This document contains clarification questions and responses related to a solicitation for dry dock repairs of the USCGC Maria Bray. The solicitation requests repairs and maintenance of the cutter including cleaning and inspection of various tanks, replacement of handrails and stanchions, inspection and repair of deck drains, overhaul of propulsion and thruster units, and renewal of deck plating. Questions covered pricing sheets, reference drawings, quantities of materials to be removed, and component parts included in government furnished materials. Responses provided additional details, guidance on estimations, and clarification of work items. The question deadline was December 15, 2021 and the solicitation closing date is January 10, 2022. The solicitation was issued by the US Coast Guard for dry dock repairs of the USCGC Maria Bray to be completed by the contractor.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| UPDATED SOSS.xls | XLS spreadsheet | |
| 70Z08522QP4504500_A00002_SF30.pdf | ||
| Cont Amendment A00002 Request_for_Clarifications_70Z08522QP4504500_MARIA BRAY DD FY22.pdf | ||
| 70Z08522QP4504500_ A00001_ SF30.pdf | ||
| Attachment 4 - Request for Clarifications.docx | DOCX document | |
| Attachment 1 - MARIA BRAY DD FY22 SOSS.xls | XLS spreadsheet | |
| Attachment 2 - MARIA BRAY (WLM 175) DD FQ2 BGW 21R0.pdf | ||
| Attachment 3 - Past Performance Information Form.docx | DOCX document | |
| MARIA BRAY DD FY22 Solicitation.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 4
Offeror’s questions will be answered by an Amendment.
1. Offeror’s questions concerning this solicitation shall be submitted in writing, and must be submitted on the following attached “Request for Clarification” form.
One (1) question should be submitted per form.
Each form should indicate the name of the offeror’s firm & date submitted.
2. Questions may be submitted via E-mail ONLY to:
Iris.M.Johnson@uscg.mil AND Arlene.D.Wright@uscg.mil mailto:Iris.M.Johnson@uscg.mil
REQUEST FOR CLARIFICATION
(Copy as Needed)
SUBMIT REQUESTS NO LATER THAN Wednesday, 15 December 2021 @ 2:30 PM PT
CUTTER & HULL NUMBER: USCGC MARIA BRAY (WLM 562)
USCG RFQ Number: 70Z085-22-Q-P4504500
QUESTION
NO:
OFFEROR’S
NAME:
SUBMITTAL
DATE:
12/9/21
SOLICITATION
SECTION NO AND/OR
PAGE NO:
PARAGRAPH
N/A
DEFINITE/OPTION
ITEM NO:
TITLE (DESCRIPTION):
Attachment 1 – Pricing Sheet
QUESTION: The pricing sheet provided by the government is not complete. The formulas do not extend to cover all work items. The formulas to total Definite and Option Items are incorrect and do not capture all items listed.
Response – updated price schedule attached; UPDATED ATTACHMENT 1 MARIA
BRAY DD FY 22 SOSS
Lyon Shipyard, Inc.
SUBMITTAL
12/14/21
N/A
DEFINITE/OPTION
ITEM NO:
D-08
PARAGRAPH
NO:
3.9
Tanks, Fuel Service, Clean and Inspect
QUESTION: Paragraph 3.9 is incomplete, the reference drawing has been omitted. Please provide the correct reference.
Response – Please use the drawings listed.
N/A
DEFINITE/OPTION
ITEM NO:
D-09
PARAGRAPH
NO:
3.4
Tanks, Potable Water, Clean and Inspect
QUESTION: How much potable water will the vessel have onboard that is required to be removed?
Response – Cannot predict due to operations
N/A
DEFINITE/OPTION
ITEM NO:
D-010
PARAGRAPH
NO:
3.3
Tanks, Ballast, Clean and Inspect
QUESTION: How much ballast water will the vessel have in each tank that is required to be removed?
Response – Cannot predict due to operations
N/A
DEFINITE/OPTION
ITEM NO:
D-021
PARAGRAPH
3.5.1
Grey Water Holding Tanks, Clean and Inspect
QUESTION: How much grey water will the vessel have in each tank that is required to be
Response – Cannot predict due to operations.
N/A
DEFINITE/OPTION
ITEM NO:
D-022
PARAGRAPH
NO:
3.5.1
Sewage Holding Tanks, Clean and Inspect
QUESTION: How much effluent will the vessel have in each tank that is required to be
Response – cannot predict due to operations
N/A
DEFINITE/OPTION
ITEM NO:
D-038
PARAGRAPH
NO:
3.3 and 3.4
Handrails and Stanchions, Inspect, Repair or Renew
QUESTION: Paragraph 3.3 directs the contractor to “tank a total of 03 UT measurements”. Is this a total of three (3) measurements? Or is the number incorrect?
Response – number is correct
Paragraph 3.4 directs the contractor to “verify the integrity of all boundaries affected by this work item”. Please clarify the intent of this paragraph. Is it the government’s intent to NDT all welds completed to insert or repair the handrails?
Response – follow guidance for boundary NDT in Standard spec 0740.
N/A
DEFINITE/OPTION
ITEM NO:
D-039
PARAGRAPH
NO:
3.4 thru 3.5
Deck Drains, Inspect, Service & Repair
QUESTION: Paragraph 3.3 directs the contractor to “Crop out as necessary, and retain the drain for use as templates”. Paragraph 3.4 directs the contractor to “Crop out, scrap and renew, as necessary, deck drains”. Paragraph 3.5 directs the contractor to
“Fabricate, as necessary, the missing grating cover”.
The contractor has no way to foresee the amount and sizes of piping in each deck drain that must be removed and renewed and the amount and size of deck drain gratings to fabricate until the cleaning and inspection has been completed. Will the results of the inspection be the subject of a Change Order? Will the government consider including amounts of pipe, fittings, sizes and a number of gratings to be fabricated for bidding purposes?
Response – the amount can be estimated per the drawings. Ship checks are recommended.
N/A
DEFINITE/OPTION
ITEM NO:
D-040
PARAGRAPH
NO:
3.2.1
Watertight Door, External, Renew
QUESTION: Paragraph 3.2.1 says “Install GFP door in place of that removed. When
GFP door is not provided, the contractor shall fabricate and install new door”. Does the government have the door in question in stock?
Response – Doors are GFE
If the GFP door is not provided, fabrication of a new door will not take place within the government’s performance period. Will the government consider overhaul and repair of the existing door as a suitable alternative?
Response – Overhaul will be considered if necessary
N/A
DEFINITE/OPTION
ITEM NO:
D-044
PARAGRAPH
NO:
Entire Item
Anchors, Preserve
QUESTION: Work Item 19 includes the provision to prepare and preserve the vessel’s anchors. It is the contractor’s opinion that Work Item 44 is redundant and should be deleted. Will the government delete this work item?
Response – recommend bid as specified
N/A
DEFINITE/OPTION
ITEM NO:
D-048
PARAGRAPH
NO:
3.2.3
01 Level Deck, Repair
QUESTION: Paragraph 3.2.3 directs the contractor to “Renew approximately 50-linear feet of coaming and deck plating”. 50 linear feet of deck plating does not provide enough information for the contractor to develop a quote. Please provide a square foot dimension of deck plate to be renewed.
Response – recommend per the drawing
12/15/21
N/A
DEFINITE/OPTION
ITEM NO:
D-036
PARAGRAPH
NO:
2.0
Single Point Davit Winch, Replace
QUESTION: The reference titles “Coast Guard Technical Publication (TP) 3632, 07 JAN
97, Manufacturers Instruction Book-SWBS Group(s) 582-583 was not included in the reference download. Please provide this reference.
Response - The reference titles “Coast Guard Technical Publication (TP) 3632, 07 JAN 97, Manufacturers Instruction Book-SWBS Group(s) 582-583) request please from the librarian.
12/16/21
N/A
DEFINITE/OPTION
ITEM NO:
D-004
Appendages, U/W Hull, Leak Test
QUESTION: The Section B has this work item classified as an “OPTION” item. The item contains a Critical Inspection Report (CIR) requirement which would be hard to complete if the item is not started at the beginning of the repair period. Will the government consider making this item a “DEFINITE” item?
Response – D-004 updated to Definite item
12/22/21
N/A
DEFINITE/OPTION
ITEM NO:
D-050
PARAGRAPH
1.2
Thruster Unit (General), Overhaul
QUESTION: Please identify the components included in the GFM Seal Kit, Thruster, NSN: 2010-01-555-9048. The contractor wants to insure that we do not price items that are included in the kit.
Response - THE BOW THRUSTER SEAL KIT CONSISTS OF THE FOLLOWING
PARTS AND QUANTITIES: GASKET (SEALING RING): P/N B125SM44186, 1
EACH
SPLIT SEAL, SP 3.62 X 4.62 X .5: P/N N-2-4-9, 3 EACH
SPLIT SEAL, 8.00 X 9.25 X .500: P/N N-2-3-39, 5 EACH
PINION SEAL SHIM: P/N B125SM44191, 1 EACH
O-RING, 7.750 ID X .139 BUNA-N: P/N O-2-2-21, 1 EACH
O-RING, 9.000 ID X .139 BUNA-N: P/N O-2-2-25, 1 EACH
O-RING, 21.000 ID X .210 BUNA-N: P/N O-3-2-6, 1 EACH
O-RING, 20.625 ID X .210 BUNA-N: P/N O-8-1-26, 1 EACH
O-RING, 11.000 ID X .139 BUNA-N: P/N O-2-3-2, 1 EACH
O-RING, 7.500 ID X .210 BUNA-N: P/N O-3-1-23, 1 EACH
O-RING, 16.000 IC X .210 BUNA-N: P/N O-3-2-23, 1 EACH
SAT-O-BRS SEAL, .500 DIA: P/N O-4-2-25, 3 EACH
DRIVE BEARING HOUSING SHIM: P/N B125SM44095, 2 EACH
TUNNEL POD SHIM: P/N B125SM44152, 2 EACH
SHIM PINION SEAL, .020 THICK P/N B125SM44191-1 2 EACH
SHIM, PINION SEAL .125 THICK P/N B125SM44191-2 1 EACH
12/22/21
N/A
DEFINITE/OPTION
ITEM NO:
D-050
PARAGRAPH
1.2
Thruster Unit (General), Overhaul
QUESTION: The OEM has indicated that any parts required for the thruster overhaul that need to be purchased by the contractor have at least a 2 month lead time. This
Request for Clarification is to inform the government.
Response - Noted
12-10-2021
3.1.2
DEFINITE/OPTION
ITEM NO:
Work Item 12
PARAGRAPH
NO:
3.1.2
Z Drive Propulsion Unit Renew
QUESTION:
Section 3.1.2 Tech Rep. States that the authorized Tech Rep is Pacific Star Marine.
We contacted Mr. Mike Butler for a quote to provide the services as described in the specifications. We were informed he no longer has the contract with USCG. Can you provide the information for the new contact holder of said services?
Response – No contracted services the services are contractor provided.