Attachment (1) - Schedule of Supplies and Services dtd 29 October 2021
Solicitation No.: 70Z08522QP4503200
USCGC STONE (WMSL 758) Dockside FY22 FYQ2
Provide all labor, materials, and equipment, except as specified, to perform the services identified in Attachment (2) REV-1, dated 29 October 2021.
CLIN 0001 - DEFINITE WORK ITEMS
These are the items that, if there is an award at all, will be awarded. The proposal shall be evaluated to include the proposed price for each definite item.
Work ItemDescriptionQTYUnitAmount
D-01Tanks (Ballast), Clean and Inspect, 5-82-0-W1JOB$0.00
D-02Tanks (Oily Waste), Clean and Inspect, 5-59-1-F1JOB$0.00
D-05Fire Extinguishing System (Galley Grease), Inspect and Test1JOB$0.00
D-06Gas Turbine Module Fixed CO2 Fire Fighting System, Inspect and Test1JOB$0.00
D-07Heptafluropropane (HFP) Fire Fighting System , Inspect and Test1JOB$0.00
D-08Water Mist Fire Fighting System, Inspection1JOB$0.00
D-09Water Mist Fire Fighting System, Discharge Test1JOB$0.00
D-10Handgrabs, Install (Remaining)1JOB$0.00
D-11Handrails, Install1JOB$0.00
D-12Storage Cages, Install1JOB$0.00
D-13Sounding Tube, Replace1JOB$0.00
D-14HVAC and Chill Water System, Modify - REMOVEDCANCELLED
D-15Transom Double Doors and Tow Outfits, Modify1JOB$0.00
D-16Stern Door Hydraulic and Control System, Modify1JOB$0.00
D-17Dry Provisioning Storeroom, Modify - REMOVEDCANCELLED
D-18HVAC System (Port Aft Capstan), Modify1JOB$0.00
D-19Floating Platform, Provide1JOB$0.00
$0.00
CLIN 0002 - OPTIONAL WORK ITEMS
Optional items listed below will be awarded if inspection reports reveal the necessity for activation. Evaluation of the options shall not obligate the Government to exercise the option.
Work ItemDescriptionQTYUnitAmount
O-03Tanks (Ballast), Preserve (100%) 5-82-0-W1JOB$0.00
O-04Tanks (Oily Waste), Preserve (100%) 5-59-1-F1JOB$0.00
O-20Crane Barge Services, Provide1JOB$0.00
$0.00$0.00
COMPOSITE LABOR HOUR RATE (CLHR)
The following labor hour rate shall be used in pricing all contract changes in accordance with the ADDENDA clause entitled “Composite Labor Rate.” Composite Labor Hour Rate - Provide the all inclusive mark-up/loading rate for materials and subcontractors below. This rate will be incorporated into the contract and used on change requests.
Labor Rate Per HourEstimated Quantity**Total
$0.002,737$0.00$0.00