge piping condition.
• Fastener material and condition.
• Pit measurements
• Ultrasonic thickness (UT) measurements
17 (Rev-1)
3.7.1 Pit measurement. The Contractor must measure 50 pits within each tank/location listed in Table 1, in accordance with SFLC Std Spec 0740, Paragraph 3.13 (Evaluation of pitting corrosion). The results of these measurements must be included in the inspection report, showing where pit measurements were taken and the depth of the pit.
3.7.2 Ultrasonic thickness (UT) measurement. The Contractor must take UT measurements in the surrounding area of any pit measuring greater than 25% of plate thickness. UT measurements must be taken in the four quadrants at an equal-distant radius from the pit center until full plate thickness is measured. For bidding purposes, assume 200 UT measurements per tank listed in Table 1. UT measurements must be conducted in accordance with SFLC Std Spec 0740, Appendix C, using Coast Guard Drawings 750-WMSL-100-36 as guidance. The results of these measurements (original thickness, measured thickness, and any observed cracks) and the locations where they were taken must be included in the inspection report.
3.8 Substrate fairing and repair by filling Epoxy for shallow pits and small corrosions (i.e. pits < 25% or corrosions < 25%). The Contractor must repair small pin holes, shallow pitted substrates (with remaining plate thicknesses over 75% of required plate thicknesses), and fair corroded substrates (with remaining cross sections over 75% of required cross section areas), after removing coating, in accordance with SFLC Std Spec 6310 and manufacturers’ instructions.
• Procure 2 kits of Epoxy Fairing Compounds (e.g. Belzona 1111, 0.5 Gallon/5 Kg Kit ) to conduct repairs.
• Turn over all unused kits to the COR.
3.9 Tank closing. The Contractor must ensure that the tank(s) remain open for approximately 24 hours after completion of any authorized repair and preservation procedures. Notify the COR at least 48 hours prior to closing the tank(s). After satisfactory inspection by the Coast Guard Inspector and completion of all authorized repairs, remove all installed temporary plugs and document removal via signature on the plug log by the Coast Guard Inspector and Contractor prior to tank closing. Close tank manhole cover(s) using new gasket material, nuts and grommets in accordance with Coast Guard Drawing 750-WMSL- 167-001, in the presence of the Coast Guard Inspector. Chase threads on studs to ensure even installation of the access covers. Submit a CFR with the completed plug log.
3.10 Operational test, post repairs. After completion of work, the Contractor must thoroughly test, in the presence of the Coast Guard Inspector and demonstrate all items or shipboard devices that have been disturbed, used, repaired, altered, or installed to be in satisfactory operating condition. Submit a CFR.
3.10.1 Perform a post-work operational test of each tank TLIs to demonstrate that each radar head/sensor is functional (i.e., Digital readout is displayed).
3.10.2 Ensure that there is interface/communication between the TLI sensor and the Machinery Control and Monitoring System (i.e. Digital readout at the TLI is identical to that displayed).
NOTE
“Substrate fairing and repair by filling Epoxy for shallow pits and corrosions (i.e. pits < 25% or corrosions < 25%)” is a supplement barrier intending to help delay penetration.
18 (Rev-1)
3.11 Touch-up preservation. The Contractor must prepare and coat all new and disturbed surfaces, and all manhole cover external surfaces to match existing adjacent surfaces in accordance with SFLC Std Spec 6310, paragraph 3.1.13 (Touch-ups and minor coating repairs). Do not paint any manhole cover fasteners.
This section is not applicable to this work item.
19 (Rev-1)
12305_ESD_1124_FLT
REC_12311_FLT_418’ WMSL (755 CGC MUNRO) (1124)
WORK ITEM 2: Tanks (MP Fuel Service), Clean and Inspect
1.1 Intent. This work item describes the requirements for the Contractor to clean and inspect the following tank(s):
TABLE 1 – LIST OF UNPAINTED TANKS
TYPE OF TANK LOCATION CAPACITY - 95%
(GALLONS)
TANK CONTENT DISPOSAL
(GALLONS)
PAINTED
Fuel Oil Day Tank 1-81-1-F 846 45 N
Coast Guard Drawing 418A-WMSL-100-001, Rev B, General Arrangements Coast Guard Drawing 750-WMSL-085-039, Rev -, Tank Sounding and Moment of Inertia Tables
(ASC085014F) (WMSL 755 Only) Coast Guard Drawing 750-WMSL_100_43, Rev L, Unit 3240 – Main Deck To 01 Level – Fr 76
To Fr 82 (ASC100324) Coast Guard Drawing 750-WMSL-167-001, Rev J, Manhole List Installation and Fabrication
Details Ship Wide (ASC167001)
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and Allied Processes Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures
20 (Rev-1)
3.1.1 CIR.
None.
3.1.2 Tech Rep.
None.
3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).
3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the following:
• TLIs
• Piping
• Residual tank contents/fluids
3.2 Operational test, initial. Prior to commencement of work, the Contractor must witness Coast Guard personnel perform an initial operational test of all items or shipboard devices to be disturbed, used, repaired, or altered, to demonstrate existing operational condition. Submit a CFR.
3.2.1 Perform an initial operational test of each tank TLIs to demonstrate that each radar head/sensor is functional (i.e., Digital readout is displayed).
3.2.2 Ensure that there is interface/communication between the TLI sensor and the Machinery Control and Monitoring System (i.e. Digital readout at the TLI is identical to that displayed).
3.3 Tank opening. The Contractor must remove the tank manhole cover(s) and ventilate the confined spaces in accordance with SFLC Std Spec 0000, Paragraphs 3.3.1.1 and 3.3.1.2. The Contractor must provide fall protection to cover tank manhole cover when opened for ventilation/work.
3.4 Tank content and waste disposal. The Contractor must dispose of residual tank contents listed in Table 1 and any cleaning fluids in compliance with all applicable Federal, state, and local laws, ordinances and regulations. Notify the COR (in writing) at least 48 hours prior to removal of wastes and fluids. Document a complete chain of custody record of the removed tank contents and generated wastes, from the vessel to the point of final destination or delivery. Submit chain of custody record to the COR upon completion of work.
NOTE
Coast Guard personnel will operate all shipboard machinery and equipment.
WARNING
Do not use the Fuel Service or Transfer systems to drain the water from the tank. Excessive fuel contamination will result.
21 (Rev-1)
3.5 Temporary plugs. The Contractor must plug all inlet and outlet piping in the tank to prevent contaminants from entering the tank or piping system. Use plugs with an attached lanyard, ring or other system that will ensure plugs are not lost in the pipe openings.
3.5.1 Plug log. The Contractor must keep a written record of all installed plugs. Keep a separate list for each tank. Maintain a plug accountability log posted immediately outside the tank to prevent any of the installed temporary plugs from being lost inside the tank or left behind inside at tank closure.