Attachement 2 - (Updated) Work Specification - IDA LEWIS (WLM 175) DS FQ3 MAS 23R1.pdf

PDF 3 MB Posted

Attached to
CGC IDA LEWIS Dock side repairs
Solicitation number
70Z08523RIBCT0001
Issued by

About this file

This is a solicitation for commercial services to conduct dockside repairs to the USCGC IDA LEWIS, a 175-foot Coastal Buoy Tender homeported in Newport, Rhode Island. The Coast Guard seeks a contractor to provide all necessary materials, equipment, and personnel to complete repairs from June 6 to July 18, 2023. Required work includes hydraulic and electric deck machinery overhaul, tank cleaning and inspection, ventilation cleaning, exhaust piping cleaning, and interior and exterior painting. Questions regarding the solicitation are due by February 1 and quotes by February 21, 2023. The contract is set aside for small businesses and will be a firm fixed price award made by March 20, 2023. Drawings may be requested by February 10. The solicitation number is 70Z08523RIBCT0001.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USCGC IDA LEWIS (WLM 551)

SPECIFICATION FOR DOCKSIDE REPAIRS

FY2023

Developed By: Mark A Schmalstieg

(Rev-1, 14 December 2022)

USCGC IDA LEWIS (WLM-175) DOCKSIDE AVAILABILITY FY2023

ii (Rev-1)

TABLE OF CONTENTS

Revisions Record ......................................................................................................................................... iii Consolidated List of References ................................................................................................................... iv Consolidated List of Government-furnished Property ................................................................................. ix Consolidated List of Critical Inspection Items ............................................................................................. xi Principal Characteristics - TENDER .......................................................................................................... xii General Requirements WORK ITEM 1: Tanks, Potable Water, Clean and Inspect WORK ITEM 2: Voids, Accessible, Clean and Inspect WORK ITEM 3: Tanks, Dirty Oil and Waste, Clean and Inspect WORK ITEM 4: Ship Service Diesel Generator, SSDG, Exhaust Piping, Commercial Clean WORK ITEM 5: Vent Ducts, Engine And Motor Room, All, Commercial Cleaning WORK ITEM 6: Vent Ducts, Galley and Pantry Room, All, Commercial Cleaning WORK ITEM 7: Vent Ducts, Laundry Exhaust, Commercial Cleaning WORK ITEM 8: Vent Ducts, All Other, Commercial Cleaning WORK ITEM 9: Hot Water Accumulator Tanks, Clean and Inspect WORK ITEM 10: Compressed Air Receivers and System Valves, All, Clean, Inspect, Hydro and Lift ... 46 WORK ITEM 11: Sewage Holding Tanks, Clean and Inspect WORK ITEM 12: Sewage Piping, Clean and Flush WORK ITEM 13: Tanks (Sewage Holding), Preserve, 100 percent WORK ITEM 14: Tanks (Sewage Holding), Preserve, Partial WORK ITEM 15: Tanks, Dirty Oil and Waste, Preserve, 100 Percent, WORK ITEM 16: Tanks, Dirty Oil and Waste, Preserve, Partial, WORK ITEM 17: Tanks, Potable Water Preserve, 100 Percent WORK ITEM 18: Tanks, Potable Water, Preserve, Partial, WORK ITEM 19: Watertight Hatches 1-50-1 and 01-89-2, Upgrade WORK ITEM 20: Machinery Plant Control and Monitoring System, Groom WORK ITEM 21: Potable Water Piping, Renew WORK ITEM 22: Potable Water System Valves, Overhaul or Renew WORK ITEM 23: Hydraulic Piping and Hangers, Renew WORK ITEM 24: Deck Covering, Interior, Wet and Dry, Renew WORK ITEM 25: Point of Use Potable Water Filters, Install WORK ITEM 26: Main Diesel Engine, MDE, Exhaust Piping, Commercial Clean WORK ITEM 27: Watertight Scuttle (External), Renew WORK ITEM 28: Sewage Deck Connections, Renew WORK ITEM 29: Directional Control Valve, Upgrade WORK ITEM 30: Temporary Services, Provide - Cutter WORK ITEM 31: Crane Weight Harness, Renew WORK ITEM 32: Weather Deck Drain, Repair WORK ITEM 33: Auxiliary Seawater (ASW) System Piping, Renew WORK ITEM 34: Mechanical Remote Valve Operators, Renew iii (Rev-1)

REVISIONS RECORD

This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.

DATE REV# WORK

ITEM#

CHANGES MADE

12/14/2022 1 33 Added WI 33 (Auxiliary Seawater System Piping, Renew

12/14/2022 1 34 Added WI 34 (Mechanical Remote Valve Operators, Renew

NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.

iv (Rev-1)

CONSOLIDATED LIST OF REFERENCES

The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at the time of specification writing and during contract execution.

All Coast guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – from links located on the SFLC website. Commercial sites provide access to their respective documents.

COAST GUARD DRAWINGS

Coast Guard Drawing 175 WLM 167-001, Rev L, Structural Closures

Coast Guard Drawing 175 WLM 259-001, Rev A, Combustion Exhaust Diagram

Coast Guard Drawing 175 WLM 259-005, Rev C, Combustion Exhaust A&D, Hull Block 970

Coast Guard Drawing 175 WLM 505-002, Rev F, Mech Remote Valve Oprs A & D

Coast Guard Drawing 175 WLM 506-001, Rev G, Overflows, Air Escapes & Sounding Tubes Diagram

Coast Guard Drawing 175 WLM 508-002, Rev A, Combustion Exhaust Pipe Insulation

Coast Guard Drawing 175 WLM 512-001, Rev E, HVAC Diagram

Coast Guard Drawing 175 WLM 533-001, Rev G, Potable Water System Diagram

Coast Guard Drawing 175 WLM 533-001, Rev H, Potable Water System Diagram

Coast Guard Drawing 175 WLM 533-003, Rev G, Potable Water System A/D Hull Block 910, 920, 930, 940, 950

Coast Guard Drawing 175 WLM 533-006, Rev D, Independent Tank Potable Water Hb 950

Coast Guard Drawing 175 WLM 551-001, Rev J, Compressed Air System Diagram

Coast Guard Drawing 175 WLM 593-001, Rev G, Sewage & Waste Water System Diagram

Coast Guard Drawing 175 WLM 593-001, Rev G, Sewage and Waste Water System Diagram

Coast Guard Drawing 175 WLM 593-009, Rev E, Independent Tanks, Sewage Holding Tank

Coast Guard Drawing 175 WLM 601-002, Rev H, Booklet of General Drawings (IDA LEWIS)

Coast Guard Drawing 175 WLM 601-003, Rev F, Booklet of General Drawings (552-564)

Coast Guard Drawing 175 WLM 601-003, Rev F, Booklet of General Plans

Coast Guard Drawing 175 WLM 601-003, Rev F, Booklet of General Plans

Coast Guard Drawing 175 WLM 601-003, Rev F, Booklet Of General Plans

Coast Guard Drawing 175 WLM 633-001, Rev D, Cathodic Protection

Coast Guard Drawing 175 WLM-528-001, Rev E, Plumbing and Interior Deck Drains Diagram

Coast Guard Drawing 175-WLM 505-1, Rev C, General Requirements for Piping Systems

Coast Guard Drawing 175-WLM 528-2, Rev H, Weather Deck Drains Diagram

Coast Guard Drawing 175-WLM 556-1, Rev L, Hydraulic System Diagram

Coast Guard Drawing 175-WLM 573-50, Rev A, Hydraulic Piping Installation for Chain Stopper

Coast Guard Drawing 175-WLM 593-1, Rev G, Sewage & Waste Water System Diagram v (Rev-1)

Coast Guard Drawing 175-WLM 593-10, Rev -, Sewage/Waste Water System Shore Tie Deck

Connection Mods

Coast Guard Drawing 175-WLM 202-1, Rev J, MPCMS Cabling Diagram

Coast Guard Drawing 175-WLM 202-2, Rev F, MPCMS Cabling Diagram COED

Coast Guard Drawing 175-WLM 202-6, Rev B, MPCMS Wiring Modifications to Main & Secondary

Consoles (551-559)

Coast Guard Drawing 175-WLM 202-7, Rev C, MPCMS Wiring Data Modifications to Consoles

(COED), Hulls 551-559

Coast Guard Drawing 175-WLM 256-001, Rev J, Seawater Cooling System Diagram

Coast Guard Drawing 175-WLM 256-003, Rev D, Seawater Cooling System Frame 61 FWD, Blocks

910, 920, & 930

Coast Guard Drawing 175-WLM 256-004, Rev J, Seawater Cooling System A&D, Hull Blocks 940-970

Coast Guard Drawing 175-WLM 256-012, Rev B, ASW System Piping Modifications

Coast Guard Drawing 175-WLM 601-003, Rev N, Booklet of General Plans

Coast Guard Drawing 175-WLM-167-001, Rev L, Structural Closures

Coast Guard Drawing 175-WLM-202-201, Rev Q, MPCMS

Coast Guard Drawing 175-WLM-320-001, Rev AP, Electrical One-Line Diagram

Coast Guard Drawing 175-WLM-437-007, Rev R, Buoy Dk Control Sys Block, ISO & Elem Wrg Diag

Coast Guard Drawing 175-WLM-573-013, Rev -, Replacement DCV Amplifier Card Wiring Diagram

Coast Guard Drawing 175-WLM-601-001, Rev T, General Arrangement Inboard and Outboard Profiles

Coast Guard Drawing 225B-WLB 202-1, Rev G, MPCMS Cabling Diagram

Coast Guard Drawing 225B-WLB 202-2, Rev D, MPCMS Connection Table

Coast Guard Drawing 225-WLB 202-1, Rev F, MPCMS Cabling Diagram

Coast Guard Drawing 225-WLB 202-2, Rev G, MPCMS COED

Coast Guard Drawing FL 533-001, Rev B, Point of Use Potable Water Flush

Coast Guard Drawing FL 533-002, Rev A, Point of Use Water Filter Install

NAVSEA Drawing 804-5959214, Rev -, Piping Insulation-Installation Details

COAST GUARD PUBLICATIONS

CGTO PG-85-00-230-S, August 2013, Planned Maintenance System Development Process Guide

Coast Guard Commandant Instruction (COMDTINST) 9077.1 (series), Equipment Lockout/Tags-Plus

Instruction

Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors

Manual

Coast Guard Maintenance Procedure Card (MPC) A-A-14033, Dec 2017, Buoy Chain Winch Wire Rope

Weight

Coast Guard Technical Publication (TP) 10502 Machinery Plant Control & Monitoring System Operating

Manual (MPCMSOM)

Coast Guard Technical Publication (TP) 3498, SWBS 573, Aug 2019, Buoy Chain Winch

Coast Guard Technical Publication (TP) 3505 A & B Machinery Plant Control & Monitoring System

Operating Manual (MPCMSOM)

Coast Guard Technical Publication (TP) 3507 MPCMS Computer System Operating Manual (CSOM)

Coast Guard Technical Publication (TP) 3508 MPCMS Computer System Diagnostic Manual (CSDM)

Coast Guard Technical Publication (TP) 3509 MPCMS Software User's Manual (SUM) vi (Rev-1)

Coast Guard Technical Publication (TP) 3585 A& B Machinery Plant Control & Monitoring System

Operating Manual (MPCMSOM)

Coast Guard Technical Publication (TP) 3589 MPCMS Computer System Manual

Coast Guard Technical Publication (TP) 3605 A & B Machinery Plant Control & Monitoring System

Operating Manual (MPCMSOM)

Coast Guard Technical Publication (TP) 3607 MPCMS Computer System Operating Manual (CSOM)

Coast Guard Technical Publication (TP) 3608 MPCMS Computer System Diagnostic Manual (CSDM)

Coast Guard Technical Publication (TP) 3630, SWBS 573, Nov 2022, Buoy Crane - Model SB230-42 -

Operation, Maintenance and Repair Instructions

Coast Guard Technical Publication (TP) 3932 MPCMS Data Logging System

COMDTINST M9085.1, Rev C, Naval Engineering Computer Aided Design Standards

Fire Prevention and Response

SFLC Technical Standard 086, June 2013, Technical Publications (TP)

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2020, General

Requirements

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Latest Version, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2020, Welding and

Allied Processes

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), Latest Version, Welding and Allied Processes

Surface Forces Logistics Center Standard Specification 0850 (SFLC Std Spec 0850), 2020, General

Requirements for Drawing Preparation

Surface Forces Logistics Center Standard Specification 3041 (SFLC Std Spec 3041), 2020, Shipboard

Electrical Cable Test

Surface Forces Logistics Center Standard Specification 3042 (SFLC Std Spec 3042), 2020, Shipboard

Electrical Cable Removal, Relocation, Splice, Repair, and Installation

Surface Forces Logistics Center Standard Specification 5100 (SFLC Std Spec 5100), 2020, Clean

Shipboard Ventilation Systems

Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), Latest Version, Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2020 Requirements for Preservation of Ship Structures

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2020, Preserve Ship

Structures

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2020, Requirements for Preservation of Ship Structures

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), Latest Version, Requirements for Preservation of Ship Structures

Surface Forces Logistics Center Standard Specification 6341 (SFLC Std Spec 6341), 2020, Install Interior

Deck Covering Systems

Surface Forces Logistics Center Standard Specification 8635 (SFLC Std Spec 8635), 2020, Temporary

Services

Surface Forces Logistics Center Standard Specification 8636 (SFLC Std Spec 8636), 2020, Temporary

Hull Accesses vii (Rev-1)

OTHER REFERENCES

American National Standards Institute/American Water Works Association (ANSI/AWWA) C652, 2002, Disinfection of Water-Storage Facilities

American National Standards Institute/American Water Works Association (ANSI/AWWA) C652, 2011, Disinfection of Water-Storage Facilities

American National Standards Institute/American Water Works Association (ANSI/AWWA) C652, 2019, Disinfection of Water-Storage Facilities

American National Standards Institute/NSF International (ANSI/NSF) 61, 2008, Drinking Water System

Components - Health Effects

American National Standards Institute/NSF International (ANSI/NSF) 61, 2015, Drinking Water System

Components - Health Effects

American Society for Testing and Materials (ASTM) International F1508, 2016, Standard Specification for Angle Style, Pressure Relief Valves for Steam, Gas, and Liquid Services

American Society of Mechanical Engineers (ASME) B16.34, 2004, Valves-Flanged, Threaded, and

Welding End

American Society of Mechanical Engineers (ASME) B16.34, 2017, Valves-Flanged, Threaded, and

Welding End

ASTM International (ASTM) D1330, 2010 Standard Specification for Rubber Sheet Gaskets

ASTM International (ASTM) D1330, 2010, Standard Specification for Rubber Sheet Gaskets

ASTM International (ASTM) D1330, 2015, Standard Specification for Rubber Sheet Gaskets

ASTM International (ASTM) F683, 2014, Standard Practice for Selection and Application of Thermal

Insulation for Piping and Machinery

ASTM International (ASTM) F992, 2006, Standard Specification for Valve Label Plates

ASTM International (ASTM) F992, 2017, Standard Specification for Valve Label Plates

Code of Federal Regulations (CFR) Title 29, Part 1915, 2014, Occupational Safety and Health Standards for Shipyard Employment

Code of Federal Regulations (CFR) Title 29, Part 1915, 2022, Occupational Safety and Health Standards for Shipyard Employment

Code of Federal Regulations (CFR) Title 29, Part 1915, Occupational Safety and Health Standards for

Shipyard Employment

Commercial Item Description (CID) A-A-59316, 2003, Abrasive Materials for Blasting

Compartment Check Off List: WLM 175 – 551 (IDA LEWIS)

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-61, 2019 Edition, Pressure Testing Of Valves

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-67, 2017 Edition, Butterfly Valves

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-72, 2010 Edition, Ball Valves with Flanged or Butt-Welding Ends for General Service

Manufacturers' Standardization Society of the Valve and Fittings Industry (MSS) SP-80, 2008 Edition, Bronze Gate, Globe, Angle and Check Valves

Manufacturers' Standardization Society of the Valve and Fittings Industry (MSS) SP-80, 2019 Edition, Bronze Gate, Globe, Angle and Check Valves

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS), SP-58, 2009, Pipe

Hangers and Supports – Materials, Design, Manufacture, Selection, Application and Installation viii (Rev-1)

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS), SP-58, 2018, Pipe

Hangers and Supports – Materials, Design, Manufacture, Selection, Application and Installation

NAVSEA Technical Publication T9074-AD-GIB-010/1688, (TP 1688), July 2012, Requirements for

Fabrication, Welding, and Inspection of Submarine Structure

Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2013, Cork and

Rubber Composition Sheet; For Aromatic Fuel and Oil Resistant Gaskets

Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2019, Cork and

Rubber Composition Sheet; For Aromatic Fuel And Oil Resistant Gaskets

Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183B, 2019, Cork and Rubber Composition Sheet; For Aromatic Fuel and Oil Resistant Gaskets

The Society for Protective Coatings (SSPC) Surface Preparation Specification No. 16 (SSPC-SP 16), 2010, Brush-Off Blast Cleaning of Coated and Uncoated Galvanized Steel, Stainless Steels, and

Non-Ferrous Metals

The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2004, Power Tool Cleaning to Bare Metal

The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2012, Power Tool Cleaning to Bare Metal

The Society for Protective Coatings (SSPC)/NACE International (NACE) 2006, Joint Surface Preparation

Standard SSPC-SP 10/NACE No.2, Near-White Blast Cleaning

The Society for Protective Coatings (SSPC)/NACE Joint Surface Preparation Standard SSPC-SP

10/NACE No.2, 2004, Near-White Blast Cleaning ix (Rev-1)

CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY

The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.

WORK

ITEM

MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED

COST

($/UNIT)

19 N 30in x 30in Watertight

Hatch w/ 21in Scuttle, 15 PSI

N/A 2 ea. 14,500.00

23 Y **Lockring Tool and

Equipment

N/A 1 ea. 4000.00

25 N Water Filter Assembly, (3M) (ACN) 44330-01-

F20-5959

PN: DWS160-L NSN: 6 ea. 160.00

25 N Water Filter Element, (3M)

PN: 56134-44 6 ea. 180.00

25 N Placard - Potable Water

Flush

N/A 8 ea. 50.00

27 N 18 in steel QAWTS

(Raised 12in combing, NAVSEA 803-1401892 1 ea. $9,500.00

29 N Directional Control

Valve (DCV)

NSN: 4810-01-F19-5719 PN:

4WRE10E75-2X/G24K4/V

1 ea. 1748.00

29 N Amplifier Card NSN: 5996-01-F19-5720 PN:

VT-VRPA2-2-1X/V0/T1

1 ea. 1552.00

29 N Mating Connector, 4P

G4WIF PG7 SW

NSN: 5935-01-F19-5722 PN:

R900023126

1 ea. 46.00

31 N Cable, 3 shielded pairs PN: 20265817 60 ft. 4.53/ft

31 N Cable, 2 shielded pairs, 14 AWG

PN: 37-102-621 60 ft. 8.25/ft

31 N Cable, 2 PR, 16 AWG PN: 20260643 60 ft. 3.38/ft

31 N Electrical Enclosure PN: YMD-6896 1 ea.

31 N Connection Box, watertight

PN: YMD-10578 3 ea. 1,752.00

34 N Deck Box: ¾-in size w/10 turns, weld-in, cam-lock cover included

BFG P/N: VCDB-1200-10 15 ea. 576.00

34 N 90deg Gear Box: ¾-in size, bronze

BFG P/N: VCG-3200 7 ea. 402.00

34 N Consolidated Hinged

Joint: 3/4in size, manganese bronze housing, sst shafts

BFG P/N VCK-1200 2 ea. 439.95

34 N U-Joint 1-3/4in OD x

3/4in bore, steel

BFG P/N VCU-1142 18 ea. 110.99

34 N Valve Coupling Rising

Handwheel, 3/4in male

BFG P/N: VCU-3200 5 ea. 82.75

34 N Valve Coupling Rising BFG P/N: VCM-2200 2 ea. 139.00 x (Rev-1)

Stem, 3/4in *Government-loaned property, which shall be returned to the vessel upon completion of the availability.

**New or refurbished equipment that the Government may provide for installation in place of existing equipment.

***Government-furnished property, which is to be supplied by either the vessel or the C4IT ServiceCenter xi (Rev-1)

CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS

The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5

(Inspection report particulars)):

Work

Item Title

20 Machinery Plant Control and Monitoring System, Groom

24 Deck Covering, Interior, Wet and Dry, Renew

29 Directional Control Valve, Upgrade

31 Crane Weight Harness, Renew

32 Weather Deck Drain, Repair xii (Rev-1)

PRINCIPAL CHARACTERISTICS - TENDER

175' WLM, BUOY TENDER

PHYSICAL

Length overall 174' 8"

Length between perpendiculars 155' 1"

Depth 14' 8"

Maximum beam 36' 0"

Designed draft 8' 0"

Mast height (above 8' waterline) 58' 8"

Frame spacing 20"

Full load displacement 855.15 Long Tons SW

Light load displacement 719.78 Long Tons SW

Minimum op condition displ 852.19 Long Tons SW

HULL

Hull material Steel

MACHINERY

Main propulsion Two Caterpillar 3508 DITA V-8 diesel; 999 BHP ea @ 1500 RPM

Two Ulstein 360 degree steerable Z-Drives, 403 SRPM @ 1600 ERPM

Reduction gears Two Z-Drive units, Cardan shafting; 3.973:1 gear ratio

Shaft seal John Crane Type ND

Shaft bearings Five pedestal mounted, Cooper split roller bearings

Number of propellers 2

Number of blades 4

Diameter 57.1"

Rudders None; Z-drive

Ship's service generators Three Caterpillar Model 3406 DITA Turbocharged; 285KW, 450V, 60 Hz, 1800

RPM

Emergency diesel generator One Caterpillar Model 3406 DIT 210 KW, 24V, 60 Hz, 1800 RPM

TANK CAPACITIES

Diesel oil capacity (100%) 16,385 gal

Fresh water capacity (100%) 7,339 gal

Lubricating oil (100%) 86 gal

1 (Rev-1)

00000_0522_FLT

REC_00000_FLT_Commercial Project @ CG Facility (0121)

General Requirements

1. SCOPE

1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed by commercial contractors at a Coast Guard facility for Coast Guard vessels.

1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and

'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is

Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.

2. REFERENCES

COAST GUARD DRAWINGS

None

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Latest Version, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), Latest Version, Welding and Allied Processes

Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), Latest Version, Fire Prevention and Response

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), Latest Version, Requirements for Preservation of Ship Structures

OTHER REFERENCES

Code of Federal Regulations (CFR) Title 29, Part 1915, Occupational Safety and Health Standards for

Shipyard Employment

NAVSEA Technical Publication T9074-AD-GIB-010/1688, (TP 1688), July 2012, Requirements for

Fabrication, Welding, and Inspection of Submarine Structure

2 (Rev-1)

3. REQUIREMENTS

3.1 General. The Contractor must conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability. The requirement of this WI applies to all work under the scope of this contract, whether explicitly stated in all following work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.

3.1.1 The Contractor must conform to all requirements specified in SFLC Std Spec 5550 and in the Fire

Protection and Response work item, as applicable, during the performance of this availability.

3.1.1.1 Fire Safety Plan submission. The Contractor must submit a copy of the CFR 1915, Subpart P, Fire Safety

Plan with the Contractor’s bid when work will be conducted in a Contractor–owned facility. Include any MOA(s) with local firefighting facilities.

3.1.1.2 Fire Plan submission. The Contractor must submit a copy of the developed availability specific fire plan, as requested in the Fire Protection and Response work item, seven (7) days before the Arrival Conference.

NOTE

NAVSEA drawings listed will be available FOR INSPECTION ONLY from the Coast

Guard Port Engineer post-award. SFLC will not redistribute NAVSEA documents.

Contractors can apply to NAVSEA headquarters directly for copies.

3.2 Fire watch requirements. The Contractor must refer to 3.3.1.3 (Fire watch requirements) of SFLC Std Spec

0000, in accomplishing the following task:

• Provide portable fire extinguishers for Coast Guard fire watch personnel. Coast Guard fire watch is in lieu of contractor personnel during the hours of 0800-1700, Monday through Friday, and limited to two Coast Guard fire watch personnel.

• Contractor must provide any additional fire watch personnel and fire extinguishers needed for hotwork that occurs beyond the hours and personnel requirements listed above.

3.3 Preservation requirements. The Contractor must accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.

3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec

6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).

3.3.2 Coating colors and system color schemes. The Contractor must obtain a written KO authorization to deviate from any coatings required in SFLC Std Spec 6310 Appendix C before work.

3.3.3 In-process quality control measures. The Contractor must abide by all the safety, preservation, and quality control requirements specified in SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces”).

3.3.3.1 Quality control requirements. The Contractor must abide by the following when performing preservation related inspections. The following measurements must be randomly spaced throughout for the purposes of providing a representation of the entire prepared or coated surface.

3 (Rev-1)

3.3.3.1.1 Surface profile measurements. One surface profile measurement must be taken for every 200 square feet for the first 1000 square feet; for each additional 500 square feet or less, one profile measurement must be taken.

Profile measurements must be taken in accordance with SFLC Std Spec 6310, paragraph 3.1.8.3 (Surface profile measurements). A “measurement” for surface profile is defined as follows:

• ASTM D4417, Method B: One profile measurement is the average (mean) of 10 individual readings.

• ASTM D4417, Method C: One profile measurement is the average (mean) of 2 individual readings.

3.3.3.1.2 Soluble salt conductivity measurements. 5 conductivity measurements must be taken every 1000 square feet. For submerged (immersed) applications conductivity measurements must not exceed 30 microsiemens/cm.

For non-submerged (non-immersed) applications conductivity measurements must not exceed 70 microsiemens/cm. If a conductivity check fails, clean the surface in accordance with SFLC Std Spec 6310, paragraph 3.1.8.5 (Soluble salt removal).

3.3.3.1.3 Coating thickness measurements. Three area measurements must be taken for the first 1000 square feet;

for each additional 1000 square feet, perform an additional area measurement. A “measurements” for coating thickness is defined as follows:

• SSPC-PA 2 defines an area measurement as 5 separate spot measurements randomly spaced throughout a 100 square foot area.

• SSPC-PA 2 defines a spot measurement as 3 gage readings and each new gage reading the probe must be moved to a new location within a 1.5 inch diameter circle defining the spot.

3.4 Welding and brazing requirements. The Contractor must perform all welding and allied processes, and NDE in accordance with SFLC Std Spec 0740.

3.4.1 HY-130 material substitution. The Contractor must be aware that HY-130 steel plating is no longer commercially available. For the purpose of performing flight deck repairs on US Coast Guard WMEC-270 “B-

Class” cutters, Weldox 900 steel plating has been approved as a replacement for HY-130. Due to the similarity in material properties and weldability of HY-130 and Weldox 900, all welding procedures and welder qualifications for welding Weldox 900 must be the same as those outlined in NAVSEA TP 1688 as applicable for welding HY-

130.

3.4.2 Standard spec modification. For any welding involving HY-130 on the flight deck of WMEC-270 “B-Class” cutters, perform all welding and allied processes, and non-destructive evaluation (NDE) in accordance with

NAVSEA TP 1688. The Contractor must be aware that the welding requirements specified in this document take precedence over paragraph 3.3.6 of SFLC Standard Spec 0000 for the purpose of welding involving HY-130.

3.4.3 Approval to weld HY-130. To obtain Coast Guard approval to weld on HY-130 steel for WMEC-270 “B-

Class” cutters, the Contractor must provide written Performance Qualification Records (PQR’s) for each process to be used. The PQR’s must be approved by one of the regulatory agencies affirming that the WPS meets the welding requirements of NAVSEA TP 1688. In addition, the Contractor must ensure that all subcontractors, prior to performing welding operations, have qualified procedures by meeting all the requirements set forth in this document.

NOTE

NAVSEA approval is NOT required for welding procedures submitted but the procedures must be reviewed and shown to satisfy the requirements set forth in

NAVSEA TP 1688, by a welding regulatory agency. The requirements for welding

Weldox 900 are considered the same as those for welding HY-130.

4 (Rev-1)

3.5 Environmental protection requirements. The Contractor must adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:

3.5.1 USCG / Naval facilities. The Contractor must provide and maintain environmental protection as defined in

SFLC Std Spec 0000 Appendix B, Requirements for Environmental Protection at USCG / Naval Facilities, during the performance of this availability. Contractor must plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor must comply with applicable

Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item must not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.

3.5.1.1 USCG Generator status. The activity Generator Status for Naval Station Newport RI is a (HW Generator).

3.5.1.2 Plans and permits. Naval Station Newport has unit specific permits including the following:

• Spill Prevention Control and Countermeasures (SPCC) Plan: Unit has a SPCC Plan which requires certain unit-specific procedures be followed for the storage, inspection, and transfer of petroleum products in containers 55 gallons or greater.

• National Pollutant Discharge Elimination System (NPDES) Storm Water (SW) Permit: Unit has an

NPDES SW permit which requires unit-specific procedures be followed for the storage and inspection of equipment and materials which may contribute contaminants to storm water discharges.

• Air Emission Permit: Unit has an Air Emission Permit which requires unit-specific procedures be followed for the emissions of VOCs and hazardous air pollutants.

3.5.2 Test and procedures. The Contractor is required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work must be done by qualified laboratories; and where required by law, the laboratories must be certified.

3.5.3 Regulatory notifications. The Contractor is responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG / USN Facility, the local Facility Engineer or Engineering Officer. The

Contractor must submit copies of all regulatory notifications to the Contracting Officer and the local Facility

Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications must be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System

(NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.

3.5.4 Environmental manager. The Contractor must appoint in writing an Environmental Manager for the project, who is responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager must ensure compliance with Hazardous Waste Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the Contractors’

Environmental Management Plan; ensure that all environmental permits are obtained, maintained, and closed out;

ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous

Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas; ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements

5 (Rev-1) and individual position requirements; coordinate removal of waste containers; and maintain the Environmental

Records binder and required documentation, including environmental permits compliance and close-out.

3.5.5 HW disposal. Contractor must comply with SFLC Std Spec 0000 Appendix B, Requirements For

Environmental Protection At USCG / Facilities for HW disposal, and ensure that waste removals are conducted during normal business hours (0800-1600) on Monday through Friday (excluding holidays).

3.5.6 Additional Requirements. The Contractor must be aware of the following:

3.5.6.1 No Contractor or Subcontractor must have the authority to sign a Hazardous Waste Manifest using the

Coast Guard facility’s EPA Generator ID Number or remove contract generated hazardous waste from the Coast

Guard facility without COR or KO-approval.

3.5.6.2 Local environmental regulations at the Government facilities may be more stringent. As with all environmental regulations, the Contractor must prepare for and comply with local and state regulations.

3.5.6.3 Coast Guard facilities do not maintain Facilities Response Plans (FRPs) per 33 CFR 154. Contractor must furnish the FRP when required for over-the-water liquids transfers to and from vessels and is required for oil/fuel transfers to/from vessels for 250 barrels (10,500 gallons) or more.

3.6 Local Policy. The Contractor must refer to site (e.g., Base) Regulations and Instructions for details regarding local policies (e.g., crane services, parking, or facility usage).

3.7 SFLC Standard Specification approved changes. The Contractor must be aware that the following are approved changes to published SFLC 2020 Edition Standard Specifications and supersede published content:

3.7.1 SFLC Standard Specification 8636. Add missing paragraphs between 3.2 and 3.5 of Std Spec 8636 as follows:

“3.3 Access cut boundaries. The Contractor shall ensure that access cuts comply with the requirements and restrictions detailed in the following and in SFLC Std Spec 0740 and referenced codes.

3.3.1 Location of boundaries. Boundaries of access cuts and closure plates shall, in general, be located between principal ship framing, bulkheads, and other structural members and shall be at least three inches from any of these members or from the toes of other welds. A reduction in this three-inch minimum may be approved by the KO on a case-by-case basis provided sufficient clearance is maintained for welding and inspection requirements. The boundaries of access cuts and closure plates should land on existing butts or seams, wherever practicable. The boundaries of prior access cuts should be utilized wherever possible. Boundaries may extend across one or more frames as required for the size of the opening.

3.3.2 Access hole dimensions and arrangements. Holes or access cuts shall be the minimum size necessary and shall be in accordance with the following:

• Rectangular access cuts and closure plates welded into primary hull structure shall be at least 12 inches wide in the lesser dimension.

• For circular access cuts, the minimum diameter shall be 4T, where T = thickness of the involved structural member, but not less than three inches.

• Circular closure plates for access cuts less than two feet in diameter shall be

6 (Rev-1) dished 1/16 to 1/8 inch to allow for shrinkage when welded.

• Corners of rectangular access cuts and closure plates shall have a minimum radius of 6 inches except when a boundary lands on an existing hull longitudinal seam or transverse butt weld.

• Corners at an existing seam or butt shall intersect at a 90-degree angle.

• Cuts that are to cross existing butts or seams shall do so at an angle of 90 degrees plus or minus 15 degrees.

• In primary hull structure, existing welds forming the boundary of a cut shall be cut back 3 inches beyond the toe of the access cut, except that the cut back shall not intersect or cross an existing weld, frame, or structural member. In which case, the cut back may be reduced to a minimum of two inches in length.

• Existing welds crossed by the cut shall not be cut back.

3.3.3 Primary hull structure. Primary Hull Structure includes the shell, main strength decks, principal longitudinal bulkheads, vertical keel, deep web girders and stiffeners designed to withstand the ship bending stress.

3.3.4 Mechanically fastened joints. Welding closer than six inches to a mechanically fastened joint should be avoided. When access cuts cross or come within six inches of a mechanically fastened joint, the fasteners shall be checked for tightness and if necessary, loose fasteners shall be seal welded or removed, and replaced for a distance of 6 inches beyond the edge of the cut. When a cut crosses a mechanically fastened seam the cut plates shall be repaired using single V welds backed with glass tape (MIL-C-20079) to prevent fusion between the mechanically fastened plates.

3.4 Ship integrity maintenance. The Contractor shall maintain safety and ship integrity by installing temporary guarding and coaming, in addition to weathertight and watertight closures. Remove these temporary fabrications after closing the hull access, and grind surfaces flush in way of removals. For shell plating cuts made at or below the waterline where temporary closures are impractical, the Contractor shall secure each vulnerable compartment and subdivision to minimize potential damage to the extent permitted by the scope and urgency of the work.

3.4.1 Guarding. Install temporary guards in accordance with 29 CFR 1915.73.

3.4.2 Coaming. Ensure that in areas where flammable liquids may be stored, a 4-inch-high metal coaming shall be installed on the surface of the deck with tack welds and fully sealed with caulking compound. The coaming shall encircle the access cut in the deck.

3.4.3 Weathertight and contamination closures. Fabricate temporary closures, using fire retardant material, before cutting access openings and install closures whenever access is not in use. Closures shall be:

• Constructed to protect the access from inclement weather and entry of contaminants (shall include a coaming or dam on the deck to redirect rain runoff away from the opening).

• Fitted with fasteners that permit rapid installation and removal.

• Able to support a minimum of 150 pounds per square foot for horizontal

7 (Rev-1) deck closures.

• Where the access opening is in way of a removed hatch, scuttle or door, the closure shall be configured to allow normal passage of ship’s personnel and equipment.

3.4.4 Watertight closures. Ensure that access openings created four feet or less above the maximum anticipated waterline shall include temporary watertight closures when the vessel is waterborne.

NOTE

NAVSEA S0600-AA-PRO-160/CH16 provides requirements for design, fabrication, and installation of temporary watertight closures.”

3.7.2 SFLC Standard Specification 0000. Replace paragraph 3.3.4 Vessel access, as follows:

"3.3.4 Vessel access. During work at the Contractor’s facility, provide access and/or egress to and from the vessel in accordance with 29 CFR 1915.74, Subpart E. Provide a minimum of two gangways that have the following:

• Adequate walking surface width and strength and be safely secured.

• A railing, with a mid-rail, on each side of the gangway, and a turn table if necessary.

• Substantial steps properly secured and equipped with at least one handrail, when the upper end of the gangway rests on or is flush with the top of the bulwark of the dock.

• Nets or other suitable protection on both sides, when there is a danger of personnel falling between the ship and the dock. Nets and other suitable protection must extend beyond the projected area of the access and egress points so as to catch personnel that may be falling outward: i.e., the nets must be wider than the gangway.

• Proper trimming at all times.

• Adequate illumination for their full length.

• Separated by one-fourth the length of the vessel, at a minimum, as to mitigate the possibility that an incident could block both means of escape."

3.7.3 SFLC Standard Specification 8635. Replace and add paragraphs as follows, "3.3.10.4.1 Contractor-furnished supporting equipment. Provide all hoses and fittings needed to supply water to the system. Provide pressure gauges at the connection(s) to the ship and the furthest firehose station to allow personnel to clearly read the gage-face to demonstrate or record the required water pressure is available at all energized portions of the system."

"3.2.3 Shipboard access/egress and routing of temporary services. Maintain a primary and secondary means of access/egress for each vessel, where practicable.

Pre-plan for the installation of temporary services to minimize the total number of service leads penetrating the hull by maximizing the use of backbones and/or manifolds for industrial services. Pre-planning for the installation of temporary services shall include removal (first in, last out, when no longer required). Pay

8 (Rev-1) special attention to transitional spaces (cross passages, top and bottom of stairwells) where services could potentially fall and restrict emergency personnel egress and/or casualty responder access."

"3.2.3.2 Materials used for suspending temporary services. Temporary services shall be suspended at regular intervals, to prevent impeding personnel access/egress and emergency response, using a high temperature line that meets the noncombustibility test requirements contained in reference (e). When using steel wire rope, or other potentially abrasive material, an anti-chafing material shall be used to prevent damage of the temporary service line. When available, temporary service lines may be run through the ship’s structural elements (i.e., cable ways, light stanchions, etc.). When the routing of temporary services overhead is not practicable, temporary services, rigging of hoses, welding leads, and temporary lights shall be clear of the decks on temporary “trees” or brackets and be arranged to minimize tripping and other hazards."

"3.2.3.5 Quick Disconnect Fittings. QDFs shall be located within 10 feet of designated vertical and horizontal fire zone boundaries. When practicable, QDFs shall be installed within 10 feet of hull penetrations used for personnel access, to facilitate the deployment of smoke control curtains. QDFs must be capable of being disconnected safely on pressurized or energized systems unless approved for use as described in paragraph 3.2.3.7. Pressurized and disconnected QDFs must prevent wetting of energized equipment. For hull openings used for services only, QDFs are not required, provided the opening is fitted with an air and smoke control “sock” that remains in place around the services. Air and smoke control curtains are not intended to provide an airtight seal of the hull opening. Rather, the curtains or socks, are to ensure that emergency responders can control the flow of air and smoke through the opening to allow for de-smoking of compartments and minimize “chimney” effects. Curtains shall be made of fire-resistant fabric meeting the requirements of NFPA 701."

"3.2.3.7 Service lines crossing fire zone boundaries. When service lines transit a fire zone boundary which cannot be safely disconnected locally (e.g., high voltage cables), the COR shall approve, in advance, the method to safely secure and remove the service."

3.7.4 SFLC Standard Specification 6310.

3.7.4.1 On page 2, replace REFERENCE “MIL-PRF-24667C, May 2008, Coating System, Non-Skid, for Roll, Spray, or Self-Adhering Application” with “MIL-PRF-24667D, FEB 2021, Coating System, Non-Skid, for Roll, Spray, or Self-Adhering Application”

3.7.4.2 On page 9, replace the NOTE under paragraph 3.1.8.5 as follows:

NOTE

De-ionized water may be used in cases where available fresh water has excessive chloride/chlorine content. Submit a CFR prior to using de-ionized water.

9 (Rev-1)

4. NOTES

4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.

10 (Rev-1)

QA-1 - QUALITY ASSURANCE INSPECTION FORM

(PRESERVATION CHECKLIST)

VESSEL NAME HULL # WORK ITEM

WORK ITEM TITLE

LOCATION OF WORK (INCL. FRAME #’S) AREA (SQFT)

CHECKPOINT 1 – COATING SYSTEM COMPLIANCE

Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.

CHECKPOINT 2 - PAINT STORAGE

Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfg.

CHECKPOINT 3 - AMBIENT CONDITIONS

Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).

Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).

Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfg.

CHECKPOINT 4 - PRE-SURFACE PREPARATION

Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.

Verify equipment setup, blast media, and surface preparation methods match designated test coupon.

CHECKPOINT 5 - SURFACE PREPARATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).

Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.

Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).

CHECKPOINT 6 - PRIMER COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Verify proper mixing and stand-in (induction) times.

Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.

Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).

Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.

Brush out all runs, sags, drips, and puddles.

Perform visual inspection for holidays and other defects.

CHECKPOINT 7 – STRIPE COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).

CHECKPOINT 8 – TOP COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

Verify proper mixing and stand-in (induction) times, as applicable.

Verify wet film thickness at random, to prevent under or over application.

Brush out all runs, sags, drips, and puddles.

CHECKPOINT 9 – FINAL INSPECTION

Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.

Ensure that system cure is in accordance with manufacturer's recommendation for intended service.

Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.

For immersion coatings (including tank U/W body), record date and time of the following events:

Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____

CHECKPOINT 10 – RECORD KEEPING

Complete, sign, and submit all provided QA Inspection Forms.

NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE / TIME

NAME OF CG REPRESENTATIVE SIGNATURE UNIT DATE/TIME

11 (Rev-1)

QA-2 - QUALITY ASSURANCE INSPECTION FORM

(ENVIRONMENTAL READINGS)

VESSEL NAME HULL #

WORK ITEM

Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.

DATE

TIME

ACTIVITY (SURFACE

PREPARATION, PRIMER COAT,

BARRIER COAT, TOP COAT,

ETC…)

LOCATION (FRAME &

DECK, RELATION TO

EQUIPMENT, ETC.)

TEMPERATURE % REL.

HUMID-

ITY

DEW

PT.

SURFACE AMBIENT ΔT

| DP -

SURFACE |

12 (Rev-1)

QA-3a - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)

VESSEL NAME HULL # WORK ITEM

LOCATION OF WORK (FRAME REFERENCES) AREA (SQFT)

SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)

MIN MAX MEAN

SSPC-SP-10/NACE No. 2

SSPC-SP WJ-2/NACE WJ-2

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area)

Brush-blasting (non-metallic substrate)

ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:

PLACE SURFACE PROFILE REPLICA TAPES IN THE SPACES PROVIDED BELOW, TO…

This is the start of the file's text. The full file is on GovTribe.