SOW revised - Amendment 1 - 70Z08425QDL950040.docx
DOCX document 36 KB Posted
- Solicitation number
- 70Z08425QDL950040
About this file
This is a Statement of Work (SOW) for replacing the fire alarm system at the United States Coast Guard (USCG) Station in Crisfield, Maryland. The project involves removing the existing 35-year-old fire alarm control panel and associated components, and installing a new addressable fire alarm system, including 30 smoke detectors, 5 heat detectors, 7 pull stations, and 6 alarm/horn strobes. The contractor must be NFPA certified, ensure the new system calls out to local fire departments, and complete a function test with USCG personnel present.
The solicitation is a total small business set-aside with a period of performance not exceeding 60 calendar days. The site visit was scheduled for Tuesday, September 23 at 10:30am Eastern time, with REAL ID required for access. The quote submission deadline was amended to Wednesday, September 24, 2025, at 4pm Eastern. The project will be executed at 810 Norris Harbor Drive, Crisfield, MD 21817, under the Department of Homeland Security US Coast Guard, with work to be performed between 0700 and 1600 EST, Monday through Friday.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation Amendment 3 - 70Z08425QDL950040.docx | DOCX document | |
| Coast Guard Fire Protection Configuration Standard Technical Order.pdf | ||
| Solicitation Amendment 2 - 70Z08425QDL950040.docx | DOCX document | |
| Solicitation Amendment 1 - 70Z08425QDL950040.docx | DOCX document | |
| Solicitation - 70Z08425QDL950040.docx | DOCX document | |
| SOW - 70Z08425QDL950040.docx | DOCX document | |
| WD 2015-4271.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PR 70Z03021PCV215A00
STATEMENT OF WORK
PR 70Z03021PCV215A00
STATEMENT OF WORK
STATEMENT OF WORK (SOW)
for Replace Fire Alarm system/control panel at USCG Station Crisfield/ANT
1.0 GENERAL
The USCG is seeking a contractor to replace the building fire alarm control panel, fire alarm signaling devices, detectors, and pull stations. Prior to submitting a quote, it is mandatory to examine the SOW and it is highly recommended to visit the facility to take field evaluations and become familiar with existing conditions under which the work will be performed.
1.1 BACKGROUND
The existing Fire Alarm panel and system are over 35 years old. Currently the system is fully functioning and current fire panel replacement parts are becoming obsolete. This SOW includes the removal of the old fire alarm control panel along with all detectors and alarming devices connected to the system and replacing/installing a new addressable fire alarm control panel with all new capable detectors and alarming devices ensuring station is up to code for fire.
1.2 SCOPE
· Lockout tagout the equipment
· Removal of old fire panel control panel, detectors, and signaling devices
· Furnish & install fire alarm control panel.
· Furnish & install 30 smoke detectors.
· Furnish & install 5 heat detectors.
· Furnish & install 7 pull stations.
· Furnish & install 6 alarm/horn strobes.
· Ensure fire alarm control panel is tied into Galley/kitchen ANSUL alarm.
· Cost of necessary labor, material for installation.
· Provide equipment for access to panel, signaling device, and detectors.
· Verify proper operation and testing of newly installed system.
· Ensure fire alarm system calls out to local fire departments.
· Before the USCG accepts the work, the contractor will complete a function test of the new Fire Alarm panel system, with USCG POC present.
· Attach annual inspection tag after completion of install & function test.
Equipment Information:
1 – fire alarm control panel 30 – compatible smoke detectors 5 – compatible heat detectors 7 - compatible pull stations 6 – compatible alarm/horn strobes
· More if fire code dictates need more than above listed
1.3 OBJECTIVE
The goal is to restore full fire alarm panel capabilities with an up-to-date fully functioning installed system for crew safety.
1.4 APPLICABLE DOCUMENTS
N/A
2.0 SPECIFIC REQUIREMENTS/TASKS
Please see the Scope of the SOW
3.0 CONTRACTOR PERSONNEL
Contractor personnel will have the appropriate certifications for working on fire alarm control systems and/or NFPA (National Fire Protection Association) certified.
3.1 QUALIFIED PERSONNEL
The Contractor shall provide qualified personnel to perform all requirements specified in this SOW.
3.2 CONTINUITY OF SUPPORT
The Contractor shall ensure that the contractually required level of support for this requirement is always maintained. The Contractor shall ensure that all contract support personnel are present for all hours of the workday. If for any reason the Contractor staffing levels are not maintained due to vacation, leave, appointments, etc., and replacement personnel will not be provided, the Contractor shall provide e-mail notification to the Contracting Officer’s Representative (COR) prior to employee absence. Otherwise, the Contractor shall provide a fully qualified replacement.
3.43 EMPLOYEE CONDUCT
Contractor’s employees shall comply with all applicable Government regulations, policies and procedures (e.g., fire, safety, sanitation, environmental protection, security, “off limits” areas, wearing of parts of DHS uniforms, and possession of weapons) when visiting or working at Government facilities. The Contractor shall ensure Contractor employees always present a professional appearance and that their conduct shall not reflect discredit on the United States or the Department of Homeland Security. The Project Manager shall ensure Contractor employees understand and abide by Department of Homeland Security established rules, regulations and policies concerning safety and security.
3.4 REMOVING EMPLOYEES FOR MISCONDUCT OR SECURITY REASONS
The Government may, at its sole discretion (via the Contracting Officer*), direct the Contractor to remove any Contractor employee from DHS facilities for misconduct or security reasons. Removal does not relieve the Contractor of the responsibility to continue providing the services required under the contract. The Contracting Officer will provide the Contractor with a written explanation to support any request to remove an employee.
4.1 PERIOD OF PERFORMANCE
The period of performance for this contract shall not exceed 60 calendar days from the date of award.
4.2 PLACE OF PERFORMANCE
United States Coast Guard at 810 Norris Harbor Drive, Crisfield, MD, 21817.
4.3 HOURS OF OPERATION
Contractor employees shall generally perform all work between the hours of 0700 and 1600 EST, Monday through Friday (except Federal holidays). However, there may be occasions when Contractor employees shall be required to work other than normal business hours, including weekends and holidays, to fulfill requirements under this SOW.
4.4 TRAVEL
Contractor travel shall not be required for this requirement.
5.0 GOVERNMENT FURNISHED RESOURCES
The Government will not furnish any resources to the Contractor in support of this contract.
6.0 CONTRACTOR FURNISHED PROPERTY
The Contractor shall furnish all facilities, materials, equipment, and services necessary to fulfill the requirements of this contract.
7.0 GOVERNMENT ACCEPTANCE PERIOD
The COR will review deliverables prior to acceptance and provide the contractor with an e-mail that provides documented reasons for non-acceptance. If the deliverable is acceptable, the COR will send an e-mail to the Contractor notifying it that the deliverable has been accepted.
7.1 The COR will have the right to reject or require correction of any deficiencies found in the deliverables that are contrary to the information contained in the Contractor’s accepted proposal. In the event of a rejected deliverable, the Contractor will be notified in writing by the COR of the specific reasons for rejection. The Contractor may have an opportunity to correct the rejected deliverable and return it per delivery instructions.
7.2 The Contractor shall have 30 business days to make corrections and redeliver.