Question:

ATTACHMET 1 - TAB Schedule: CLIN 0001 – 2001 Labor Rates for Overhaul per specifications: Line Items

-001 – 003: The Spreadsheet Request only “hourly “Labor Rate but does not have a “Total Hours

Column” nor an “Extended Price Column” to execute specific tasks (Labor to Reassemble and Prepare to

Ship; Complete Overhaul); do you want us to modify the spreadsheet to reflect those changes? CLIN

0003 – 2003: Contractual Services: again, only has the hourly rate and should have a “Total Hours

Column” and “Extended Price Column.

Answer:

No, a “Total Hours Column” or “Extended Price Column” is not required for Attachment 1 – Schedule for

CLINS 0001 – 2001 and 0003 – 2003. We are only requesting the hourly rate for those lines on the schedule.

Question:

ATTACHMENT 2: We would require further explanation as to how to complete the document

Attachment 2; it appears both TABs sample delivery order and sample task order may require “Total

Hours Column” and “Extended Price Column.

Answer:

ATTACHMENT 2, sample delivery order and task order tabs have been updated with a “Total Hours

Column”. Line items totals should be entered in the “L/I Total” column on the sheets.