About this file

This document is a continuation sheet for Solicitation 70Z08424RWOPL0002, Amendment 0001, issued by the Department of Homeland Security U.S. Coast Guard for the procurement of Lithium Ice Buoy Batteries.

The key details are:

  • Delivery is FOB Destination, with all transportation costs included in the fixed price for the Lithium Ice Batteries.
  • Deliveries must be made Monday-Friday between 10am-3pm local time, with a minimum 3 business days' notice required to schedule. No deliveries on federal holidays.
  • The Government requires 3 Lithium Battery Packs to be delivered/tested within 45 days of receipt of a delivery order as a First Article.
  • The desired delivery schedule is for all CLINs to be delivered within 75 days after issuance of a delivery order.
  • The contract has a 1-year base period with four 1-year option periods, for a total potential duration of up to 5 years.

View the file

Other files for this federal contract opportunity

Other files attached to Ice Buoy Batteries, newest first.
File Type Posted
SF-30_A0001.pdf PDF
Attachment 2 - DHS Form 700-21.pdf PDF
Attachment 1 - Spec 505-E.2.pdf PDF
Attachment 4 - Destinations.pdf PDF
70Z08424RWOPL0002.pdf PDF
Attachment 3 - PPQ.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTINUATION SHEET REFERENCE NO. OF DOCUMENT BEING CONTINUED Page Solicitation 70Z08424RWOPL0002 10 of 50 Amendment 0001

NAME OF OFFEROR OR CONTRACTOR

SECTION F

DELIVERIES OR PERFORMANCE

F. 1 PLACE OF DELIVERY – DESTINATION. Price shall include cost of transportation for delivery FOB Destination. All items including option years may be deliver to the following Coast Guard destinations, which will be identified on individual delivery orders. See Section J, Attachment 4, for Delivery Destinations.

F.2 SHIPPING. All transportation cost shall be included in the fixed price for Lithium Ice Battery.

F.3 PREPARATION FOR DELIVERY. All deliveries will be made no later than the date specified on the delivery order, unless otherwise discussed and approved by the Contracting Officer. All deliveries shall be made Monday through Friday between the hours of 10:00 am and 3:00 pm, local time of the destination. No deliveries shall be scheduled or made on federally observed holidays. The contractor shall schedule deliveries by contacting the Coast Guard destination, specified in each delivery order to set a mutually agreed upon delivery date. To ensure the availability of equipment and Coast Guard personnel to accept delivery, a minimum of three business days is required between scheduling a delivery and delivery being made. Requests to deliver later than the date specified on the delivery order must be approved by the Contracting Officer. The Coast Guard reserves the right prior to agreeing to a delivery date to declare a date as a non-delivery date. Expenses incurred by the contractor due to failure to make delivery on a mutually agreed upon delivery date shall be the responsibility of the contractor.

F.4 FIRST ARTICLE DELIVERY TESTING SCHEDULE. In accordance with Section B of the solicitation, the Government requires the following first article items to be delivered/tested as indicated below:

CLIN SUPPLIES QTY UNIT TIME OF DELIVERY

000A Lithium Battery Pack 3 EA 45 days after receipt of a delivery order

F.5 DELIVERY SCHEDULE. The Government desires delivery to be made according to the following schedule:

Required Delivery Schedule CLIN No. Quantity Within Calendar Dates From…..

All CLIN’s All 75 Days After Issuance of Delivery Order

F.6 ORDERING PERIOD. The term of the contract base ordering period is for one base year (or less depending on the date of award) with the addition of four, one-year options which extend the contract through May 2029. The total contract duration period will not exceed five years. Evaluation of options does not obligate the Government to exercise any option period. The estimated contract period is as follows (dates nay be adjusted based upon award date):