Crane Industry Day Briefing_cbm_CMD 01-13-26.pptx
PPTX presentation 3 MB Posted
- Attached to
- RAIL MOUNTED CRANE INDUSTRY DAY
- Solicitation number
- 70Z04026Q62301Y00
About this file
This document is a PowerPoint briefing for the U.S. Coast Guard Yard's Crane Industry Day, scheduled for 13 January 2026, focusing on waterfront infrastructure optimization and crane procurement. The Coast Guard plans to upgrade its Curtis Bay, Maryland shipyard to support new Offshore Patrol Cutters and National Security Cutters arriving in 2030, which requires reconstructing three piers (Pier 2, Pier 3, and South Wharf) and installing new rail-mounted tower cranes. The project involves a design-build approach with specific technical requirements, including a Pier #3 crane objective of lifting 75,000 lbs at a 105-foot shaft and an auxiliary hoist with a 155-foot reach.
The procurement timeline spans from 2026 to 2030, with an estimated 2.2-year process for each crane's planning, design, manufacturing, transportation, and commissioning. The Coast Guard anticipates ordering three cranes simultaneously, with the first crane delivered at 84 weeks, the second at 96 weeks, and the third at 108 weeks. Industry representatives are invited to attend the Industry Day to provide feedback on technical requirements, with registration limited to one representative per company and closing on 29 December 2025. The event will include a project overview, site visit, and optional one-on-one sessions with U.S. Coast Guard technical representatives at 2401 Hawkins Point Rd., Baltimore, Maryland.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Industry Day Attendance List 01-13-26.pdf | ||
| Request for Information (RFI) - Crane 121125.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Brief for:
Traveling Crane – Industry Day Mr. John Bragaw Production Manager CG Yard Date: 13 January 2026 CG-SEA-E/Surface Forces Logistics Center- CG Yard
Assistant Commandant – Surface Program Executive Officer (CG-SEA)
OPENING REMARKS & INTRODUCTIONS
BACKGROUND & PROJECT SCOPE
DESIGN BUIILD RFP: TECHNICAL OVERVIEW
TECHNICAL REQUIREMENTS DISCUSSION
POTENTIAL TIMELINE
SITE WALK
LUNCH
ONE-ON-ONES
AGENDA
Introductions – Coast Guard
| Department | Name | Position |
| Command | Captain Emily Tharp | Commanding Officer |
| Industrial | Captain Jay Kime | Industrial Manager |
| CG-Shore | Captain John Adams | Program Manager |
| Contracting | Ms. Yohanna Allen | Contracting Specialist |
| Facilities | Commander Parker Bratman | Facilities Engineer |
| Facilities | Lieutenant Charlie McAllister | Construction Chief |
Title of Presentation | Office | Presenter | Audience | Date of Presentation
Introductions – Coast Guard
| Department | Name | Position |
| Industrial | Mr. John Bragaw | Production Manager |
| Industrial | Mr. Jim Hoehn | Business Manager |
| Industrial | Mr. Jim Calvert | Chief Engineer |
| Industrial | Mr. John Wells | Mechanical Engineering Branch Chief |
| Industrial | Ron Viands | Services Group General Foreman |
| Industrial | Brian Dash | Supervisor, Crane Operations |
| Industrial | Mr. Henry Vernacchio | Supervisor, Heavy Equipment Maintenance |
Introductions – Army Corps of Engineers
| Division | Name | Position |
| Program Management | Carrie Ozgar | Program Manager |
| Project Management | Christine Danaher | Project Manager |
| Engineering | Jason Woelper | Chief, Civil Works Design Mgmt Section, COR |
| Engineering | Mapa Mapagunarathne | Design Manager |
| Engineering | Henry Wassinger | Structural Engineer |
Title of Presentation | Office | Presenter | Audience | Date of Presentation
CG Yard Service to the Fleet Since 1899 Yard Shiplift Video
The United States Coast Guard (USCG) Yard in Curtis Bay, Maryland has operated continuously since 1899 and is the sole USCG-operated shipyard in the United States.
The CG Yard is responsible for construction, repairs and renovation of vessels and various aids to navigation, and for the manufacturing of miscellaneous Coast Guard equipment.
To maintain these capabilities and advancements to their surface fleet, the CG Yard is planning for the arrival, and maintenance and repair of a new class of USCG Cutters (Offshore Patrol Cutter [OPC] and National Security Cutter [NSC]) at the Yard anticipated to arrive in 2030. CG has produced a comprehensive recap plan to align the Yard capabilities with the needs of the future fleet.
The arrival of the new Cutters will require greater water depths, and the CG Yard needs to update its waterfront infrastructure to be capable of supporting and dry-docking these new vessels.
CG has partnered with USACE Baltimore District to execute components of the CG Yard Shipyard Infrastructure Optimization Plan (SIOP)
Purpose Gather industry feedback and expertise to inform the technical requirements for a Design-Build RFP Pier Design Specs Necessary specs to inform the pier design for a DB RFP Considerations for crane pier interface, foundation, and supporting infrastructure Technical Requirements Gathering
Title of Presentation | Office | Presenter | Audience | Date of Presentation
Utilizing a Design-Build approach to integrate pier design and crane procurement Meet delivery timeline Maximize value Ensuring optimal performance Procurement How do customers order cranes?
What information is needed What are “typical” order performance specs Waterfront Reconstruction
Title of Presentation | Office | Presenter | Audience | Date of Presentation
Waterfront Reconstruction
Pier 2 – Demolition & reconstruction, new crane Pier 3 – Demolition & reconstruction, new crane South Wharf – Demolition & reconstruction Building 68 – Demolition & site restoration Associated infrastructure work, utility connections Renew Tower Crane 1 on existing pier/tracks * Tower Crane 3 Tower Crane 1
Rough Order of Magnitude costs for cranes meeting the space and required lift capacity and reach Crane delivery and commissioning timelines and how they align with the Coast Guard’s operational needs.
Crane Cost and Delivery
| CY 2026 | CY 2027 | CY 2028 | CY 2029 | CY 2030 | ||
| FY26 | ||||||
| Q2 | FY26 | |||||
| Q3 | FY26 | |||||
| Q4 | FY27 | |||||
| Q1 | FY27 | |||||
| Q2 | FY27 | |||||
| Q3 | FY27 | |||||
| Q4 | FY28 | |||||
| Q1 | FY28 | |||||
| Q2 | FY28 | |||||
| Q3 | FY28 | |||||
| Q4 | FY29 | |||||
| Q1 | FY29 | |||||
| Q2 | FY29 | |||||
| Q3 | FY29 | |||||
| Q4 | FY30 | |||||
| Q1 | FY30 |
Q2 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3
1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3
WATERFRONT OPTIMIZATION
DB RFP DEVELOPMENT / AWARD
WATERFRONT OPTIMIZATION
DESIGN & CONSTRUCTION
Hypothetical Crane Timeline
DESIGN & MANUFACTURE / TRANSPORT TO U.S. ASSUMBLY LOCATION*
(~25 MONTHS)
PLANNING / DESIGN
COORDINATION
(~ 6 MONTHS)
ASSEMBLY OF CRANE ON BARGE / PREPARE TO SHIP TO CG YARD
(~1 MONTH)
BARGE TRANSPORT TO CG YARD FROM SOUTH CENTRAL U.S.
(~ 2-4 WKS / 1 MONTH)
CRANE ASSEMBLY / TESTING / COMMISSIONG
(~ < 1 MONTH)
WATERFRONT OPTIMIZATION CONSTRUCTION COMPLETE
Assumptions:
~2.2 yr timeline for Planning/Coordination, Design, Manufacturing, Transportation, Testing, & Commissioning (looking for feedback).
*Assumes transportation from overseas to assembly location in South Central U.S.
Waterfront Optimization Construction Complete NLT 12/31/2029 Electrical upgrades are complete to allow for testing / commissioning of cranes on piers
154-WPC-601-302-1 (general arrangement) C:\Users\PCVogelgesang1\OneDrive - United States Coast Guard\Desktop\PFILES\154\154B-WPC_601_302\154B-WPC_601_302_1_-_A.dwg
Also: 154-WPC-085-301 (hull lines and offsets)C:\Users\PCVogelgesang1\OneDrive - United States Coast Guard\Desktop\PFILES\154\154B-WPC_85_301\154B-WPC_85_301_1_-_-.dwg
1 Assuming the DBC will need at least 6 months for planning/design of the piers in order to be able to order the cranes?
2 Design & Manufacturing and transport to assembly location in South Central U.S = assume longest phase 3 Assemble crane on barge, prepare for shipment to the CG Yard 4 Transportation to CG Yard (Barge) 5 Installation/Assembly/Testing/Commissioning
Timeline represents the longest duration of if ordering all 3 cranes for each pier 1,2, &3. Email from 12/18/2025: Based on all of the cranes ordered simultaneously, delivery time would be 84 weeks for the first crane, and each subsequent crane would be delivered at 12-week intervals. Crane #1 delivered at 84 weeks, crane #2 delivered at 96 weeks, crane #3 delivered at 108 weeks. Assumes “delivery” is to the assembly location in the U.S. (Seatrax assumed Galveston TX.) For simplicity and ease, going to assume that 1 crane takes 2.2 yrs from start to finish.
Pier 3 Tower Crane support both Floating Drydock and Shiplift Pier #3 objective: 75,000 lbs shaft @ 105ft Aux Hoist Longest Reach: 155ft (to outer wing wall) Pier #3 Lift topmast from EAGLE tall ship that is 150’ above main deck* *Heights do not include drafts, blocks, FDD pontoon, etc.
Closer to the 200’ range?
Pier 3 Concept
Title of Presentation | Office | Presenter | Audience | Date of Presentation
CG Yard evaluating business case to overhaul or replace tower crane 1.
Pier 1 will be primary heavy lift capability until pier 2 work complete.
Control system obsolete Upper structure Inspect & Preserve (lead paint remediation) Winch renewals Main Hoist Drum Bearing Renewal Current construction to increase pier capacity
Pier 1 Tower Crane
Open Discussion image2.png image3.png image4.png image5.jpeg image6.png image7.jpeg image8.png image9.png image10.png image11.png image12.emf image13.jpeg image14.png image1.png