MACKINAW_(WLBB_240)_DS_AKT_16R0.pdf

PDF 260 KB Posted

Attached to
USCGC MACKINAW ENGINE AND GENERATOR MAINTENANCE AND REPAIR
Solicitation number
70Z04019Q61445B00
Issued by

About this file

SPECIFICATION

View the file

Other files

File Type Posted
A00001.pdf PDF
OMBUDSMAN.doc DOC document
FINAL_SOLICITATION_PACKAGE_3-8-2019.pdf PDF
WAGE_RATE_DETERMINATION.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USCGC MACKINAW (WLBB 30)

SPECIFICATION FOR MAINTENANCE AND SUPPORT OF THE MAIN PROPULSION/AUX

DIESEL ENGINE AND GENERATOR

Developed By: Alessandra K Twomey

(Rev-0, 07 December 2016)

USCGC MACKINAW (WLBB-30) MAINTENANCE AND SUPPORT OF THE MAIN

PROPULSION/AUX DIESEL ENGINE AND GENERATOR

ii (Rev-0)

TABLE OF CONTENTS

Revisions Record ....................................................................................................................................... iii Consolidated List of References ................................................................................................................ iv Consolidated List of Government-furnished Property ............................................................................... vi Consolidated List of Critical Inspection Items ......................................................................................... vii Principal Characteristics .......................................................................................................................... viii General Requirements WORK ITEM 1: Maintenance and Support Service for the Main Diesel Engine and Generator - Annual 7 WORK ITEM 2: Maintenance and Support Service for the Main Diesel Engine and Generator - Periodic WORK ITEM 3: Main Diesel Engine Overhaul (Top End and Major) WORK ITEM 4: Maintenance and Support Service for the Auxiliary Diesel Engine and Generator - Annual WORK ITEM 5: Maintenance and Support Service for the Auxiliary Diesel Engine and Generator - Periodic WORK ITEM 6: Auxiliary Diesel Engine Overhaul (Top End and Major) WORK ITEM 7: Provide Technical Remote or On-Site Support and Diagnostics iii (Rev-0)

Revisions Record This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.

DATE REV# WORK

ITEM#

CHANGES MADE

NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.

iv (Rev-0)

Consolidated List of References

The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at time of specification writing and during contract execution.

All Coast Guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – as follows:

• MIL/DOD/CID Specifications: http://www.assistdocs.com/search/search_basic.cfm

• Commandant Instruction Manuals: http://www.uscg.mil/directives/default.asp

• Public Laws, Code of Federal Regulations, U.S Codes, and other Federal Government laws::

www.gpoaccess.gov

The Government is aware of the following internet web links where contractors may procure commercial specifications:

• American Welding Society (AWS): http://www.awspubs.com/index.php

• ANSI, ASTM, IEEEE, NFPA, ASME, SAE Standards: http://www.techstreet.com/

• NFPA: http://www.nfpa.org

• SSPC Standards and pictorial guides: http://shopping.netsuite.com/sspcmarketplace

COAST GUARD DRAWINGS

None

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3D, Jan 2014, Coatings and Color Manual Coast Guard Technical Publication (TP) 3813, SWBS 312A, Apr 2005, Emergency Diesel Generator – Model Coast Guard Technical Publication (TP) 3814, SWBS 312A, Nov 2006, Emergency Diesel Generator – Engine Parts Coast Guard Technical Publication (TP) 3815, SWBS 312A, Nov 2006, Emergency Diesel Generator – Generator Parts Coast Guard Technical Publication (TP) 3858, SWBS 235A , Dec 2006, Main Diesel Generator – Engine Service Coast Guard Technical Publication (TP) 3859, SWBS 235A, Dec 2006, Main Diesel Generator – Monitoring System and Drawing Coast Guard Technical Publication (TP) 3860, SWBS 235A, Dec 2006, Main Diesel Generator – Engine Parts Coast Guard Technical Publication (TP) 3861, SWBS 235A, Dec 2006, Main Diesel Generator – Generator Service and Parts – Model AA2741700 Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740, 2014, Welding and Allied Processes http://www.assistdocs.com/search/search_basic.cfm http://www.uscg.mil/directives/default.asp http://www.gpoaccess.gov/ http://www.awspubs.com/index.php http://www.techstreet.com/ http://www.nfpa.org/ http://shopping.netsuite.com/sspcmarketplace v (Rev-0)

OTHER REFERENCES

ASTM International (ASTM) D4417, 2003, Standard Test Methods for Field Measurement of Surface Profile of Blast Cleaned Steel Code of Federal Regulations (CFR) Title 33 CFR, 2008, Navigation and Navigable Waters Code of Federal Regulations (CFR) Title 40, Chapter I, 2008, Environmental Protection Agency Code of Federal Regulations (CFR) Title 49, Chapter I, 2008, Pipeline and Hazardous Materials Safety Administration, Department Of Transportation Commercial Item Description (CID) A-A-59316, Nov 2003, Abrasive Materials for Blasting MIL-A-22262, Mar 1996, Abrasive Blasting Media Ship Hull Blast Cleaning NAVSEA Technical Publication T9074-AD-GIB-010/1688, (TP 1688), May 1997, Requirements for Fabrication, Welding, and Inspection of Submarine Structure The Society for Protective Coatings (SSPC) VIS 1, 2004, Guide and Reference Photographs for Steel Surfaces Prepared by Dry Abrasive Blast Cleaning vi (Rev-0)

Consolidated List of Government-furnished Property The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.

This section is not applicable to this package.

vii (Rev-0)

Consolidated List of Critical Inspection Items The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000_STD, paragraph

3.2.6.5 (Inspection report particulars)):

Work Item Title 3 Main Diesel Engine Overhaul (Top End and Major) 6 Auxiliary Diesel Engine Overhaul (Top End and Major) viii (Rev-0)

PC_240_WLBB_1011

Principal Characteristics

240' WLBB (30 CGC MACKINAW)

PHYSICAL CHARACTERISTICS

Length Overall 240’ 0” Depth (main deck at side to baseline) 24' 0" Maximum Beam 58’ 0” Height of Highest Projection (above DWL) 95' 6" Full Load Draft 16’ 0” Full Load Displacement (Icebreaking) 3426.73 LT Freshwater Shore Tie Voltage Requirements 1,200 Amp total

3EA 400A 450VAC 3PH

Ungrounded forward/aft stations

HULL CHARACTERISTICS

Frame Spacing FR 19-25 = 19"

FR 33-39 = 21"

ALL Else = 20"

MACHINERY CHARACTERISTICS

Number of Propellers 2 Number of Blades per Propeller 4

Diameter of Propeller 10.25' Pitch 96.98" Revolutions per Minute (RPM) 226 rated 270 max Shafting/Propulsion System Azipod

TANK CAPACITIES

Diesel Oil 115,538 gallons Fresh Water Capacity 27,948 gallons Hydraulic Oil Capacity 696 gallons Lube Oil Storage 1,159 gallons Grey Water Tank 27, 080 gallons Sewage Holding Tank 5,313 gallons ix (Rev-0)

This page was left blank intentionally. Do not delete.

1 (Rev-0)

00000_PWB_1111_FLT

REC_0000_FLT_ Commercial Project @ CG Facility (0211)

General Requirements

1. SCOPE

1.1 Intent. This item describes the general requirements to be followed by the Contractor while conducting tasks specified in this performance work statement (PWS).

2. REFERENCES

COAST GUARD DRAWINGS

None.

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3D, Jan 2014, Coatings and Color

Manual Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General

Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and

Allied Processes

OTHER REFERENCES

Code of Federal Regulations (CFR) Title 33 CFR, 2008, Navigation and Navigable Waters Code of Federal Regulations (CFR) Title 40, Chapter I, 2008, Environmental Protection Agency Code of Federal Regulations (CFR) Title 49, Chapter I, 2008, Pipeline and Hazardous Materials Safety

Administration, Department Of Transportation

3. REQUIREMENTS

3.1 General. The Contractor shall conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability.

NOTE

The requirements of paragraph 3.1 (General) applies to all work under the scope of this contract, whether explicitly stated in work items or not, and also to all other work subsequently authorized by changes, modifications, or extensions to the contract.

3.2 Scope of work.

3.2.1 Work. The Contractor shall provide all personnel, labor, materials, parts, tools, test equipment, test fittings, supplies, consumables, and equipment required to maintain and support the main propulsion/auxiliary diesel engines, generator, and controls as defined in this PWS.

2 (Rev-0)

NOTE

Coast Guard personnel will operate all shipboard machinery and equipment, perform electrical tag-outs in support of maintenance, and be available to advise on rigging safety procedures as necessary. All other labor associated with maintenance tasks (i.e. rigging, parts delivery, repairs, etc) shall be provided by the Contractor.

3.2.2 Travel. The Contractor shall provide all travel to support tasks onboard the vessel at the vessel’s homeport (Cheboygan, MI), in accordance with each order issued.

3.2.3 Parts. The Contractor shall use only new, Original Equipment Manufacturer (OEM)-approved parts for accomplishments of tasks.

3.2.4 System and equipment information. The following are the core system components and shall be referred to as “system” throughout the body of this PWS.

• Main Diesel Engine (MDE): Caterpillar Model 3612 - Direct Injected, Turbocharged, Aftercooled (DITA) (3 each)

• Main Generator: KATO Model 3130 KW (3 each)

• Generator Monitoring System (GMS): Caterpillar Model 3612 generator set (3 each)

• Auxiliary Diesel Generator (ADG) Engine: Caterpillar Model 3508 - Direct Injected, Turbocharged, Aftercooled (DITA) (1 each)

• Auxiliary Diesel Generator: KATO Model 750 KW (1 each)

• Generator Monitoring System (GMS): Caterpillar Model 3508 generator set (1 each)

3.3 Contractor qualifications. The Contractor shall provide qualified personnel to perform all contract work and services within specified time frames. Qualification requirements are as follows:

3.3.1 Project Manager (PM). The Contractor shall provide a PM who shall coordinate all Contractor support under this contract and shall be a single point of contact for the Contracting Officer (KO) and designated of the Contracting Officer Representative (COR). The name, position, and title of this person shall be stated in writing to the KO as part of the Contractor’s proposal. The Contractor shall provide a substitute PM if the designated PM is unavailable, provided the KO is given (10) days advance written notice. The PM shall be able to read, write, speak and understand English fluently.

3.3.2 Tech Reps.

3.3.2.1 Caterpillar Tech Rep. The Contractor shall provide the services of a certified Tech Rep, who is familiar with the Caterpillar Model 3612 and 3508 diesel engines, to accomplish the following tasks – on site:

• Provide manufacturer's proprietary information, software, and tools pertinent to the equipment/system.

• Assist with proper repair methods, and ensure compliance with manufacturer's procedures and standards during disassembly, inspection, repair, modification, calibration, and reassembly of the equipment/system.

• Conduct Marine Engine Performance diagnostic testing (CAMPAR or load bank testing), ensuring compliance with manufacturer's, U.S. Coast Guard, OSHA, and other pertinent procedures and standards.

• Generate a Computer Aided Marine Performance Analysis Report (CAMPAR) with the diagnostic test data and recommendations for the diesel engines. (Reports shall be submitted to COR within 90 days of test completion)

• Provide genuine, OEM-approved parts

3.3.2.1.1 Ensure that the Tech Rep is a Certified Representative of Caterpillar.

3 (Rev-0)

3.3.2.1.2 Tech Rep should be knowledgeable and competent with performance of mechanical and electrical tasks / troubleshooting for the Caterpillar Model 3612 and 3508 diesel engines and ancillary support equipment.

3.3.2.2 KATO Tech Rep. The Contractor shall provide the services of a certified Tech Rep, who is familiar with the KATO generators, to accomplish the following tasks – on site:

• Provide manufacturer's proprietary information, software, and tools pertinent to the equipment/system.

• Assist with proper repair methods, and ensure compliance with manufacturer's procedures and standards during disassembly, inspection, repair, modification, calibration, and reassembly of the equipment/system.

• Provide genuine, OEM-approved parts

3.3.2.2.1 Ensure that the Tech Rep is a Certified Representative of KATO.

3.3.2.2.2 Tech Rep should be knowledgeable and competent with performance of mechanical and electrical tasks / troubleshooting for the KATO Model 3130 KW and 750 KW generator sets and ancillary support equipment.

3.3.3 Contractor’s personnel in training. The Contractor may not use trainees to perform any of the required services unless each trainee performs all work under the close supervision of a technical representative. At least a (1:1) technical representative to trainee ratio shall be strictly maintained. The full cost associated with trainee efforts shall be funded by the Contractor and shall not be charged to this contract.

3.3.4 Employee identification and access. At least seventy two (72) hours prior to each ship visit to perform work under this contract, the Contractor shall submit a list of all employees who shall be performing that work to the COR. In the case of a ship visit as a result of a casualty, the list of all employees who will be performing the work shall be submitted within 8 hours after the ship visit is authorized by the KO. To gain access to the ship or other Government facilities to perform any work under this contract, each Contractor employee shall carry a picture identification card furnished by the Contractor, or other servicing agent authorized by the Contractor/Manufacturer. The employee shall prominently display this card on their person in the chest area at all times when on any Government facility, except when actively engaged in labor wherein the card might get caught in tools or operating machinery and represent a hazard to the employee.

3.3.5 Security clearances. No special security clearances are normally required to perform any work under this PWS. The Contractor shall supply a list of all employees who may be required to perform work under this PWS and periodically update that list. Prior to each ship visit to perform work under this PWS, the Contractor shall submit information on visiting employees. Should the cutter be berthed at a Department of Defense or foreign government military facility, the KO will provide instructions on the method by which the cutter crew will assist the Contractor’s representatives in meeting facility access requirements at the time the Contractor is tasked.

3.3.6 Government facility regulations. The Contractor shall observe and comply with all USCGC MACKINAW (WLBB-30) and Homeport Facility policy/instructions that might affect work performance under this PWS. A copy will be provided to the contractor after contract award.

3.4 Documentation and reporting.

3.4.1 Technical Plan. The Contractor shall develop and provide a technical plan with its proposal. The plan shall contain the methodology that the Contractor will use to execute this PWS. The plan shall contain a description of all proposed tasks stated in the PWS including but shall not be limited to:

• Technical support and remote diagnostics (corrective maintenance)

4 (Rev-0)

• Management of employees

• Quality assurance measures/checks and balances to ensure proper products commercial or other standards utilized to measure compliance with federal, state and local laws, rules, regulations and this performance work statement. Please refer to the solicitation for details.

3.4.2 Contract and performance evaluation meetings. The Contractor’s PM shall attend a Post Contract Award Orientation Conference with the KO and/or COR no later than two weeks after contract award at a location to be designated by the KO. The purpose of this meeting is to discuss contract requirements, task order objectives, and to ensure that all Government and Contractor representatives understand contract clauses and procedures; however, this meeting is not a substitute for the Contractor’s full understanding of the work requirements at the time offers are submitted, nor is it to be used to alter the final agreement arrived at in any negotiations leading to contract award. Thereafter, the Contractor’s PM shall meet the KO and/or COR twice each year to discuss performance problems and review Contractor’s corrective actions, to address Contractor or Government concerns, and to plan future contract tasks and events. Additional meetings may be held, if requested by the Government or Contractor. The Contractor shall prepare and submit an agenda prior to each meeting. The Contractor shall submit minutes documenting the discussions at each meeting.

3.4.3 Trip reports.

3.4.3.1 The Contractor shall submit a trip report summarizing all work accomplished for the applicable ship visit. The report shall include the following:

• List of all work accomplished

• List of all CIRs and CFRs submitted

• List of all pending work and current status

• Log of all requested technical assistance (remote and on-site), including description of requested support and resolution

• List of any parts resulting from work accomplished required for dealer turn-in

3.4.3.2 The Contractor shall submit the report to the COR no later than seven (7) calendar days after visit departure.

3.4.4 Quarterly reports.

3.4.4.1 The Contractor shall submit a quarterly report summarizing all work accomplished for the fiscal quarter. The report shall include the following:

• List of all trip reports provided to the CG

• List of all CIRs and CFRs submitted

• List of all pending work and current status

• Log of all requested technical assistance (remote and on-site), including description of requested support and resolution

• List of any parts resulting from work accomplished required for dealer turn-in

• Any technical bulletins or service updates issued for applicable equipment under this contract

• List of any components being investigated by OEM for engineering defects or suspected issues

• List of any system or equipment modifications performed by request of the USCG

• List of any recommended component , equipment, or software upgrades recommended by OEM to applicable equipment

3.4.4.2 The Contractor shall submit the report to the COR no later than thirty (30) calendar days after the end of the fiscal quarter.

5 (Rev-0)

3.4.5 General administrative support. The Contractor shall provide administrative services in support of the activities outlined in this PWS, including but not be limited to the following:

3.4.5.1 The Contractor shall prepare and provide written reports, briefing materials and other documentation.

3.4.5.2 The Contractor shall provide meeting support, including but not limited to providing meeting notes.

3.4.5.3 The Contractor shall provide all written reports in electronic format with read/write capability using applications that are compatible with Coast Guard Standard Workstation III (Windows Vista, Microsoft Office, and Adobe Acrobat applications).

3.5 Government quality assurance. The Government will establish a Quality Assurance Surveillance Plan (QASP) for this PWS. The purpose of the QASP is to describe the methods the Government will use to evaluate Contractor services required in this PWS. However, the QASP is not part of this PWS.

The Government has the right to inspect, test, and audit all services and quality records called for by this PWS, to the extent practical, at all times during the terms of this PWS. The Government will perform inspections and tests in a manner that will not unduly delay the work. When on-the-spot action to correct observed defects cannot be taken, the Government will use a Contract Deficiency Report (CDR) to advise the Contractor of the problem and to indicate to the Contractor the requirement for response or corrective action. The Contractor shall respond within 24 hours to the COR with a copy to the KO.

3.6 Government furnished property and services.

3.6.1 Government furnished information. The Government will provide a copy of the ship’s Allowance Parts Lists (APL’s) to the Contractor within (30) days after contract award. The Contractor may make use of any of the equipment technical manuals, ship’s drawings, Engineering Logs and records available on the ship. However, the Contractor shall be responsible for ensuring that the documents covering these systems are up to date with the latest technical information from the OEM prior to their use.

3.6.2 Government’s right for changing out parts. The Contractor shall be aware that the Government reserves the right to furnish new replacement parts for installation in-place of contractor removed parts.

When the Government exercises this right, the Contractor shall turn over the removed part to the Coast Guard as a Mandatory Turn-In (MTI) item.

3.7 Authorized additional work. The Contractor shall provide a separate price proposal for additional work, which may or may not be accepted by the Government, negotiated and executed at time of service interval. Within the proposal, the Contractor shall describe tasking, required labor, and associated costs.

3.8 Engineering support services. The Government may require the conduct of engineering analyses to support system/component design changes, hardware and software modifications, or related efforts.

Such analyses may include, but are not limited to feasibility studies, inspection reports, reports of onboard technical surveys, specification development, failure analyses, etc. The Contractor shall submit a proposal to provide such services, when requested by the KO. The Contractor shall perform those services, which are subsequently authorized by the KO.

3.9 Contractor-provided fire watch personnel. The Contractor shall provide fire watch personnel and equipment.

3.10 Welding and brazing requirements. The Contractor shall perform all welding and allied processes, and NDI in accordance with SFLC Std Spec 0740.

3.11 HW disposal. The Contractor shall be responsible for all hazardous wastes generated by work under this contract. Label and package all hazardous wastes in 49 CFR-approved containers, and in accordance with all other applicable Federal, state, and local laws and regulations. In addition, comply with applicable parts of 40 CFR 262, applicable to handling of hazardous wastes.

6 (Rev-0)

3.11.1 Along with the Government, the Contractor shall be contractually considered the co-generator of all hazardous wastes; be aware that the Government will make available its facility’s EPA Generator Identification (ID) Number for manifesting of hazardous wastes.

3.11.2 The Contractor shall identify, arrange, and be responsible for the turnover of all hazardous wastes, within the confines of the Coast Guard shore facility, to the facility’s HM/HW Coordinator.

Notify the ship’s HW Coordinator prior to any transfers of HW from ship to shore.

3.11.3 The Contractor shall prepare a manifest of hazardous waste to be reviewed and signed by the HM/HW Coordinator. Contact the HM/HW Coordinator for turnover of any hazardous waste; in addition, notify the COR in writing 24 hours prior to any waste removals, and ensure that waste removals are conducted during normal business hours (0800-1600) on Monday through Friday (excluding holidays).

3.11.4 The Contractor shall be aware of the following:

3.11.4.1 No Contractor or Subcontractor shall have the authority to sign a Hazardous Waste Manifest using the Coast Guard facility’s EPA Generator ID Number or remove contract generated hazardous waste from the Coast Guard facility without COR or KO approval.

3.11.4.2 Local environmental regulations at the Government facilities may be more stringent than in many jurisdictions. As with all environmental regulations, it is the Contractor's responsibility to research, prepare for, and comply with local and state regulations.

3.11.4.3 Coast Guard facilities do not have Facilities Response Plans (see 33 CFR 154 Subpart F). It is the Contractor’s responsibility to furnish the Facility Response Plan (FRP) when required for over-the-water liquids transfers to and from vessels. This requirement is applicable to transfers to/from vessels with an oil/fuel capacity of 250 barrels or more.

3.12 Touch-up preservation. The Contractor shall prepare and coat all new and disturbed exterior and interior surfaces to match existing adjacent surfaces, in accordance with COMDTINST M10360.3, Appendix A (Cutter and Boat Exterior Painting Systems) and Appendix B (Cutter and Boat Interior Painting Systems), respectively, and as applicable. Abide by all touch-up requirements outlined in SFLC Std Spec 0000, Appendix A (Requirements for Preservation of Ship Structures).

3.13 Protective measures. The Contractor shall furnish and install suitable covering to seal off and protect all non-affected surfaces/equipment and spaces in the vicinity of the work area against contamination during the performance of work. Upon completion of work, remove protective material and inspect for the presence of contamination. Clean all equipment and spaces, contaminated due to improper protection, to original condition of cleanliness.

4. NOTES

4.1 Access to COMDTINST M10360.3. The COMDTINST M10360.3 may be accessed at the following URL address: http://www.uscg.mil/directives/cim.asp http://www.uscg.mil/directives/cim.asp

7 (Rev-0)

23500_CAT Maint IDIQ_MWC_1011_30

WORK ITEM 1: Maintenance and Support Service for the Main Diesel Engine and Generator - Annual

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to provide annual support and service for three Caterpillar Model 3612 main propulsion diesel engine and generator.

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

None.

COAST GUARD PUBLICATIONS

Coast Guard Technical Publication (TP) 3858, SWBS 235A , Dec 2006, Main Diesel Generator – Engine

Service Coast Guard Technical Publication (TP) 3859, SWBS 235A, Dec 2006, Main Diesel Generator –

Monitoring System and Drawing Coast Guard Technical Publication (TP) 3860, SWBS 235A, Dec 2006, Main Diesel Generator – Engine

Parts Coast Guard Technical Publication (TP) 3861, SWBS 235A, Dec 2006, Main Diesel Generator –

Generator Service and Parts – Model AA2741700

OTHER REFERENCES

None.

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

None.

3.1.2 Tech Rep.

8 (Rev-0)

Refer to “General Requirements”.

3.1.3 Protective measures.

Refer to “General Requirements”.

3.1.4 Interferences.

None.

3.1.5 Maintenance prerequisites. Prior to a maintenance interval being performed, the Contractor shall verify that all maintenance requirements from the previous interval have been completed.

NOTE

Ship’s Force will be performing routine maintenance in support of equipment operations. The Contractor shall coordinate with the COR to ensure all prerequisites have been accomplished prior to conduct of scheduled work.

3.2 Scope of work. The Contractor shall perform the following annually in accordance with TP 3858, TP 3859, TP 3860, TP 3861, and manufacturer’s instructions. Submit CFR and recommendations for all inspection items.

3.2.1 Diesel engine.

• CAMPAR test.

• Aftercooler Condensation - Drain.

• Engine Timing Synchronization, Valve Lash Inspect & Adjust.

• Engine valve rotators - Inspect.

• Oil Mist Detector – Clean / Replace.

• Cooling System Supplemental Coolant Additive (SCA) – Test / Add.

• Aftercooler Core – Clean / Test.

• Air Starting Motor Lubricator Bowl - Clean.

• Starting Motor – Inspect

• Water Temperature Regulator – Replace

• Engine Protection Devices - Calibrate.

3.2.2 Generator and Generator Monitoring System.

• Perform MPC E-A-8993

• Generator Monitoring System – Clean & Inspect.

• Clearance and spacing of lead wires and electrical connections – Inspect.

• Outlet box, air screens, bearing housings, and air baffles – Clean & Inspect.

9 (Rev-0)

4. NOTES

4.1 “As-Built” engine configuration. Specific as-built engine configuration parts group data is available upon request.

10 (Rev-0)

23501_CAT Maint IDIQ_MWC_1011_30

WORK ITEM 2: Maintenance and Support Service for the Main Diesel Engine and Generator - Periodic

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to provide periodic support and service for one Caterpillar Model 3612 main propulsion diesel engine and generator.

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

None.

COAST GUARD PUBLICATIONS

Coast Guard Technical Publication (TP) 3858, SWBS 235A , Dec 2006, Main Diesel Generator – Engine

Service Coast Guard Technical Publication (TP) 3859, SWBS 235A, Dec 2006, Main Diesel Generator –

Monitoring System and Drawing Coast Guard Technical Publication (TP) 3860, SWBS 235A, Dec 2006, Main Diesel Generator – Engine

Parts Coast Guard Technical Publication (TP) 3861, SWBS 235A, Dec 2006, Main Diesel Generator –

Generator Service and Parts – Model AA2741700

OTHER REFERENCES

None.

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

11 (Rev-0)

Refer to “General Requirements”.

3.1.4 Interferences.

None.

3.1.5 Maintenance prerequisites. Prior to a maintenance interval being performed, the Contractor shall verify that all maintenance requirements from the previous interval have been completed.

NOTE

Ship’s Force will be performing routine maintenance in support of equipment operations. The Contractor shall coordinate with the COR to ensure all prerequisites have been accomplished prior to conduct of scheduled work.

3.2 Scope of work. The Contractor shall perform the following at the given time intervals in accordance with TP 3858, TP 3859, TP 3860, TP 3861, and manufacturer’s instructions. Submit CFR and recommendations for all inspection items.

3.2.1 Diesel Engine.

3.2.1.1 8,000 Hour Service or 3 Years.

• Camshaft Roller Followers – Inspect.

• Cooling System Coolant (DEAC) – Change.

• Cooling System Coolant Extender (ELC) – Add.

• Crankshaft Vibration Dampener – Inspect.

• Driven Equipment - Check.

• Engine Oil Temperature Regulator - Replace.

• Exhaust Shields – Inspect.

• Governor Actuator Oil – Replace.

• Turbocharger – Inspect.

• Water Pump – Inspect.

3.2.1.2 16,000 Hour Service or 6 Years.

• Cooling System Coolant (ELC) – Change.

3.2.1.3 Vibration Analysis (As-Required).

• Vibration Analysis – Conduct.

12 (Rev-0)

3.2.2 Generator and Generator Monitoring System.

3.2.2.1 20,000 Hour Service or 3 Years.

• Sleeve bearing, liner, shaft journal, and seal surfaces – Inspect.

• Generator windings – Clean and Inspect.

3.2.2.2 40,000 Hour Service or 6 Years.

• Generator – Overhaul per TP 3861.

3.2.2.3 Generator Balancing (As-Required).

• Generator Balancing – Conduct.

3.2.2.4 Infrared Scan (As-Required).

• Infrared Scan – Conduct.

4.1 “As-Built” engine configuration. Specific as-built engine configuration parts group data is available upon

13 (Rev-0)

23503_CAT Maint IDIQ_MWC_1211_30

WORK ITEM 3: Main Diesel Engine Overhaul (Top End and Major)

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to disassemble, clean, inspect, repair and reassemble (Top End and Major Overhaul) for one Caterpillar Model 3612 main propulsion diesel engine.

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

None.

COAST GUARD PUBLICATIONS

Coast Guard Technical Publication (TP) 3858, SWBS 235A, Dec 2006, Main Diesel Generator – Engine

Service Coast Guard Technical Publication (TP) 3859, SWBS 235A, Dec 2006, Main Diesel Generator –

Monitoring System and Drawing Coast Guard Technical Publication (TP) 3860, SWBS 235A, Dec 2006, Main Diesel Generator – Engine

Parts Coast Guard Technical Publication (TP) 3861, SWBS 235A, Dec 2006, Main Diesel Generator –

Generator Service and Parts – Model AA2741700

OTHER REFERENCES

None.

3. REQUIREMENTS

3.1 General.

3.1.1 CIR. The Contractor shall submit a CIR for the inspections listed in the following paragraph(s):

• 3.3.1 (Engine component cleaning and inspections).

• 3.4.1 (Engine component cleaning and inspections).

14 (Rev-0)

Refer to “General Requirements”.

3.1.4 Interferences.

None.

3.1.5 References. The Contractor/technicians shall disassemble, clean, inspect, repair or renew and reassemble the Caterpillar engine units and accessories in accordance with the references listed in Section 2 herein.

3.1.6 Authority to proceed. The Contractor/technicians shall not proceed with any work on the engine units or accessories described in this specification, until specific instructions are given by the KO on what work is to be accomplished.

NOTE

The Contracting Officer (KO) will provide a written response to the Contractor, after receipt of the CIR, regarding all work to be completed for repairs. Work may not proceed until this authorization is received.

3.1.7 Responsibility for inspection. The Contractor/technicians shall be responsible for all inspections and test requirements specified herein. The Contractor shall provide the necessary calibrated test equipment to conduct all of the inspection requirements. Be aware that the Government reserves the right to verify or perform any of the inspections or tests set forth in this specification where such inspections are deemed necessary to assure that supplies or services conform to the prescribed requirements.

3.1.8 Report. The Contractor shall record the appropriate inspection findings on a CFR (clearance and tolerance readings of the cylinder block and related components). Submit a written report of all findings and recommendations to the Coast Guard Inspector (CGI) within 24 hours after inspection.

3.1.9 Government’s right for furnishing various components and parts. The Contractor shall be aware that the Government reserves the right, to furnish new or rebuilt components or parts for installation, in place of the existing parts, at no additional cost to the Government. If the Government exercises this right, the Contractor shall turn over all existing components or parts to the Coast Guard PA as Mandatory Turn-In (MTI) items.

3.2 Operational test – initial. Prior to commencement of work, the Contractor shall witness an operational pre-test (by Coast Guard personnel) of the Main Diesel Engine to demonstrate existing operational condition. Submit a CFR.

3.3 Top End Overhaul.

3.3.1 Clean and Inspect Engine Components. The Contractor shall disassemble, clean, inspect and test the engine components listed below, (Refer to Table 1) utilizing the appropriate publications as outlined in Section 2.1 and

2.2 as guidance. Provide a CIR of these components to the KO for potential reuse determination.

Table 1 - Engine Components to be disassembled, cleaned, inspected or tested during the performance of a Top End Overhaul

COMPONENT

Aftercooler

15 (Rev-0)

Exhaust Manifold Rocker Shaft Assembly and Push Rods

Turbocharger Water Manifold

3.3.2 Automatic renewal. The Contractor shall perform the following engine component renewals with genuine, remanufactured (or new) OEM components, (Refer to Table 2).

Table 2 - Engine Components to be disassembled and automatically renewed during the performance of a Top End Overhaul

COMPONENT

Complete Cylinder Head Assemblies

Cylinder Head Gaskets and Seals Inlet Air Line Seals

Turbocharger Bearings, Bushings and Seals Valve Lubricator (If Equipped) Water Pump Bearings and Seals

Water Temperature Regulators and Seals

3.3.3 Discretionary renewal. If a modification has been authorized and released by the KO, the Contractor shall renew the specified engine components with genuine, remanufactured (or new) OEM components. (Refer to Table 3).

Table 3 - Engine Components to be renewed upon inspection and with KO authorization

COMPONENT

Aftercooler Exhaust Manifold

Rocker Shaft Assembly and Push Rods Turbocharger

Water Manifold

3.4 Major Overhaul (Including Top End).

3.4.1 Clean and Inspect Engine Components. The Contractor shall disassemble, clean, inspect and test the engine components listed below, (Refer to Table 4) utilizing the appropriate publications as outlined in Section 2.1 and

2.2 as guidance. Provide a CIR of these components to the KO for potential reuse determination.

Table 4 - Engine Components to be disassembled, cleaned, inspected or tested during the performance of a Major Overhaul

COMPONENT

Camshaft Camshaft Lifters Connecting Rods

Crankshaft Crankshaft Vibration Damper

Cylinder Block Cylinder Liners

16 (Rev-0)

Driven Equipment (alignment) Engine Mounts

Flywheel Front Gear Train (Gears)

Fuel Injection Pump Fuel Transfer Pump

Governor Oil Cooler Core

Oil Suction Screen Pistons (Crowns/Skirts) Rear Gear Train (Gears)

3.4.2 Automatic renewal. The Contractor shall perform the following engine component renewals with genuine, remanufactured (or new) OEM components, (Refer to Table 5).

Table 5 - Engine Components to be disassembled and automatically renewed during the performance of Major Overhaul

COMPONENT

Camshaft Bearings Con Rod Bearings Crankshaft Seals

Crankshaft Thrust Plates Exhaust Manifold (Seals and Bellows)

Fuel Group Fuel Injectors

Fuel Transfer Pump Gear Train Bushings

Inlet Manifold (Gaskets and Seals) Jacket Water Pump

Lube Oil Cooler Lubricating Oil Pump

Main Bearings Piston rings

Sea Water Pump Software (Install new software when a new ECM is installed) Valve Rotators

3.4.3 Discretionary renewal. If a modification has been authorized and released by the KO, the Contractor shall renew the specified engine components with genuine, remanufactured (or new) OEM components. (Refer to Table 6).

Table 6 - Engine Components to be renewed upon inspection and with KO authorization

COMPONENT

Crankshaft Camshaft

Connecting Rods

17 (Rev-0)

Crankshaft Vibration Damper

Cylinder Liners

Driven Equipment (alignment) Engine Mounts

Flywheel Front Gear Train (Gears)

Fuel Injection Pump Fuel Transfer Pump

Governor Oil Cooler Core

Oil Suction Screen Pistons (Crowns/Skirts) Rear Gear Train (Gears)

3.5 Gaskets and seal. The Contractor shall furnish and renew all gaskets and seals (consumables) associated with the engine reassembly in this contract.

3.6 Fluids. The Contractor shall furnish and renew all fluids and filters associated with the engine reassembly.

3.7 Reassemble Engine Units and Accessories. After any authorized repairs and renewals, the Contractor shall reassemble the engine units and accessories to its original configuration utilizing the appropriate publications as outlined in Section 2.1 as guidance.

3.8 Operational test – post repairs. After completion of work, the Contractor shall witness an operational test (by Coast Guard personnel) of the diesel engine unit and accessories to prove satisfactory operating condition. The Contractor shall conduct engine test run (break-in) in accordance with applicable Caterpillar and Coast Guard standards. Upon successful operational testing, the Contractor shall perform the applicable CAMPAR test requirement.

3.9 Compliance. All work shall meet the requirements of section 3 (Requirements) of this work specification.

The inspections set forth shall become part of the Contractor's overall Inspection System or Quality Program. The absence of any inspection requirements shall not relieve the Contractor of the responsibility of ensuring that all work submitted to the Government for acceptance complies with all requirements of the contract.

3.9.1 Noncompliance. If any work fails to pass a test or inspection, the Contractor shall take action to correct the work.

3.10 Acceptance. Acceptance of the work shall be discontinued until corrective actions, acceptable to the Government, have been taken. After taking corrective action, repeat the inspection on the corrected work.

3.11 Final acceptance. Final acceptance shall be withheld until re-inspection shows the corrective action to be successful. In the event of failure after re-inspection, the Contractor shall submit to the Coast Guard Inspector a written report concerning the failure with recommended corrective actions.

3.12 Conformance. Quality conformance tests and inspections shall be the minimum test and inspection methods used to demonstrate compliance to the requirements set forth in section 3 of this work specification.

18 (Rev-0)

4.1 Equipment operation. Coast Guard personnel will operate all shipboard machinery and equipment during all operational tests.

4.2 “As-Built” engine configuration. Specific as-built engine configuration parts group data is available upon request.

4.3 Coast Guard Inspector responsibilities. Although the Contractor is responsible for applying appropriate quality assurance measures, the Coast Guard will witness the accomplishment of these measures. Therefore, a Coast Guard Inspector will:

4.3.1 Monitor the assigned work items to keep informed of progress and to ensure that the specifications are being followed.

4.3.2 Witness all test as required by the specification.

4.3.3 Be guided by the work item and seek immediate clarification when necessary.

4.3.4 Immediately bring to the attention of the Contracting Officer any work which appears to be contrary to the work item requirements.

4.3.5 Document all work performed in the Machinery History Log.

NOTE

When there is overwhelming documentation to record. The Engineer Officer/Engineer Petty officer may state in the Machinery History Log, “All overhaul documentation is located

(indicate where) for reference.”

4.4 Definitions.

4.4.1 Tools - Common tools normally contained in a standard toolbox (screwdrivers, wrenches, pliers) etc.

4.4.2 Special Tools/Test Equipment - Such as torque wrenches, calibrated electronic meters, computer devices etc not normally found in a standard toolbox.

4.4.3 Consumables - A non-reusable item such as a rag, disposable gloves, paint, oil, grease, solvent, adhesive, sealant, corrosion preventive product, cleaner, etc.

19 (Rev-0)

31200_CAT Maint IDIQ_MWC_1211_30

WORK ITEM 4: Maintenance and Support Service for the Auxiliary Diesel Engine and Generator - Annual

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to provide annual support and service for the Caterpillar Model 3508 auxiliary diesel engine and generator.

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

None.

COAST GUARD PUBLICATIONS

Coast Guard Technical Publication (TP) 3813, SWBS 312A, Apr 2005, Emergency Diesel Generator –

Model 3508 Coast Guard Technical Publication (TP) 3814, SWBS 312A, Nov 2006, Emergency Diesel Generator –

Engine Parts Coast Guard Technical Publication (TP) 3815, SWBS 312A, Nov 2006, Emergency Diesel Generator –

Generator Parts

OTHER REFERENCES

None.

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

None.

20 (Rev-0)

3.1.4 Interferences.

None.

3.1.5 Maintenance prerequisites. Prior to a maintenance interval being performed, the Contractor shall verify that all maintenance requirements from the previous interval have been completed.

NOTE

Ship’s Force will be performing routine maintenance in support of equipment operations. The Contractor shall coordinate with the COR to ensure all prerequisites have been accomplished prior to conduct of scheduled work.

3.2 Scope of work. The Contractor shall perform the following annually in accordance with TP 3813, TP 3814, TP 3815, and manufacturer’s instructions. Submit CFR and recommendations for all inspection items.

3.2.1 Diesel engine.

• CAMPAR test.

• Cooling System Coolant Analysis (Level II) – Obtain.

• Engine – Clean.

• Engine Crankcase Breather – Clean.

• Engine and Oil Filter – Change.

• Engine Protective Devices – Check.

• Fuel System Primary Filter – Clean / Inspect / Replace.

• Fuel System Secondary Filter – Replace.

• Air Starting Motor Lubricator Bowl - Clean.

• Crankshaft Vibration Dampener – Inspect.

• Engine Mounts – Check.

• Turbocharger - Inspect.

• Engine Valve Lash – Inspect / Adjust.

• Fuel Injector – Inspect / Adjust.

3.2.2 Generator and Generator Monitoring System.

• Generator Monitoring System – Clean & Inspect.

• Stator output leads, protective sleeving and insulation - Inspect.

• Tightness of electrical connections - Inspect.

21 (Rev-0)

• Transformers, fuses, capacitors, and lightning arrestors – Inspect.

• Clearance and spacing of lead wires and electrical connections – Inspect.

• Outlet box, air screens, bearing housings, and air baffles – Clean & Inspect.

• Insulation resistance to ground on all generator windings – Check.

• Space heater operations - Check.

• Exciter armature for proper rotating rectifier connection tightness – Check.

4. NOTES

4.1 “As-Built” engine configuration. Specific as-built engine configuration parts group data is available upon

22 (Rev-0)

31201_CAT Maint IDIQ_MWC_1211_30

WORK ITEM 5: Maintenance and Support Service for the Auxiliary Diesel Engine and Generator - Periodic

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to provide periodic support and service for the Caterpillar Model 3508 auxiliary diesel engine and generator.

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

None.

COAST GUARD PUBLICATIONS

Coast Guard Technical Publication (TP) 3813, SWBS 312A, Apr 2005, Emergency Diesel Generator –

Model 3508 Coast Guard Technical Publication (TP) 3814, SWBS 312A, Nov 2006, Emergency Diesel Generator –

Engine Parts Coast Guard Technical Publication (TP) 3815, SWBS 312A, Nov 2006, Emergency Diesel Generator –

Generator Parts

OTHER REFERENCES

None.

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

None.

23 (Rev-0)

3.1.4 Interferences.

None.

3.1.5 Maintenance prerequisites. Prior to a maintenance interval being performed, the Contractor shall verify that all maintenance requirements from the previous interval have been completed.

NOTE

Ship’s Force will be performing routine maintenance in support of equipment operations. The Contractor shall coordinate with the COR to ensure all prerequisites have been accomplished prior to conduct of scheduled work.

3.2 Scope of work. The Contractor shall perform the following at the given time intervals in accordance with TP 3813, TP 3814, TP 3815, and manufacturer’s instructions. Submit CFR and recommendations for all inspection items.

3.2.1 Diesel Engine.

3.2.1.1 3,000 Hour Service or 3 Years.

• Cooling System Coolant (DEAC) – Change.

• Cooling System Coolant Extender (ELC) – Add.

3.2.1.2 6,000 Hour Service or 6 Years.

• Cooling System Water Temperature Regulator – Replace.

• Prelube Pump – Inspect.

• Starting Motor – Inspect.

• Water Pump – Inspect.

3.2.2 Generator and Generator Monitoring System.

3.2.2.1 20,000 Hour Service or 3 Years.

• Sleeve bearing, liner, shaft journal, and seal surfaces – Inspect.

• Generator windings – Clean and Inspect.

3.2.2.2 40,000 Hour Service or 6 Years.

• Generator – Overhaul per TP 3861.

24 (Rev-0)

4.1 “As-Built” engine configuration. Specific as-built engine configuration parts group data is available upon

25 (Rev-0)

31202_CAT Maint IDIQ_MWC_1011_30

WORK ITEM 6: Auxiliary Diesel Engine Overhaul (Top End and Major)

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to disassemble, clean, inspect, repair and reassemble (Top End and Major Overhaul) for the Caterpillar Model 3508 auxiliary diesel engine.

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

None.

COAST GUARD PUBLICATIONS

Coast Guard Technical Publication (TP) 3813, SWBS 312A, Apr 2005, Emergency Diesel Generator –

Model 3508 Coast Guard Technical Publication (TP) 3814, SWBS 312A, Nov 2006, Emergency Diesel Generator –

Engine Parts Coast Guard Technical Publication (TP) 3815, SWBS 312A, Nov 2006, Emergency Diesel Generator –

Generator Parts

OTHER REFERENCES

None.

3. REQUIREMENTS

3.1 General.

3.1.1 CIR. The Contractor shall submit a CIR for the inspections listed in the following paragraph(s):

• 3.3.1 (Engine component cleaning and inspections).

• 3.4.1 (Engine component cleaning and inspections).

26 (Rev-0)

3.1.4 Interferences.

None.

3.1.5 References. The Contractor/technicians shall disassemble, clean, inspect, repair or renew and reassemble the Caterpillar engine units and accessories in accordance with the references listed in Section 2 herein.

3.1.6 Authority to proceed. The Contractor/technicians shall not proceed with any work on the engine units or accessories described in this specification, until specific instructions are given by the KO on what work is to be accomplished.

NOTE

The Contracting Officer (KO) will provide a written response to the Contractor, after receipt of the CIR, regarding all work to be completed for repairs. Work may not proceed until this authorization is received.

3.1.7 Responsibility for inspection. The Contractor/technicians shall be responsible for all inspections and test requirements specified herein. The Contractor shall provide the necessary calibrated test equipment to conduct all of the inspection requirements. Be aware that the Government reserves the right to verify or perform any of the inspections or tests set forth in this specification where such inspections are deemed necessary to assure that supplies or services conform to the prescribed requirements.

3.1.8 Report. The Contractor shall record the appropriate inspection findings on a CFR (clearance and tolerance readings of the cylinder block and related components). Submit a written report of all findings and recommendations to the Coast Guard Inspector (CGI) within 24 hours after inspection.

3.1.9 Government’s right for furnishing various components and parts. The Contractor shall be aware that the Government reserves the right, to furnish new or rebuilt components or parts for installation, in place of the…