RFP 70Z08520RP4500400 Amendment 0001 Offerors' Questions and Coast Guard Response Question/Clarification

No. Solicitation Reference Question Government Response

1 SF 1449

Offeror inquired about the willingness of the Government to remove the 45 day dry-dock hold requirement from the solicitation and to remove it as an evaluation factor.

The Government carefully considered this request and has decided that the potential operational impact of removing this requirement was greater than could be absorbed by other assets. The governments use of the 45 day dry dock hold requirement as an evaluation factor remains unchanged.

2 SF 1449

Offeror respectfully requests a two week extension for proposal submission From 14FEB to 28FEB.

Request for proposal due date is extended to 21 FEB 2020 1000 (PST).

The Government does not anticipate extending the solicitation close date beyond 21 FEB 2020 in anticipation of administrative requirements necessary to complete contract award and the period of performance start date.