Crane Industry Day Briefing_cbm_CMD 01-13-26.pptx

PPTX presentation 3 MB Posted

Attached to
RAIL MOUNTED CRANE INDUSTRY DAY
Solicitation number
70Z04026Q62301Y00
Issued by

About this file

This document is a PowerPoint briefing for the U.S. Coast Guard Yard's Crane Industry Day, scheduled for 13 January 2026, focusing on waterfront infrastructure optimization and crane procurement. The Coast Guard plans to upgrade its Curtis Bay, Maryland shipyard to support new Offshore Patrol Cutters and National Security Cutters arriving in 2030, which requires reconstructing three piers (Pier 2, Pier 3, and South Wharf) and installing new rail-mounted tower cranes. The project involves a design-build approach with specific technical requirements, including a Pier #3 crane objective of lifting 75,000 lbs at a 105-foot shaft and an auxiliary hoist with a 155-foot reach.

The procurement timeline spans from 2026 to 2030, with an estimated 2.2-year process for each crane's planning, design, manufacturing, transportation, and commissioning. The Coast Guard anticipates ordering three cranes simultaneously, with the first crane delivered at 84 weeks, the second at 96 weeks, and the third at 108 weeks. Industry representatives are invited to attend the Industry Day to provide feedback on technical requirements, with registration limited to one representative per company and closing on 29 December 2025. The event will include a project overview, site visit, and optional one-on-one sessions with U.S. Coast Guard technical representatives at 2401 Hawkins Point Rd., Baltimore, Maryland.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Brief for:

Traveling Crane – Industry Day Mr. John Bragaw Production Manager CG Yard Date: 13 January 2026 CG-SEA-E/Surface Forces Logistics Center- CG Yard

Assistant Commandant – Surface Program Executive Officer (CG-SEA)

OPENING REMARKS & INTRODUCTIONS

BACKGROUND & PROJECT SCOPE

DESIGN BUIILD RFP: TECHNICAL OVERVIEW

TECHNICAL REQUIREMENTS DISCUSSION

POTENTIAL TIMELINE

SITE WALK

LUNCH

ONE-ON-ONES

AGENDA

Introductions – Coast Guard

DepartmentNamePosition
CommandCaptain Emily TharpCommanding Officer
IndustrialCaptain Jay KimeIndustrial Manager
CG-ShoreCaptain John AdamsProgram Manager
ContractingMs. Yohanna AllenContracting Specialist
FacilitiesCommander Parker BratmanFacilities Engineer
FacilitiesLieutenant Charlie McAllisterConstruction Chief

Title of Presentation | Office | Presenter | Audience | Date of Presentation

Introductions – Coast Guard

DepartmentNamePosition
IndustrialMr. John BragawProduction Manager
IndustrialMr. Jim HoehnBusiness Manager
IndustrialMr. Jim CalvertChief Engineer
IndustrialMr. John WellsMechanical Engineering Branch Chief
IndustrialRon ViandsServices Group General Foreman
IndustrialBrian DashSupervisor, Crane Operations
IndustrialMr. Henry VernacchioSupervisor, Heavy Equipment Maintenance

Introductions – Army Corps of Engineers

DivisionNamePosition
Program ManagementCarrie OzgarProgram Manager
Project ManagementChristine DanaherProject Manager
EngineeringJason WoelperChief, Civil Works Design Mgmt Section, COR
EngineeringMapa MapagunarathneDesign Manager
EngineeringHenry WassingerStructural Engineer

Title of Presentation | Office | Presenter | Audience | Date of Presentation

CG Yard Service to the Fleet Since 1899 Yard Shiplift Video

The United States Coast Guard (USCG) Yard in Curtis Bay, Maryland has operated continuously since 1899 and is the sole USCG-operated shipyard in the United States.

The CG Yard is responsible for construction, repairs and renovation of vessels and various aids to navigation, and for the manufacturing of miscellaneous Coast Guard equipment.

To maintain these capabilities and advancements to their surface fleet, the CG Yard is planning for the arrival, and maintenance and repair of a new class of USCG Cutters (Offshore Patrol Cutter [OPC] and National Security Cutter [NSC]) at the Yard anticipated to arrive in 2030. CG has produced a comprehensive recap plan to align the Yard capabilities with the needs of the future fleet.

The arrival of the new Cutters will require greater water depths, and the CG Yard needs to update its waterfront infrastructure to be capable of supporting and dry-docking these new vessels.

CG has partnered with USACE Baltimore District to execute components of the CG Yard Shipyard Infrastructure Optimization Plan (SIOP)

Purpose Gather industry feedback and expertise to inform the technical requirements for a Design-Build RFP Pier Design Specs Necessary specs to inform the pier design for a DB RFP Considerations for crane pier interface, foundation, and supporting infrastructure Technical Requirements Gathering

Title of Presentation | Office | Presenter | Audience | Date of Presentation

Utilizing a Design-Build approach to integrate pier design and crane procurement Meet delivery timeline Maximize value Ensuring optimal performance Procurement How do customers order cranes?

What information is needed What are “typical” order performance specs Waterfront Reconstruction

Title of Presentation | Office | Presenter | Audience | Date of Presentation

Waterfront Reconstruction

Pier 2 – Demolition & reconstruction, new crane Pier 3 – Demolition & reconstruction, new crane South Wharf – Demolition & reconstruction Building 68 – Demolition & site restoration Associated infrastructure work, utility connections Renew Tower Crane 1 on existing pier/tracks * Tower Crane 3 Tower Crane 1

Rough Order of Magnitude costs for cranes meeting the space and required lift capacity and reach Crane delivery and commissioning timelines and how they align with the Coast Guard’s operational needs.

Crane Cost and Delivery

CY 2026CY 2027CY 2028CY 2029CY 2030
FY26
Q2FY26
Q3FY26
Q4FY27
Q1FY27
Q2FY27
Q3FY27
Q4FY28
Q1FY28
Q2FY28
Q3FY28
Q4FY29
Q1FY29
Q2FY29
Q3FY29
Q4FY30
Q1FY30

Q2 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3

1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3

WATERFRONT OPTIMIZATION

DB RFP DEVELOPMENT / AWARD

WATERFRONT OPTIMIZATION

DESIGN & CONSTRUCTION

Hypothetical Crane Timeline

DESIGN & MANUFACTURE / TRANSPORT TO U.S. ASSUMBLY LOCATION*

(~25 MONTHS)

PLANNING / DESIGN

COORDINATION

(~ 6 MONTHS)

ASSEMBLY OF CRANE ON BARGE / PREPARE TO SHIP TO CG YARD

(~1 MONTH)

BARGE TRANSPORT TO CG YARD FROM SOUTH CENTRAL U.S.

(~ 2-4 WKS / 1 MONTH)

CRANE ASSEMBLY / TESTING / COMMISSIONG

(~ < 1 MONTH)

WATERFRONT OPTIMIZATION CONSTRUCTION COMPLETE

Assumptions:

~2.2 yr timeline for Planning/Coordination, Design, Manufacturing, Transportation, Testing, & Commissioning (looking for feedback).

*Assumes transportation from overseas to assembly location in South Central U.S.

Waterfront Optimization Construction Complete NLT 12/31/2029 Electrical upgrades are complete to allow for testing / commissioning of cranes on piers

154-WPC-601-302-1 (general arrangement) C:\Users\PCVogelgesang1\OneDrive - United States Coast Guard\Desktop\PFILES\154\154B-WPC_601_302\154B-WPC_601_302_1_-_A.dwg

Also: 154-WPC-085-301 (hull lines and offsets)C:\Users\PCVogelgesang1\OneDrive - United States Coast Guard\Desktop\PFILES\154\154B-WPC_85_301\154B-WPC_85_301_1_-_-.dwg

1 Assuming the DBC will need at least 6 months for planning/design of the piers in order to be able to order the cranes?

2 Design & Manufacturing and transport to assembly location in South Central U.S = assume longest phase 3 Assemble crane on barge, prepare for shipment to the CG Yard 4 Transportation to CG Yard (Barge) 5 Installation/Assembly/Testing/Commissioning

Timeline represents the longest duration of if ordering all 3 cranes for each pier 1,2, &3. Email from 12/18/2025: Based on all of the cranes ordered simultaneously, delivery time would be 84 weeks for the first crane, and each subsequent crane would be delivered at 12-week intervals. Crane #1 delivered at 84 weeks, crane #2 delivered at 96 weeks, crane #3 delivered at 108 weeks. Assumes “delivery” is to the assembly location in the U.S. (Seatrax assumed Galveston TX.) For simplicity and ease, going to assume that 1 crane takes 2.2 yrs from start to finish.

Pier 3 Tower Crane support both Floating Drydock and Shiplift Pier #3 objective: 75,000 lbs shaft @ 105ft Aux Hoist Longest Reach: 155ft (to outer wing wall) Pier #3 Lift topmast from EAGLE tall ship that is 150’ above main deck* *Heights do not include drafts, blocks, FDD pontoon, etc.

Closer to the 200’ range?

Pier 3 Concept

Title of Presentation | Office | Presenter | Audience | Date of Presentation

CG Yard evaluating business case to overhaul or replace tower crane 1.

Pier 1 will be primary heavy lift capability until pier 2 work complete.

Control system obsolete Upper structure Inspect & Preserve (lead paint remediation) Winch renewals Main Hoist Drum Bearing Renewal Current construction to increase pier capacity

Pier 1 Tower Crane

Open Discussion image2.png image3.png image4.png image5.jpeg image6.png image7.jpeg image8.png image9.png image10.png image11.png image12.emf image13.jpeg image14.png image1.png