Revised_Attachment-3__Technical_Evaluation_Factors_USCGC_COCHITO_DS.pdf

PDF 343 KB Posted

Attached to
DOCKSIDE USCGC COCHITO Federal contract opportunity
Solicitation number
70Z080-20-Q-P4506400
Issued by
Department of Homeland Security US Coast Guard

About this file

Revised Attachment-3 Technical Evaluation Factors.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REVISED ATTACHMENT -3

USCGC COCHITO FY20 DS2 Contract Solicitation #: 70Z080-20-Q-P4506400

Technical Evaluation Factors

1. Technical Approach Submit a brief overview planning document using any means (computer generated, hand written, etc.) that outlines the strategy for ensuring that this requirement is completed on or before the contract completion date. The planning document shall include at least:

1) Proposed schedule, resources, completion-dates, float, and major millstones for the various tasks required to complete this contract and

2) Identify a list of items that may pose the most contract schedule risk and approach to mitigate or eliminate each risk.

NOTE: Negative responses are required for any items listed above that the contractor does not identify (i.e. schedule risk).

2. Grey Water System Cleaning Procedures Submit a description of the methods that will be employed to clean the grey water system piping and tanks (e.g. chemical cleaning, pressure washing, etc.) and if applicable, a description of the subcontracting plan.

3. Welding Certifications/Procedures Submit welding documentation (e.g.

WPSs, welder certs, etc.) in accordance with SFLC Standard Specification 0740, specific to your internal or subcontracted staff for the weld joints that will be installed.