Cont Amendment A00002 Request_for_Clarifications_70Z08522QP4504500_MARIA BRAY DD FY22.pdf

PDF 654 KB Posted

Attached to
MARIA BRAY FY 2022 DRY DOCK REPAIRS
Solicitation number
70Z08522QP4504500
Issued by

About this file

This document contains correspondence related to a solicitation for dry dock repairs of the USCGC Maria Bray. Key details include: the solicitation number 70Z08522QP4504500; the requirement is for dry dock repairs of the cutter Maria Bray in fiscal year 2022; offerors were permitted to submit clarification questions by December 15, 2021 and proposals are due by January 10, 2022. The correspondence provides responses to offeror questions seeking clarification on work items involving overhaul of thruster units, removal of potable and ballast water, inspection and repair of deck drains, replacement of coaming and deck plate, and requests for reference drawings.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 4

Offeror’s questions will be answered by an Amendment.

1. Offeror’s questions concerning this solicitation shall be submitted in writing, and must be submitted on the following attached “Request for Clarification” form.

One (1) question should be submitted per form.

Each form should indicate the name of the offeror’s firm & date submitted.

2. Questions may be submitted via E-mail ONLY to:

Iris.M.Johnson@uscg.mil AND Arlene.D.Wright@uscg.mil mailto:Iris.M.Johnson@uscg.mil

REQUEST FOR CLARIFICATION

(Copy as Needed)

SUBMIT REQUESTS NO LATER THAN Wednesday, 15 December 2021 @ 2:30 PM PT

CUTTER & HULL NUMBER: USCGC MARIA BRAY (WLM 562)

USCG RFQ Number: 70Z085-22-Q-P4504500

QUESTION

NO:

OFFEROR’S

NAME:

SUBMITTAL

DATE:

SOLICITATION

SECTION NO AND/OR

PAGE NO:

PARAGRAPH

N/A

DEFINITE/OPTION

ITEM NO:

D-050

PARAGRAPH

NO:

1.2

TITLE (DESCRIPTION):

Thruster Unit (General), Overhaul

QUESTION: Please identify the components included in the GFM Seal Kit, Thruster, NSN: 2010-01-555-9048. The contractor wants to insure that we do not price items that are included in the kit.

Response: THE BOW THRUSTER SEAL KIT CONSISTS OF THE FOLLOWING PARTS AND

QUANTITIES:

GASKET (SEALING RING): P/N B125SM44186, 1 EACH

SPLIT SEAL, SP 3.62 X 4.62 X .5: P/N N-2-4-9, 3 EACH

SPLIT SEAL, 8.00 X 9.25 X .500: P/N N-2-3-39, 5 EACH

PINION SEAL SHIM: P/N B125SM44191, 1 EACH

O-RING, 7.750 ID X .139 BUNA-N: P/N O-2-2-21, 1 EACH

O-RING, 9.000 ID X .139 BUNA-N: P/N O-2-2-25, 1 EACH

O-RING, 21.000 ID X .210 BUNA-N: P/N O-3-2-6, 1 EACH

O-RING, 20.625 ID X .210 BUNA-N: P/N O-8-1-26, 1 EACH

O-RING, 11.000 ID X .139 BUNA-N: P/N O-2-3-2, 1 EACH

O-RING, 7.500 ID X .210 BUNA-N: P/N O-3-1-23, 1 EACH

O-RING, 16.000 IC X .210 BUNA-N: P/N O-3-2-23, 1 EACH

SAT-O-BRS SEAL, .500 DIA: P/N O-4-2-25, 3 EACH

DRIVE BEARING HOUSING SHIM: P/N B125SM44095, 2 EACH

TUNNEL POD SHIM: P/N B125SM44152, 2 EACH

SHIM PINION SEAL, .020 THICK P/N B125SM44191-1 2 EACH

SHIM, PINION SEAL .125 THICK P/N B125SM44191-2 1 EACH

DEFINITE/OPTION

ITEM NO:

Answer to Question 1

QUESTION: The government failed to provide the updated price schedule they indicated as attached. Please provide the updated price schedule.

Response: Update spreadsheet attached titled: UPDATED SOSS

PAGE NO:

AMENDMENT 01

Answers to Questions 3-6

QUESTION: The governments answer to questions 3-6 was “cannot predict due to operations”. If the government cannot provide a quantity of fluids for removal, the contractor will not be able to do so as well. The contractor recommends the government insert quantities of fluids to be removed in each work item so that the contractors can price each work item the same.

Response: We cannot predict the Potable and Ballast water levels. The tank capacities are listed and the contractor can use those levels to quote. It is always the intention for a unit to come in as light as possible but, given we do not know where an awarded contractor may be, or the operational commitment prior to the available is we cannot predict these levels.

1/5/22

PAGE NO:

AMENDMENT 01

D-039

PARAGRAPH

NO:

3.4 and 3.5

Answer to Question 8

QUESTION: The governments answer to question 8 was “the amount can be estimated per the drawings. Ship checks are recommended”. The paragraphs in question direct the contractor to “replace as necessary”. The government and the contractor have no idea how much of each drain system needs to be replaced. The drawings and ship checks will not provide identification of areas to be replaced until the inspection of each drain is completed. The government’s answer is not satisfactory. The inspection of the drains should be completed, a report of findings with recommended repairs should be submitted to the government and the cost of repairs should be covered as growth work. This is the contractor’s recommendation and request.

Response: Concur as 3.3, 3.4 and 3.5 require CFRs. The purpose of the work item is to inspect and identify work needed to make serviceable the deck drains.

PAGE NO:

AMENDMENT 01

D-048

PARAGRAPH

NO:

3.2.3

Answer to Question 11

QUESTION: The governments answer to question 11 was “recommend per the drawing”.

This does not answer the question or correct the improper dimension provided by the government in paragraph 3.2.3. The contractor can replace 50 linear feet of coaming using the drawings to identify the material. The contractor cannot replace 50 linear feet of deck plate without knowing the total square feet dimension. The contractor requests the government provide the correct square feet dimension of deck plate deck plate to be replaced.

Response: Replacing 50 linear feet of coaming, plate renewal will be identified per the plate inspection in 3.2.1.

D-036

Answer to Question 12

QUESTION: When can the contractor expect to receive the requested reference drawing?

Response: Drawings requested; KS will notify the contractor when drawing have been e-mailed.