Bids
| Attachment (1) - Schedule of Supplies and Services dtd 29 October 2021 |
| Solicitation No.: 70Z08522QP4503200 |
| USCGC STONE (WMSL 758) Dockside FY22 FYQ2 |
| Provide all labor, materials, and equipment, except as specified, to perform the services identified in Attachment (2) REV-1, dated 29 October 2021. | ||||
| CLIN 0001 - DEFINITE WORK ITEMS | ||||
| These are the items that, if there is an award at all, will be awarded. The proposal shall be evaluated to include the proposed price for each definite item. | ||||
| Work Item | Description | QTY | Unit | Amount |
| D-01 | Tanks (Ballast), Clean and Inspect, 5-82-0-W | 1 | JOB | $0.00 |
| D-02 | Tanks (Oily Waste), Clean and Inspect, 5-59-1-F | 1 | JOB | $0.00 |
| D-05 | Fire Extinguishing System (Galley Grease), Inspect and Test | 1 | JOB | $0.00 |
| D-06 | Gas Turbine Module Fixed CO2 Fire Fighting System, Inspect and Test | 1 | JOB | $0.00 |
| D-07 | Heptafluropropane (HFP) Fire Fighting System , Inspect and Test | 1 | JOB | $0.00 |
| D-08 | Water Mist Fire Fighting System, Inspection | 1 | JOB | $0.00 |
| D-09 | Water Mist Fire Fighting System, Discharge Test | 1 | JOB | $0.00 |
| D-10 | Handgrabs, Install (Remaining) | 1 | JOB | $0.00 |
| D-11 | Handrails, Install | 1 | JOB | $0.00 |
| D-12 | Storage Cages, Install | 1 | JOB | $0.00 |
| D-13 | Sounding Tube, Replace | 1 | JOB | $0.00 |
| D-14 | HVAC and Chill Water System, Modify - REMOVED | CANCELLED | ||
| D-15 | Transom Double Doors and Tow Outfits, Modify | 1 | JOB | $0.00 |
| D-16 | Stern Door Hydraulic and Control System, Modify | 1 | JOB | $0.00 |
| D-17 | Dry Provisioning Storeroom, Modify - REMOVED | CANCELLED | ||
| D-18 | HVAC System (Port Aft Capstan), Modify | 1 | JOB | $0.00 |
| D-19 | Floating Platform, Provide | 1 | JOB | $0.00 |
| $0.00 |
| CLIN 0002 - OPTIONAL WORK ITEMS | |||||
| Optional items listed below will be awarded if inspection reports reveal the necessity for activation. Evaluation of the options shall not obligate the Government to exercise the option. | |||||
| Work Item | Description | QTY | Unit | Amount | |
| O-03 | Tanks (Ballast), Preserve (100%) 5-82-0-W | 1 | JOB | $0.00 | |
| O-04 | Tanks (Oily Waste), Preserve (100%) 5-59-1-F | 1 | JOB | $0.00 | |
| O-20 | Crane Barge Services, Provide | 1 | JOB | $0.00 | |
| $0.00 | $0.00 |
| COMPOSITE LABOR HOUR RATE (CLHR) | |||
| The following labor hour rate shall be used in pricing all contract changes in accordance with the ADDENDA clause entitled “Composite Labor Rate.” Composite Labor Hour Rate - Provide the all inclusive mark-up/loading rate for materials and subcontractors below. This rate will be incorporated into the contract and used on change requests. | |||
| Labor Rate Per Hour | Estimated Quantity** | Total | |
| $0.00 | 2,737 | $0.00 | $0.00 |
| **NOTE: The estimated quantity and extended amount indicated above are for evaluation of offers only. The Composite Labor Hour Rate provided above will apply to all changes involving additional work under this contract regardless of the actual total hours required. |