MACKINAW_DD_FY19_SPECIFICATIONS.pdf
PDF 3 MB Posted
- Attached to
- DRYDOCK REPAIRS FOR THE USCGC MACKINAW
- Solicitation number
- 70Z08519-Q-P4505400
About this file
SPECIFICATION
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment_002_MACKINAW_DD.docx | DOCX document | |
| QUESTION_ANSWERS_MACK_DD_22FEB19.docx | DOCX document | |
| Mackinaw_DD_2018_Scope_of_Supply_rev4_(002).pdf | ||
| REVISED_MACKINAW_DD_SECTION_B.xls | XLS spreadsheet | |
| Amendment_001_MACKINAW_DD.docx | DOCX document | |
| CGC_MCAKINAW_DDFY19_-_PAST_PERFORMANCE.doc | DOC document | |
| CGC_MACKINAW_70Z085-19-Q-P4505400.pdf | ||
| CGC_MACKINAW_DDFY19_-_DHS_Form_700-23_DHS_Subcontracting_Plan_Review_Checklist.pdf | ||
| CGC_MACKINAW_DDFY19_-_OMBUDSMAN.doc | DOC document | |
| CGC_MACKINAW_DDFY19_-_Attachment_-Request_for_Clarification.doc | DOC document | |
| MACKINAW_(WLBB_240)_DD_FY19_SECTION_B.xls | XLS spreadsheet |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USCGC MACKINAW (WLBB 30)
SPECIFICATION FOR DRYDOCK REPAIRS
FY2019
Developed By: Byron J Belmas
(Rev-0, 18 September 2018)
USCGC MACKINAW (WLBB-240) DRYDOCK AVAILABILITY FY2019
ii (Rev-0)
TABLE OF CONTENTS
Revisions Record .......................................................................................................................................... iv Consolidated List of References .................................................................................................................... v Consolidated List of Government-furnished Property .................................................................................. x Consolidated List of Critical Inspection Items ........................................................................................... xii Principal Characteristics ............................................................................................................................ xiii General Requirements WORK ITEM 1: Hull Plating (U/W Body), Inspect WORK ITEM 2: Hull Plating (U/W Body), Ultrasonic Testing WORK ITEM 3: U/W Body, Preserve (100%) WORK ITEM 4: U/W Body, Preserve (Partial - Condition A) WORK ITEM 5: Appendages (U/W), Leak Test WORK ITEM 6: Appendages (U/W) - Internal, Preserve WORK ITEM 7: Chain Locker(s), Clean and Inspect WORK ITEM 8: Tanks (Mp Fuel Stowage And Overflow), Clean And Inspect WORK ITEM 9: Tanks (Mp Fuel Service), Clean And Inspect WORK ITEM 10: Tanks (Hydraulic Oil Stowage And Service), Clean And Inspect WORK ITEM 11: Tanks (Potable Water), Clean and Inspect WORK ITEM 12: Tanks (Lube Oil), Clean and Inspect WORK ITEM 13: Tanks (Ballast), Clean and Inspect WORK ITEM 14: Voids (Accessible), Clean and Inspect WORK ITEM 15: Tanks (Dirty Oil and Waste), Clean and Inspect WORK ITEM 16: Propellers, Remove, Inspect, and Reinstall WORK ITEM 17: Box Coolers, Clean, Inspect, and Test WORK ITEM 18: Fathometer Transducer, General Maintenance WORK ITEM 19: Underwater (Speed) Log Transducer(s), Service and Inspect WORK ITEM 20: Sea Valves and Waster Pieces, Overhaul or Renew WORK ITEM 21: Fixed CO2 Cylinders, Weight & Test WORK ITEM 22: Galley APC System, Test, Service, Renew Fuse-Able Link WORK ITEM 23: Bow Thruster Unit, Inspect WORK ITEM 24: Bow Thruster Unit AC Motor, Clean and Inspect WORK ITEM 25: Anchor Chain(s) and Ground Tackle, Inspect and Repair WORK ITEM 26: Sewage Vacuum Pumps, Overhaul WORK ITEM 27: Grey Water Holding Tank(s), Clean and Inspect WORK ITEM 28: Sewage Holding Tank(s), Clean and Inspect WORK ITEM 29: Cathodic Protection / Zinc Anodes, Renew WORK ITEM 30: Impressed Current Cathodic Protection System, Inspect and Maintain WORK ITEM 31: Impressed Current Cathodic Protection System Anodes, Renew WORK ITEM 32: Impressed Current Cathodic Protection System Reference Cells, Renew WORK ITEM 33: Impressed Current Cathodic Protection System Dielectric Shield, Repair WORK ITEM 34: Impressed Current Cathodic Protection System Dielectric Shield (Capastic Fairing), Renew WORK ITEM 35: Drydock WORK ITEM 36: Temporary Services, Provide (For Azipod Tech Rep) WORK ITEM 37: Temporary Services, Provide - Tender WORK ITEM 38: Sea Trial Performance, Support, Provide WORK ITEM 39: Azipod Propulsion System Planned Drydock Maintenance (Azipod Removed), Support147 WORK ITEM 40: Sewage Holding Tank, Repair iii (Rev-0)
WORK ITEM 41: Provide Access to Various Compartments for Ship’s Structure and Machinery Evaluation Board (SSMEB) Inspection
WORK ITEM 42: Vent Ducts (Engine And Motor Room All), Commercial Cleaning WORK ITEM 43: Vent Ducts (Galley and Pantry Room All), Commercial Cleaning WORK ITEM 44: Vent Ducts (Laundry Exhaust), Commercial Cleaning WORK ITEM 45: Vent Ducts (All Other), Commercial Cleaning WORK ITEM 46: Tanks (Grey Water Holding), Preserve “Partial” WORK ITEM 47: Tanks (Ballast), Preserve “Partial” WORK ITEM 48: Chain Locker, Preserve 100% WORK ITEM 49: Tanks (Dirty Oil and Waste), Preserve “Partial” WORK ITEM 50: Tanks (Potable Water), Preserve “Partial” WORK ITEM 51: Hull And Structural Plating (General) - Cracked Steel Welds, Repairs WORK ITEM 52: Hull And Structural Plating (General) - Degraded Weld (Steel), Repair WORK ITEM 53: Voids (Accessible, Weather Deck Exposed), Inspect WORK ITEM 54: Potable Water Pneumatic Tank(s), Clean and Inspect WORK ITEM 55: Tanks (Sewage Holding), Preserve “100%” WORK ITEM 56: Installation of Reverse Osmosis Water System WORK ITEM 57: Fuel Oil Coalescer Isolation Valves, Renew WORK ITEM 58: Air Conditioning System Piping Insulation, Renew iv (Rev-0)
REVISIONS RECORD
This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.
DATE REV# WORK
ITEM#
CHANGES MADE
NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.
v (Rev-0)
CONSOLIDATED LIST OF REFERENCES
The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at the time of specification writing and during contract execution.
All Coast guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – from links located on the SFLC website. Commercial sites provide access to their respective documents.
COAST GUARD DRAWINGS
Coast Guard Drawing 240 WLBB 111-001, Rev C, Shell Expansion
Coast Guard Drawing 240 WLBB 114-001, Rev B, Skeg A and D
Coast Guard Drawing 240 WLBB 114-002, Rev B, Forward Skeg Appendages
Coast Guard Drawing 240 WLBB 201-001, Rev E, Machinery Spaces Arrangement
Coast Guard Drawing 240 WLBB 201-002, Rev B, Equipment Access and Removal Plan
Coast Guard Drawing 240 WLBB 245-003, Rev A, Propeller Drawing
Coast Guard Drawing 240 WLBB 256-003, Rev B, Main Engine Cooling System A & D
Coast Guard Drawing 240 WLBB 264-001, Rev D, Lube Oil System Diagram
Coast Guard Drawing 240 WLBB 320-003, Rev F, Power System Deck Plan (First Platform)
Coast Guard Drawing 240 WLBB 330-002, Rev E, Lighting System Deck Plan (First Platform)
Coast Guard Drawing 240 WLBB 437-007, Rev D, HVAC Contrals WDP
Coast Guard Drawing 240 WLBB 512-001, Rev E, HVAC Diagram
Coast Guard Drawing 240 WLBB 529-1, Rev E, Ballast System Diagram
Coast Guard Drawing 240 WLBB 533-001, Rev F, Potable Water System Diagram
Coast Guard Drawing 240 WLBB 555-001, Rev D, Fire Extinguishing System Diagram CO2
Coast Guard Drawing 240 WLBB 568-001, Rev -, Bow Thruster Arrangement and Detail
Coast Guard Drawing 240 WLBB 581-001 Rev B, Anchor Handling System Arrangement
Coast Guard Drawing 240 WLBB 582-001, Rev G, Mooring and Towing A&D
Coast Guard Drawing 240 WLBB 593-001, Rev D, Sewage System Diagram
Coast Guard Drawing 240 WLBB 593-005, Rev G, Sewage System A&D
Coast Guard Drawing 240 WLBB 601-001, Rev L, Inboard & Outboard Profile, Plan View, Tankage Arrgt
Coast Guard Drawing 240 WLBB 601-002, Rev F, Booklet of General Drawings
Coast Guard Drawing 240 WLBB 633-001, Rev D, Cathodic Protection
Coast Guard Drawing 240 WLBB 633-002, Rev C, ICCP and ICAF Block Wiring Diagram and Deck Plan
Coast Guard Drawing 240 WLBB 801-001, Rev E, Line Plans
Coast Guard Drawing 240 WLBB 801-003, Rev G, Curves of Form
Coast Guard Drawing 240 WLBB 801-005, Rev A, Tank CAPACITY - 95% Curves vi (Rev-0)
Coast Guard Drawing 240 WLBB 801-015, Rev C, Scantlings Decks & Platforms
Coast Guard Drawing 240 WLBB 804-006, Rev E, Docking Plan
Coast Guard Drawing 240-WLBB 163-2, Rev -, Reverse Osmosis System Sea Chest And Foundation
Coast Guard Drawing 240-WLBB 256-1, Rev B, Main Engine Freshwater Cooling System Diagram
Coast Guard Drawing 240-WLBB 256-3, Rev -, Main Engine Cooling System A/D
Coast Guard Drawing 240-WLBB 320-1, Rev M, Electrical One Line Diagram
Coast Guard Drawing 240-WLBB 531-1, Rev -, Reverse Osmosis System
Coast Guard Drawing 240-WLBB 261-001, Rev D, Fuel Oil Service System Diagram
Coast Guard Drawing 240-WLBB 261-003, Rev B, Fuel Oil Service System A/D
Coast Guard Drawing 240-WLBB 541-001, Rev D, Fuel Oil Transfer Diagram
Coast Guard Drawing 240-WLBB 541-003, Rev D, Fuel Oil Transfer System A/D
Coast Guard Drawing 240-WLBB 601-001, Rev L, Inboard and Outboard Profile
Coast Guard Drawing 240-WLBB 601-002, Rev F, Booklet of General Drawings
Coast Guard Drawing 240-WLBB 601-002, Rev F, Inboard and Outboard Profile
Coast Guard Drawing 240-WLBB 631-001, Rev D, Paint Schedule
Coast Guard Drawing 240-WLBB 635-001, Rev E, Hull Insulation Schedule
Coast Guard Drawing 240-WLBB 801-018, Rev B, Scantlings Profile
Coast Guard Drawing, 240 WLBB 508-1, Thermal Insulation for machinery, equipment and piping
Coast Guard Drawing, 240 WLBB 514-1, Rev E, Chilled Water System Diagram
Coast Guard Drawing, 240 WLBB 514-3, Rev D, Chilled Water System A/D
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jan 2014, Coatings and Colors Manual
Coast Guard Technical Publication (TP) 3713, SWBS 568, May 2007, Bow Thruster
Coast Guard Technical Publication (TP) 3724, Jun 2004, Vacuum Sewage System - Model JETS 50MBA
Coast Guard Technical Publication (TP) 3729, Jan 2009, Azipod Propulsion and Steering System
Coast Guard Technical Publication (TP) 3730, Dec 2005, Azipod Propulsion and Steering System
Coast Guard Technical Publication (TP) 3731, Jan 2009, Azipod Propulsion and Steering Systems
Coast Guard Technical Publication (TP) 3771, Mar 2007, Change 1, SWBS Group 633
Coast Guard Technical Publication (TP) 3783, Aug 2006, Doppler Speed Log
Coast Guard Technical Publication (TP) 3796, Section B, Aug 2006, Galley Hood
Coast Guard Technical Publication (TP) 3803, SWBS 256, Mar 2008, Circulating and Sea Water System
Coast Guard Technical Publication (TP) 3811, Rev –, CO2 Fire Extinguishing System – Model 95206
International Organization for Standardization (ISO) 484/2, 1981, Shipbuilding - Ship Screw Propeller - Manufacturing tolerances - Part 2: Propellers of Diameter Between 0.80 and 2.50m, Inclusive
Naval Ships’ Technical Manual (NSTM) Chapter 555, Jan 2010, Volume 1, Revision 13, Surface Ship Firefighting
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and Allied Processes vii (Rev-0)
Surface Forces Logistics Center Standard Specification 3020 (SFLC Std Spec 3020), 2014, Overhaul AC Electrical Motors
Surface Forces Logistics Center Standard Specification 3041 (SFLC Std Spec 3041), 2014, Shipboard Electrical Cable Test
Surface Forces Logistics Center Standard Specification 3042 (SFLC Std Spec 3042), 2014, Shipboard Electrical Cable Removal, Relocation, Splice, Repair, and Installation
Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2014, Auxiliary Machine Systems
Surface Forces Logistics Center Standard Specification 5100 (SFLC Std Spec 5100), 2014, Clean Shipboard Ventilation Systems
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures
Surface Forces Logistics Center Standard Specification 8634 (SFLC Std Spec 8634), 2014, Drydocking
Surface Forces Logistics Center Standard Specification 8635 (SFLC Std Spec 8635), 2014, Temporary Services
Surface Forces Logistics Center Standard Specification 8636 (SFLC Std Spec 8636), 2014, Temporary Hull Accesses
Tech Pub E-424-014, Bathy-1500 Survey Echo Sounder
OTHER REFERENCES
ABB OY, Marine and Turbocharging, Azipod service works for USCGV Mackinaw during dry docking on 2018, Document No. 9271054, Rev 4
American Bureau of Shipping (ABS) 2, 2009, Rules for Building and Classing Steel Vessels, Iacs
CORR1
American Bureau of Shipping (ABS) Approved Chain, Accessory and Bar Manufacturing Facilities List, Oct 2016
American National Standards Institute (ANSI) B16.11, 2011, Forged Fittings, Socket-Welding and Threaded
American National Standards Institute/American Water Works Association (ANSI/AWWA) C652, 2011, Disinfection of Water-Storage Facilities
American National Standards Institute/NSF International (ANSI/NSF) 61, 2015, Drinking Water System Components - Health Effects
American Society of Mechanical Engineers (ASME) B16.34, 2004, Valves-Flanged, Threaded, and Welding End
ASTM International (ASTM) A182-14b, R2008, Standard Specification for Forged or Rolled Alloy-Steel Pipe Flanges, Forged Fittings, And Valves and Parts for High-Temperature Service
ASTM International (ASTM) A312, R2008, Standard Specification for Seamless and Welded Austenitic Stainless Steel Pipes
ASTM International (ASTM) D1330, 2015, Standard Specification for Rubber Sheet Gaskets
ASTM International (ASTM) D3359, 2009, Standard Test Methods for Measuring Adhesion by Tape Test
ASTM International (ASTM) D4138, 2013, Standard Practices for Measurement of Dry Film Thickness of Protective Coating Systems by Destructive, Cross-Sectioning Means
ASTM International (ASTM) D5363, 2008; Standard Specification for Anaerobic Single-Component Adhesives (An)
ASTM International (ASTM) F992, 2006, Standard Specification for Valve Label Plates viii (Rev-0)
Code of Federal Regulations (CFR) Title 29, Part 1915, Jul 2008, Occupational Safety and Health Standards for Shipyard Employment
Commercial Item Description (CID) A-A-59313, Nov 2003, Thread Compound; Anti-seize, Zinc Dust- Petrolatum
Commercial Item Description (CID) A-A-59588, 2005, Rubber Silicone
Federal Specification (Fed Spec) QQ-N-281, Oct 1985, Nickel-Copper Alloy Bar, Rod, Plate, Sheet, Strip, Wire, Forgings, and Structural and Special Shaped Sections
Federal Specification (Fed Spec) RR-C-271, Rev E, Mar 2016, Chains and Attachments, Carbon and Alloy Steel
Institute of Electrical and Electronics Engineers (IEEE) Standard 45, 2002, Recommended Practice for Electrical Installations on Shipboard
International Organization for Standardization (ISO) 484/2, 1981, Shipbuilding - Ship Screw Propeller - Manufacturing tolerances - Part 2: Propellers of Diameter Between 0.80 and 2.50m, Inclusive
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-58, 2009, Pipe Hangers and Supports - Materials, Design, Manufacture, Selection, Application, And Installation
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-61, 2003 Edition, Pressure Testing Of Steel Valves
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-67, 2002 Edition, Butterfly Valves
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-72, 1999 Edition, Ball Valves with Flanged or Butt-Welding Ends for General Service
Manufacturers' Standardization Society of the Valve and Fittings Industry (MSS) SP-80, 2008 Edition, Bronze Gate, Globe, Angle and Check Valves
MIL PRF-16173E INT AMD 1, Sep 2006, Corrosion Prevention Compound, Solvent Cut Back, Cold Application
MIL-A-18001, May 2005, Anodes, Sacrificial Zinc Alloy (Commercially Accepted - ASTM B418)
MIL-C-24633, Oct 2014, Chain, Stud Link, Anchor, Low Alloy Steel, Flash Butt Welded
MIL-DTL-1222, Dec 2000, Studs, Bolts, Screws and Nuts for Applications Where a High Degree of Reliability Is Required
MIL-DTL-23549, Sep 2016, Grease, General Purpose
MIL-PRF-16173, Sep 2006, Corrosion Prevention Compound, Solvent Cut-Back, Cold-Application
MIL-S-45180, 1998; Sealing Compound, Gasket, Hydrocarbon Fluid and Water Resistant
MIL-T-16420K(1), Tube, Copper-Nickel Alloy, Seamless and Welded (Copper Alloy Numbers 715 and 706), 9/16/1988
Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2013, Cork and Rubber Composition Sheet; For Aromatic Fuel and Oil Resistant Gaskets
The Society for Protective Coatings (SSPC) Surface Preparation Specification No. 1 (SSPC-SP 1), 2015, Solvent Cleaning
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.3 (SSPC-SP 3), 2004, Power Tool Cleaning
The Society for Protective Coatings (SSPC), January 2015, Paint Application Specification No. 2 (PA-2), Procedure for Determining Conformance to Dry Coating Thickness Requirements
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP 10/NACE No.2, 2007, Near-White Blast Cleaning ix (Rev-0)
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP 6/NACE No. 3, 2007, Commercial Blast Cleaning
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP WJ-2/NACE WJ-2, 2012, Waterjet Cleaning of Metals – Very Thorough Cleaning
The Society for Protective Coatings SSPC-SP 10/NACE No.2, Jan 2007, Near-White Blast Cleaning
The Society for Protective Coatings SSPC-SP 11, Jul 2012, Power Tool Cleaning to Bare Metal x (Rev-0)
CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY
The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.
WORK
ITEM
MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED
COST
($/UNIT)
16 Y **Propeller (right hand)
NSN: 2010-01-518-9869 PN:
3AFV5600561
1 ea. 160,099.00
16 Y ** Propeller (left hand) NSN: 2010-01-519-0135 PN:
3AFV5600562
1 ea. 160,099.00
16 Y Wrench, Propeller Nut NSN: 5120-01-F13-3508 PN:
3AFV5601719
1 ea. 450.00
18 Y ***Fathometer Transducer, Shallow
Water, 200 kHz
NSN: 6625-XF-C16-7152 PN:
TH200-3UAW (Odom
Hydrographic)
1 ea. 19,995.00
23 N Shaft Seal PN: P05413 1 ea. 7362.42 31 N Anode, elliptical, platinum & niobium,
37.5 A
NSN: 5342-01-540-3444 4 ea. 3,525.00
31 N Shell, mounting PN: Siemens Water Technologies W2T98554 (Electrocatalytic 74226)
1 ea. 264.50
31 N Mat, neoprene Siemens Water Technologies W2T98553 (Electrocatalytic
74225) NSN: 5330-01-540-
1 ea. 35.26
31 N Nut/washer, molded PN: Siemens Water Technologies W3T106648
(Electrocatalytic 73547)
6 ea. 35.14
32 N Reference electrode, silver & silver chloride
Siemens Water Technologies
W3T105013 (US Filter Electrocatalytic 32622-
050)
NSN: 5977-01-346-0750 2 ea. 1,300.02
35 Y *Transducer Cover Plate
N/A 4 ea. 50.00
35 Y Drydock support kit 4730-01-F13-3430 1 ea. 11,300
N Flushing Mineral Oil - Kluber Gem 1-46N (or equivalent)
NSN: N/A
PN: N/A
175 Gal. $130.00
39 N Castrol Bio-Tac EP 2
Grease
NSN: N/A
PN: N/A
10 gal. $55.00
39 Y Propeller nut wrench
NSN:5120-01-F13-3508
PN: 5601719
1 ea. Unknown
39 Y Lifting nut PN: 5600311 8 ea Unknown
39 N Bearing, Azipod Thrust
NSN: 3110-01-525-4672
PN: 11G 5937011
2 ea. $223,000.00 xi (Rev-0)
39 N Nut, Thrust Bearing
Outer Loc
NSN: 5310-01-F13-3152
PN: ANN-0027
2 ea. $13,000.00
39 N Nut
NSN: 5310-01-F13-3151
PN: ANN-0028
2 ea. $13,000.00
39 N Sleeve, Shaft
NSN: 3040-01-F13-3150
PN: LW-7438844 / v21
2 ea. $14,000.00
39 N Distance/Locking Ring
Set, Thr
NSN: 5365-01-F13-3155
PN: 11G5939393
2 ea. $17,000.00
39 N Distance/Locking Ring
Set, Thr
NSN: 5365-01-F13-3155
PN: 11G5939394
2 ea. $17,000.00
39 N Washer, BRB 13 x 24 x 2
NSN:
PN: SS 3567
12 ea. Unknown
39 N Screw, hex head, m65 12 x 45
NSN:
PN: ISO 4017 8.8
12 ea. Unknown
39 N Washer, BRB 25 x 45 x4
NSN:
PN: SS 3567
60 ea. Unknown
39 N Disc spring 50 x 25.4 x3
NSN:
PN: SKF SCHNORR 014800
240 ea. Unknown
39 N Washer, 58 x 25 x10
NSN:
PN: TBRSUB
60 ea. Unknown
39 N Screw, hex head, M65 24 x 180
NSN:
PN: ISO 4014 8.8
60 ea. Unknown
39 N Radial Sealing Assembly
NSN:
PN: CR KSWE0127 241-3853
2 ea. Unknown
39 N Bearing, Azipod
Propeller
NSN: 3110-01-525-4706
PN: C3096 KW
2 ea. $25,019.50
39 N Adapter sleeve OH 3096
HB
NSN:
PN: OH 3096 HB
2 ea. Unknown
39 Y Propeller nut lift tool NSN:5120-01-F13-3546 1 ea. Unknown
39 N Lip seal slewing bearing
NSN: 5330-01-F13-3113
PN: 9879286
6 ea. Unknown
39 N Slewing bearing
NSN:3110-01-F13-3112
PN: 94690 TR/TR
2 ea. Unknown
N
Face-type Shaft Seal, DSS, type GA of 450
MOD 420, Drw. H75052-
NSN:
PN: H705052-01
2 ea. $132,521
39 N Ice bearing, bronze
5601693
NSN: 3110-01-F18-5550
PN: 3AFV9938571
2 ea. Unknown
39 N Steering seal liner
NSN:5330-01-F13-3118
PN: 5601692
2 ea. Unknown
39 N Lube oil filters
NSN:
PN: 478 3233-622
16 ea. Unknown
39 N Inspection hatch gasket
NSN:5330-01-F13-3423 PN:
3AFV5601842
6 ea. $91.11
56 N US Watermaker RO Plant NSN: 4610-01-F15-4243 1 ea. 145,000 57 N 1†Gate Valve (Body
A105N, Forged Steel, Welded)
PN: 501-S-5-8-A-08 (BERIC®) 2 ea. 100.00
*Government-loaned property, which shall be returned to the vessel upon completion of the availability.
**New or refurbished equipment that the Government may provide for installation in place of existing equipment.
***Government-furnished property, which is to be supplied by either the vessel or the C4IT ServiceCenter xii (Rev-0)
CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS
The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5 (Inspection report particulars)):
Work Item
Title
2 Hull Plating (U/W Body), Ultrasonic Testing
3 U/W Body, Preserve (100%)
5 Appendages (U/W), Leak Test
23 Bow Thruster Unit, Inspect
24 Bow Thruster Unit AC Motor, Clean and Inspect
25 Anchor Chain(s) and Ground Tackle, Inspect and Repair
30 Impressed Current Cathodic Protection System, Inspect and Maintain
Provide Access to Various Compartments for Ship’s Structure and Machinery Evaluation Board (SSMEB) Inspection
53 Voids (Accessible, Weather Deck Exposed), Inspect xiii (Rev-0)
PRINCIPAL CHARACTERISTICS
240' WLBB (CGC MACKINAW)
PHYSICAL
Length overall 240’ 0” Depth (main deck at side to baseline) 24' 0" Maximum beam 58’ 0” Height of highest Projection (above
DWL)
95' 6"
Full load draft 15’ 6” LCF Draft Full load displacement (icebreaking) 3427.82 Long Tons Freshwater Shore tie voltage requirements 1,200 Amp total
3EA 400A 450VAC 3PH
Ungrounded forward/aft stations
HULL
Frame spacing FR 19-25 = 19"
FR 33-39 = 21"
ALL Else = 20"
MACHINERY
Number of propellers 2 Number of blades per propeller 4 Diameter of propeller 10.25' Pitch 96.98" RPM 226 rated 270 max Shafting/propulsion system Azipod
TANK CAPACITIES
Diesel oil 115,538 gal.
Fresh water capacity 27,948 gal.
Hydraulic oil capacity 696 gal.
Lube oil storage 1,159 gal.
Grey water tank 27, 080 gal.
Sewage holding tank 5,313 gal.
1 (Rev-0)
00000_0618_FLT
REC_00000_FLT_Commercial Project @ Contractor’ Facility (1212)
General Requirements
1. SCOPE
1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed at a commercial contractor’s facility for Coast Guard vessels.
1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and 'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.
2. REFERENCES
COAST GUARD DRAWINGS
None
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and Allied Processes
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures
OTHER REFERENCES
None
3. REQUIREMENTS
3.1 General. The Contractor shall conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability.
NOTE
The requirements of paragraph 3.1 (General) applies to all work under the scope of this contract, whether explicitly stated in work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.
2 (Rev-0)
3.2 Contractor-provided fire watch personnel. The Contractor shall provide fire watch personnel and equipment.
3.3 Preservation requirements. The Contractor shall accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.
3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec 6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).
3.3.2 Coating colors and system color schemes. Ensure that all colors and color coat/paint schemes are in accordance with COMDTINST M10360.3, Chapter 6 (Cutter and Boat Colors Exterior and Interior).
NOTE
Unless a waiver has been granted (in writing) by the KO, deviations from authorized coatings (listed in Appendix C of SFLC Std Spec 6310) and colors and color schemes (provided in Chapter 6 of COMDTINST M10360.3) are strictly prohibited.
3.4 Welding and brazing requirements. The Contractor shall perform all welding and allied processes, and NDE in accordance with SFLC Std Spec 0740.
3.5 Environmental protection requirements. The Contractor shall adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:
3.5.1 Contractor operated (non USCG) facilities. The Contractor shall provide and maintain environmental protection as defined in SFLC Std Spec 0000 Appendix A, Requirements for Environmental Protection at Contractor Operated (Non USCG) Facilities, as applicable, during the performance of this availability. Contractor shall plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor shall comply with applicable Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item shall not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.
3.5.2 Test and procedures. The Contractor shall be required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work shall be done by qualified laboratories; and where required by law, the laboratories shall be certified.
3.5.3 Regulatory notifications. The Contractor shall be responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The Contractor shall submit copies of all regulatory notifications to the Contracting Officer and the local Facility Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications shall be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System (NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.
3.5.4 Environmental manager. The Contractor shall appoint in writing an Environmental Manager for the project, and shall be responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager shall ensure compliance with Hazardous Waste
3 (Rev-0)
Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the Contractors’ Environmental Management Plan; ensure that all environmental permits are obtained, maintained, and closed out; ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas;
ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the Environmental Records binder and required documentation, including environmental permits compliance and close-out.
3.5.5 HW disposal. Contractor shall comply with SFLC Std Spec 0000 Appendix A, Requirements For Environmental Protection At Contractor Operated (Non USCG) Facilities for HW disposal.
3.6 Local Policy. None.
3.7 SFLC standard specification approved changes. The Contractor shall be aware that the following are approved changes to published SFLC 2014 Edition Standard Specifications and supersede published content:
3.7.1 Change to SFLC Std Spec 0000, paragraph 1.3. ‘Acronyms and term definitions’, page 5, “PCL (Paint Containing Lead)” definition replaced by, “Any paint or coating containing lead in excess of 0.009 percent by weight (1.0 mg/cm2 or 90 ppm). Lead Based Paint (LBP) is an interchangeable term with PCL.”
3.7.1.1 Change Std Spec 0000 paragraph 3.2.4.2.3(QP 1 inspector or tech rep duties) bullet, “Determine when applied coats have sufficiently cured for overcoating or for system service resumption (see paragraph 3.1.19 of SFLC Std Spec 6310 (Critical drying time requirements)).” to “Determine when applied coats have sufficiently cured for overcoating or for system service resumption (see paragraph 3.1.17 of SFLC Std Spec 6310 (Critical drying time requirements)).”
3.7.2 Change to Std Spec 5000, paragraph D2.2.1.1 bullet, "For running rigging, furnish class 6x37, uncoated, independent wire rope core (IWRC), right regular lay (RRL) wire rope or Dyform-18, rotation resistant wire rope," to "For running rigging, furnish class 6x36, uncoated, independent wire rope core (IWRC), right regular lay (RRL) wire rope or Dyform-18, rotation resistant wire rope."
3.7.2.1 Change to Std Spec 5000, page D-2, Table D-1 title from "DYFORM-18, 6X19 AND 6X37 IWRC RRL," to " DYFORM-18, 6X19 AND 6X36 IWRC RRL"
4. NOTES
4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.
4 (Rev-0)
QA-1 - QUALITY ASSURANCE INSPECTION FORM
(PRESERVATION CHECKLIST)
VESSEL NAME HULL # WORK ITEM
WORK ITEM TITLE
LOCATION OF WORK (INCL. FRAME #’S) AREA (SQFT)
CHECKPOINT 1 – COATING SYSTEM COMPLIANCE
Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.
CHECKPOINT 2 - PAINT STORAGE
Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfgr.
CHECKPOINT 3 - AMBIENT CONDITIONS
Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).
Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).
Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfgr.
CHECKPOINT 4 - PRE-SURFACE PREPARATION
Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.
Verify equipment setup, blast media, and surface preparation methods match designated test coupon.
CHECKPOINT 5 - SURFACE PREPARATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).
Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.
Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).
CHECKPOINT 6 - PRIMER COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Verify proper mixing and stand-in (induction) times.
Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.
Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).
Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.
Brush out all runs, sags, drips, and puddles.
Perform visual inspection for holidays and other defects.
CHECKPOINT 7 – STRIPE COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).
CHECKPOINT 8 – TOP COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
Verify proper mixing and stand-in (induction) times, as applicable.
Verify wet film thickness at random, to prevent under or over application.
Brush out all runs, sags, drips, and puddles.
CHECKPOINT 9 – FINAL INSPECTION
Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.
Ensure that system cure is in accordance with manufacturer's recommendation for intended service.
Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.
For immersion coatings (including tank U/W body), record date and time of the following events:
Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____
CHECKPOINT 10 – RECORD KEEPING
Complete, sign, and submit all provided QA Inspection Forms.
NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE / TIME
5 (Rev-0)
QA-2 - QUALITY ASSURANCE INSPECTION FORM
(ENVIRONMENTAL READINGS)
VESSEL NAME HULL #
WORK ITEM
Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.
DATE
TIME
ACTIVITY (SURFACE
PREPARATION, PRIMER COAT,
BARRIER COAT, TOP COAT,
ETC…)
LOCATION (FRAME &
DECK, RELATION TO
EQUIPMENT, ETC.)
TEMPERATURE % REL.
HUMID-
ITY
DEW
PT.
SURFACE AMBIENT ΔT
| DP -
SURFACE |
NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE / TIME
6 (Rev-0)
QA-3a - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)
VESSEL NAME HULL # WORK ITEM
SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)
MIN MAX MEAN
SSPC-SP-10/NACE No. 2
SSPC-SP WJ-1/NACE WJ-1
SSPC-SP WJ-2/NACE WJ-2
SSPC-SP WJ-3/NACE WJ-3
SSPC-SP WJ-4/NACE WJ-4
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)
ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:
PLACE SURFACE PROFILE REPLICA TAPES IN THE SPACES PROVIDED BELOW, TO SERVE AS
PERMANENT QA RECORD. MAINTAIN A SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS
DIVIDED INTO SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
MEAN MIL READING (IAW ASTM D4417-METHOD C) FOR ABOVE 15 READINGS:
NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE /
TIME
7 (Rev-0)
QA-3b - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)
VESSEL NAME HULL # WORK ITEM
SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)
MIN MAX MEAN
SSPC-SP-10/NACE No. 2
SSPC-SP WJ-1/NACE WJ-1
SSPC-SP WJ-2/NACE WJ-2
SSPC-SP WJ-3/NACE WJ-3
SSPC-SP WJ-4/NACE WJ-4
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)
ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:
RECORD MEASUREMENTS TAKEN IN THE SPACES PROVIDED BELOW, TO SERVE AS PERMANENT QA
RECORD. MAINTAIN SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS DIVIDED INTO
SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Mean Reading (mils)
Mean Reading (mils) IAW ASTM DD4417).
8 (Rev-0)
QA-4 - QUALITY ASSURANCE INSPECTION FORM
(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)
VESSEL NAME HULL # WORK ITEM
SOLUBLE SALT CONDUCTIVITY MEASUREMENTS IAW SSPC-GUIDE 15.
DATE TEST LOCATIONS CONDUCTIVITY (MICROSIEMENS/CM)
9 (Rev-0)
QA-5 - QUALITY ASSURANCE DATA FORM
(COATING THICKNESS)
(Use one sheet for each sequence)
VESSEL NAME HULL #
WORK ITEM
COATING MFG PRODUCT NAME
BATC
H #
INDUCTI
ON TIME
COATING SYSTEM
SEQUENCE
(PRIMER/TOUCHUP/3RD
COAT, ETC.)
DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC-PA 2.
SPOT 1 2 3 4 5
AVERAGE
VALUE
*BASE METAL READING
(BMR) Required, If Magnetic Pull-Off (Type I/Banana) Gauge Is Used.
LOCATION (FRAME REFERENCE):
SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS
1 AVG. BMR DEVIATION
3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS
AVG.
1 AVG. BMR DEVIATION
1 AVG. BMR DEVIATION
APPLICATION METHOD (AIRLESS,
CONVENTIONAL SPRAY, ROLLED)
AVERAGE DFT
10 (Rev-0)
11000_1016_FLT
REC_11000_UWHIB_FLT_240’ WLBB (30 CGC MACKINAW) (1211)
WORK ITEM 1: Hull Plating (U/W Body), Inspect
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to inspect/survey the vessel’s Under Water (U/W) hull plating, including U/W appendages and coating system.
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 240 WLBB 804-006, Rev E, Docking Plan
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements
OTHER REFERENCES
ASTM International (ASTM) D4138, 2013, Standard Practices for Measurement of Dry Film Thickness of Protective Coating Systems by Destructive, Cross-Sectioning Means
The Society for Protective Coatings (SSPC), January 2015, Paint Application Specification No. 2 (PA-2), Procedure for Determining Conformance to Dry Coating Thickness Requirements
3. REQUIREMENTS
3.1 General.
3.1.1 CIR.
None.
3.1.2 Tech Rep.
Not applicable.
3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and
11 (Rev-0) protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.
3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).
3.2 Inspection. The Contractor shall accompany the Underwater Hull Inspection Board (UWHIB) in the performance of the below inspection tasks, as applicable, using the drawings listed in Section 2 (References) as guidance. The Contractor shall provide the following, to facilitate the UWHIB in assessing the condition of the designated U/W hull components and systems:
A hull repair supervisor and a marker.
Temporary staging and other necessary equipment, as applicable, for ensuring safe access to all areas of the U/W hull.
NOTES
1. The COR will convene the UWHIB as soon as possible after the vessel has been dry-docked and before any work (except U/W hull cleaning/wash down) is performed on the U/W hull and appendages.
2. Some of the components and/or systems addressed in this work item may not be applicable to all vessel classes.
3.2.1 Hull plating. Inspect the condition of the hull plating (including thruster tunnel plating, as applicable), for the presence of marine growth, deformation, and any evidence of major corrosion or electrolytic action.
3.2.1.2 Inspect the hull and keel areas, report on the condition of butt-welded seams, doubler plates, lap seams, and for any signs of damaged plating or unusual waviness in the plating.
3.2.2 Sea chests and all other cooling system intake components. Inspect all sea chests, sea beam arrays, tunnels, hull openings, and grates for general appearance, loose, damaged, or missing grates, loose or missing fasteners, condition of sea strainers and lockwire on bolts, marine growth on grating slots, and any obstructions in the openings that might prevent proper suction and discharge of water.
3.2.3 Rudders. Check general condition, condition around the drain plugs, and check for pitting, if any, on the leading and trailing edges.
3.2.4 Propeller and shaft associated components. Inspect the condition of propellers for signs of corrosion, pitting, erosion, fouling, cracks, dings, and nicks by side and blade; inspect fairwaters, rope guards, shafts, and mechanical seals - look for missing screws, physical damage to the blades, pitting, condition of dunce caps, and condition of securing devices.
3.2.5 Transducers. Check general condition for cuts, cracks, corrosion, and surface defects around the openings. Check transducer securing nuts for tightness, and inspect cables for chafing and other damage.
3.2.6 Zinc anodes. Remove all marine growth and oxide coating from all hull, rudder, shaft strut, sea chest, sea beam array, z-drive, and thruster tunnel zinc anodes, or water jet drives anodes, as applicable, using a light-wire brush.
12 (Rev-0)
3.2.6.1 Visually inspect all zinc anodes; check the soundness of mounting strap and stud welds, missing fasteners, and percentage of remaining material.
3.2.7 Coating system inspections. Accomplish the below inspections, in conjunction with the underwater hull inspection conducted by the Underwater Hull Inspection Board (UWHIB). Document the condition found as “Partial - Condition A”, “Partial - Condition B”, or “100%”, as applicable (see 4.1 (Definitions)). Submit a CFR.
NOTE
The following inspections are for determining the existing condition of the coating system for the underwater body surfaces, which are deemed “Critical-coated” surfaces; they must be carried out by a SSPC-QP-1 certified contractor/sub-Contractor or a NACE Inspector – see SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces”).
3.2.7.1 Visual. Perform a visual inspection of the existing U/W body coating system.
3.2.7.2 Dry film thickness (DFT) measurements. Take total DFT measurements of the U/W body coating system, in accordance with SSPC-PA 2.
4. NOTES
4.1 Definitions. 4.1.1 "Partial – Condition A”: The condition that exists where the substrate is exposed in up to 33% of the entire U/W body.
4.1.2 "Partial - Condition B": The condition that exists where the coating system has incurred damage, but the substrate is not exposed in any location.
4.1.3 "100%”: The condition that exists where more than 33% of the U/W body hull substrate is exposed.
4.2 UWHIB convention. The COR will convene the UWHIB as soon as possible after the vessel has been dry-docked and before any work (except U/W hull cleaning/wash down) is performed on the U/W hull and appendages.
13 (Rev-0)
11010_UT_0617_FLT
REC_11010_UT_FLT_240’ WLBB (30 CGC MACKINAW) (0911)
WORK ITEM 2: Hull Plating (U/W Body), Ultrasonic Testing
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to conduct ultrasonic testing (UT) of U/W hull plating.
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 240 WLBB 111-001, Rev C, Shell Expansion
Coast Guard Drawing 240 WLBB 804-006, Rev E, Docking Plan
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and Allied Processes
OTHER REFERENCES
None.
3. REQUIREMENTS
3.1 General.
3.1.1 CIR. The Contractor shall submit a CIR for the inspections listed in the following paragraph:
3.2 (UT measurements).
3.1.2 Tech Rep.
14 (Rev-0)
3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.
3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).
3.2 UT measurements. The Contractor shall perform a total of 50 UT measurements of U/W hull surfaces, in locations designated by the Coast Guard Inspector, using Coast Guard Drawing 240 WLBB 804-006 and 240 WLBB 111-001 for guidance, in accordance with SFLC Std Spec 0740, Appendix C. Mark up a copy of Coast Guard Drawing 240 WLBB 111-001 to show all locations selected for measurement and record all measurements in Table I (UT Measurements Summary Sheet - Port/Stbd Shell) provided at the end of this item. Submit A CIR, to also include the marked up drawing and completed Table I.
4. NOTES
4.1 UT Table. Table 1 provided below is for the recording of all UT measurements.
15 (Rev-0)
TABLE 1 - UT MEASUREMENTS SUMMARY SHEET PORT/STBD SHELL
SHOT # STRAKE # FWD/MID/AFT ORIG PL MEASURED PL PERCENT
PLATE # TOP/MID/BOT THICKNESS THICKNESS WASTAGE
16 (Rev-0)
63130_0617_FLT
REC_63130_100Percent_FLT_240' WLBB (30 CGC MACKINAW) GREAT LAKES (0413)
WORK ITEM 3: U/W Body, Preserve (100%)
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to preserve U/W body surfaces.
NOTES
1. The purpose of the preservation tasks covered by this item is to completely remove all existing coatings and recoat the U/W body surfaces with a new coating system.
2. U/W body surfaces are as defined in 4.1 (Definitions) and exclude areas covered by docking blocks, unless the vessel is fleeted for the express purpose of preserving blocked areas.
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 240 WLBB 601-001, Rev L, Inboard & Outboard Profile, Plan View, Tankage Arrgt
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures
OTHER REFERENCES
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.1 (SSPC-SP 1), 2015, Solvent Cleaning
3. REQUIREMENTS
3.1 General.
17 (Rev-0)
3.1.1 CIR. The Contractor shall submit a CIR for the inspections listed in the following paragraph(s):
3.2.3 Post-surface preparation cleaning and inspection
3.1.2 Tech Rep. The Contractor shall refer to SFLC Std Spec 0000, paragraphs 3.2.4.2.1 (Painting contractor certification program requirement) and 3.2.4.2.2 (Coating Tech Rep), for applicable requirements.
3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness. Specific areas/equipment/components to be protected include, but are not limited to:
All scuppers and overboard discharges.
Waterline area where U/W body coating system interfaces with freeboard coating system (unless freeboard surfaces are also being preserved).
Fathometer transducer surfaces.
Sea valve openings.
Propeller shaft bearings and seals.
Rudder bearings.
AZIPOD system components.
Zinc anodes (unless anodes are being renewed).
3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the following:
Sea chest grating.
Azipod work
Freshwater cooling components and hoses
Blocking configuration
3.1.5 Initial inspection. Prior to removing the existing coating system, the Contractor shall inspect and verify whether all draft marks have permanent markings (weld beads or impressions), showing their location on the hull.