Dolphin FY-20 DS Questions & Answers (2).pdf
PDF 12 KB Posted
- Attached to
- Dockside Repair of USCGC Dolphin
- Solicitation number
- 70Z08020QP4525000
About this file
This document contains questions and answers regarding a solicitation for dockside repair of the USCGC Dolphin WPB-87354. The solicitation seeks maintenance and update of the vessel's main diesel engine assemblies, including cleaning and inspecting components such as charge air coolers and injectors. Certified MTU technicians must provide their own tools, and a new intrusion detection system has not been installed on the vessel. The Department of Homeland Security US Coast Guard is the contracting agency seeking these dockside repair services.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 70Z08020QP4525000 A00004.pdf | ||
| Dolphin FY-20 DS Questions & Answers.pdf | ||
| 70Z08020QP4525000 A00003.pdf | ||
| 70Z08020QP4525000 A00002 signed.pdf | ||
| DOLPHIN FY20 DS Repairs – Price Schedule Rev 1.xls | XLS spreadsheet | |
| 70Z08020QP4525000 A00001 Signed.pdf | ||
| Dolphin FY-20 Dockside Combined Synopsis.pdf | ||
| DOLPHIN FY20 DS Repairs – Price Schedule.xls | XLS spreadsheet | |
| Solicitation Dolphin SOW.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CUTTER & HULL Number: ___USCGC Dolphin (WPB-87354)
RFQ Number: 70Z080-20-Q-4525000
SOLICITATION SECTION: PARA NO.
DEFINITE/OPTIONAL ITEM NO. Work Item 001 PARA NO.
TITLE:
Main Diesel Engine Assemblies, Perform W-5 Maintenance and Update Control System Configuration
1. QUESTION: Will the MTU tool kit for the W-5 be provided or does the KTR need to provide their own tool kit?
ANSWER: Certified MTU tech rep must provide their own tools.
DEFINITE/OPTIONAL ITEM NO. Work Item 001 PARA NO. 3.2.5
2. According to the description both charge air coolers and all 16 injectors should be replaced. But according to section 3.2.5 Clean and inspect components it is calling for them to be removed, inspected, cleaned, and reinstalled. Which method is to be completed for this contract?
ANSWER: Double asterisk(**) GFE items will only be replaced based on CFR called for in 3.2.5.
DEFINITE/OPTIONAL ITEM NO. Work Item 001 PARA NO.
3. QUESTION: is there any way to confirm if the updated Intrusion Detection System is already installed on this vessel or should we assume that it is?
ANSWER: The new intrusion detection system is not installed on DOLPHIN.