FOUNDRY_HOOKS_70Z08519QDA17200_AMENDMENT_003.docx

DOCX document 25 KB Posted

Attached to
LIFTING HOOKS
Solicitation number
70Z08519QDA17200
Issued by

About this file

Standard Form 30 - Amendment of Solicitation

View the file

Other files

Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE
PAGE 1
OF PAGES 3
2. AMENDMENT/MODIFICATION NO. 0003
3. EFFECTIVE DATE

06 AUGUST 2019

4. REQUISITION/PURCHASE REQ. NO.
5. PROJECT NO. (Ifapplicable)

6. ISSUED BY CODE

USCG SURFACE FORCES LOGISTICS

300 EAST MAIN STREET, SUITE 600

NORFOLK, VA. 23510

52000
7. ADMINISTERED BY (If other than Item 6)CODE

CENTER

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP code)
(X)
9A. AMENDMENT OF SOLICITATION NO.

70Z08519QDA17200

9B. DATED (SEE ITEM 11)

06 AUGUST 2019

IOA. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE
FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers X is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended. by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACTIORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM IOA.

B. THE ABOVE NUMBERED CONTRACTIORDER ts MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.1030.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type ot modification and authority)

E. IMPORTANT: Contractor [2 is not, X] is required to sign this document and return 1 copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

LIFTING HOOKS

The purpose of this modification 0003 to this combined synopsis and solicitation is to provide the question received along with the answer.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or IOA as heretofore changed, remains unchanged and in full force and effect, 15A. NAME AND TITLE OF SIGNER (Type or print)

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print) Patrick D. Brown

15B. CONTRACTOR/OFFEROR
15C. DATE SIGNED
16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

(Signature of person authorized to sign)

NSN 7540-01-152-8070STANDARD FORM 30 (REV.
Previous edition unusablePrescribed by GSA FAR (48 CFR) 53.243

CONTINUATION SHEET

RFQ: 7008519QDA17200

AMENDMENT 0003

Continuation of SF 30, Block 14, Question 1: Section 3.3.2 of Specification P-573-2033 states. ‘any hook design deviations from the Coast Guard provided design parameters shall be approved by the KO.’

Shall this design change be brought to the KO now or if awarded, at that time?

Answer 1: Yes, it can be provided now. Section 3.3.2 revised to “Any hook design deviations from the Coast Guard provided design parameters shall be brought to the attention of the KO, bur approved by Technical.” Revised Specification attached.

Question 2: Section 3.3.8 of Specification P-573-2033 states. ‘each hook shall then be epoxy coated.”

Is 100% of the hook expected to be epoxy coated including the three thru holes (.22” dia, .313” dia, and .75”dia) on each hook?

Answer 2: The .22” dia and .313”dia holes do not have to be painted inside. The .75” hole should be painted inside.

CONTINUATION SHEET

RFQ: 7008519QDA17200

AMENDMENT 0003

Continuation of SF 30, Block 14

Question 3: Quality Assurance and Testing - Destructive Load Tests. Is it a requirement for the Coast Guard Representative be present during each of the Destructive Load Tests, as well?

Answer 3: Yes, the Coast Guard Representative should be present during the Destructive Load Tests.

image1.jpg image2.jpg

File details come from the government source that posted it.