Abstract of Offers_70Z08226BCEUM0001.pdf
PDF 380 KB Posted
- Solicitation number
- 70Z08226BCEUM0001
About this file
This is an Abstract of Offers for a construction solicitation issued by the U.S. Coast Guard Civil Engineering Unit Miami for the Rebuild Bahia de Guayanilla Entrance Range Rear Light project at United States Coast Guard Aids to Navigation (ANT) in Puerto Rico (Project No. 13832866, Solicitation No. 70Z08226BCEUM0001).
The solicitation was issued on July 2, 2026, with offers opened on August 25, 2026. The government estimate for the project was $859,000.00. Three amendments were issued to the solicitation, and all eight bidders acknowledged receipt of these amendments. All bidders provided bid bonds as required security. Eight offers were received for the single base item (1 job), with total bid prices ranging from a low of $553,899.00 (Caribbean Marine Construction LLC) to a high of $3,773,807.51 (OTAK Group, Inc.). The other bidders and their respective bids were: Advantix Engineering Corp. ($859,000.00), Villawolf LLC ($946,100.00), J&J Builder Contractors Group Corp. ($999,990.00), Barlovento LLC ($1,157,769.00), Gabriel Fuentes Jr. Construction Co. Inc. ($1,994,500.00), and Desarrolladora J.A. Inc. ($2,550,000.00). The contracting officer, Gregory Hodgson, certified the abstract on August 26, 2026.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ABSTRACT OF OFFERS - CONSTRUCTION
1. SOLICITATION NUMBER
70Z08226BCEUM0001
2. DATE ISSUED
7/2/2026
3. DATE OPENED
8/25/2026
PAGE OF PAGES
1 3
4. ISSUING OFFICE
U.S. COAST GUARD
CIVIL ENGINEERING UNIT MIAMI
15608 SW 117TH AVENUE
MIAMI, FL 33177-1630
I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation.
NAME AND TITLE OF CERTIFYING OFFICIAL (TYPE)
GREGORY HODGSON, CONTRACTING OFFICER
SIGNATURE
DATE SIGNED
8/26/2026
5. PROJECT TITLE
Rebuild Bahia de Guayanilla Entrance Range Rear Light at United States Coast Guard Aids to Navigation (ANT) Puerto Rico
PROJECT NO. 13832866
8. GOVERNMENT ESTIMATE
9. OFFERS
NO. 1 NO. 2
A. HIRED LABOR
A. OFFEROR
Advantix Engineering Corp.
Caribbean Marine Construction
LLC
B. REASONABLE CONTRACT
(Without Profit)
B. BID SECURITY (Type and amount)
Yes – Bid Bond B. BID SECURITY (Type and amount)
Yes – Bid Bond
6. NUMBER OF AMENDMENTS ISSUED
AMENDMENTS: 03 X C. REASONABLE CONTRACT
(Including profit)
C. AMENDMENTS ACKNOWLEDGED
Yes
7A.
ITEM
NO.
7B. DESCRIPTION OF OFFERED ITEM
7C. EST.
QUANTITY
D.
UNIT
E. UNIT
PRICE
7F. ESTIMATED
AMOUNT
D. UNIT
PRICE
E. ESTIMATED
AMOUNT
D. UNIT
PRICE
E. ESTIMATED
AMOUNT
0001 BASE ITEM 1 JB $859,000.00 $553,899.00 $617,380.17
TOTAL BID PRICE $859,000.00 $553,899.00 $617,380.17
NOTE: If more than two offers are received, continue on OF 1419A. OPTIONAL FORM 1419 (11-88) Prescribed by GSA – FAR (48 CFR)53.236-1
ABSTRACT OF OFFERS – CONSTRUCTION
CONTINUATION SHEET
70Z08226BCEUM0001
PAGE OF PAGES
2 3
INSTRUCTIONS – Attach this form to OF-1419, Abstract of Offers – Construction, when more than 2 offers are received on a construction project. Each Continuation Sheet will accommodate 14 contract items to conform to the number of items which can be entered on the OF-1419. Use additional OF-1419’s for contract items in excess of 14 and attach additional Continuation Sheets (OF-1419A) as needed.
2. PROJECT TITLE
Rebuild Bahia de Guayanilla Entrance Range Rear Light at United States Coast Guard Aids to Navigation (ANT) Puerto Rico
PROJECT NO. 13832866
4. OFFERS (Continued)
NO. 3 NO. 4 NO. 5 NO. 6
Villawolf LLC
J&J Builder Contractors Group Corp.
Barlovento LLC
Gabriel Fuentes Jr.
Construction Co. Inc.
B. BID SECURITY (Type and amount)
Yes – Bid Bond
3. CONTRACT ITEMS
A.
ITEM
NO.
B.
ESTIMATED
QUANTITY
C.
UNIT
D. UNIT
PRICE
E. ESTIMATED
AMOUNT
D. UNIT
PRICE
E. ESTIMATED
AMOUNT
D. UNIT
PRICE
E. ESTIMATED
AMOUNT
D. UNIT
PRICE
E. ESTIMATED
0001 BASE ITEM 1 JB $946,100.00 $999,990.00 $1,157,769.00 $1,994,500.00
TOTAL BID PRICE $946,100.00 $999,990.00 $1,157,769.00 $1,994,500.00
OPTIONAL FORM 1419A (11-88)
Prescribed by GSA – FAR (48 CFR) 53.236-1
ABSTRACT OF OFFERS – CONSTRUCTION
CONTINUATION SHEET
70Z08226BCEUM0001
PAGE OF PAGES
3 3
INSTRUCTIONS – Attach this form to OF-1419, Abstract of Offers – Construction, when more than 2 offers are received on a construction project. Each Continuation Sheet will accommodate 14 contract items to conform to the number of items which can be entered on the OF-1419. Use additional OF-1419’s for contract items in excess of 14 and attach additional Continuation Sheets (OF-1419A) as needed.
2. PROJECT TITLE
Rebuild Bahia de Guayanilla Entrance Range Rear Light at United States Coast Guard Aids to Navigation (ANT) Puerto Rico
PROJECT NO. 13832866
4. OFFERS (Continued)
NO. 7 NO. 8
Desarrolladora J.A. Inc.
OTAK Group, Inc.
3. CONTRACT ITEMS
A.
ITEM
NO.
B.
ESTIMATED
QUANTITY
C.
UNIT
D. UNIT
PRICE
E. ESTIMATED
AMOUNT
D. UNIT
PRICE
E. ESTIMATED
AMOUNT
D. UNIT
PRICE
E. ESTIMATED
AMOUNT
D. UNIT
PRICE
E. ESTIMATED
0001 BASE ITEM 1 JB $2,550,000.00 $3,773,807.51
TOTAL BID PRICE $2,550,000.00 $3,773,807.51
OPTIONAL FORM 1419A (11-88)
Prescribed by GSA – FAR (48 CFR) 53.236-1
| 2026-08-26T15:46:12-0400 | |