Text version
Question # RFP Document Section # Question for Government Government Response
70Z03819RH0000002_-
_Amend_2.pdf
52.212-2 General Submission Requirements Pg. 4 & 7
Factor 1, SubFactor 2 a.
The RFP does not include the integrated master schedule (IMS) as a separate electronic file. We believe the IMS should be included as a Microsoft Project electronic file. Does the Government agree that the IMS should be submitted as a separate file from Volume 1 and Volume 2 ?
The IMS provided by the offeror may be a separate attachment to the proposal and will not count toward the page total.
This IMS shall be submitted in PDF. A copy of the updated solicitation is attached.
70Z03819RH0000002_-
_Amend_2.pdf
52.212-2 General Submission Requirements Pg. 4 & 7
Factor 1, SubFactor 2 a. Page 4
The RFP does not specify how the Contracts data is to be submitted. Does the USCG want contractors to only return the signed DD-1149 (and any amendments), along with checking the blocks for Reps and Certs (pgs. 24 &
25) or would you like the complete solicitation to be submitted? Additionally, for these items, does the USCG want them submitted as part of Volume 1 or 2, or should we submit them separately as enclosures to our cover letter, or as a separate Volume 3?
The Signature page for the SF- 1449 and the asnwers to FAR 52.212-3 shall be provided as an enclosure to the Contractor's cover page, or Volume 1.
The statement of the location of the Contractor's facility shall be listed on Attachment 1, Schedule. An updated copy of the schedule and solicitation have been provided with this amendment (Amd 0003)
70Z03819R0000002 and
ATT 4
52.212-1 Instructions to
Offerors, Page 3
In fairness to offerors in Texas Counties of Falls / McLennan and South Carolina Counties Anderson / Greenville / Laurens / Pickens, will the
Government please provide comparable Wage Determinations for the counties of all competitors who requested copies of the tech data set?
All wage determinations from interested parties who are subject to the SCA Labor Standards have been made available to all offerors. Should additional interested parties be identified, the solicitation will be amended to include their wage determination.
4 SOW 2.2.8, 2.2.10 Is the contractor responsible for ground run fuel and test flight fuel? No.
5 SOW 2.1.2
During transport of the aircraft to and from the contractors facility, will fuel costs and fee's be USCG cost or contractor cost? USCG Cost.
6 SOW 2.1.1
Can an inventory list be provided for the aircrew survival equipment that the contractor will need to remove during induction?
No. The USCG will provide its own Life Vest and 02 Masks. The Contractor will have to update the first aid kits on the aircraft IAW the appropriate ACMS card.
7 SOW 2.2.3
Disassembly Phase 3 indicates that wings, vertical and horizontal stabilizer could be removed however we were unable to locate a task card for this work. Please confirm if the removal of these components will be scheduled for this check.
The wing removal will be at the discretion of the contractor, as it is not required. Some overhaul providers prefer the wings off to conduct a better inspection and to alleviate late findings that may require a wing to come off.
The Vertical and Horizontal stab should not come off.
8 SOW 2.2.4, 2.2.4.1
Are all of the DMPC task cards provided in the Tech Data Package scheduled to be performed at this check? Is there any additional TO's, SB's or TCTO's that will require action at this time. If so can this list be provided in advance?
It is impossible to anticipate all TCTOs that would be required for this effort. At this time, the Government has provided all DMPC task cards, Block upgrade 8.1 TCTOs, ASIPs and paint specifications as a part of the Technical Data package to those who have requested the package via written request.
9 SOW 2.2.5
Is the estimated fixed-price "repair" phase hours shown in Attachment 1 to the SOW from the last 5 HC-130J PSIs based off of direct touch labour or have other production supporting hours contributed to this total?
The hours are based off of direct touch labor.
10 SOW 2.2.5.1
In the event that the contractor is called upon to incorporate changes to TCTO's, SCTO's or SB's will the costs be covered under CLIN 008 as "Unexpected Work"?
TCTO’s are expected and have been factored in to the last five aircraft’s hours. They will not be considered part of the “unexpected work”.
11 SOW SOW - 2.2.5.4
Can AE 2100D3 Engine records be provided in advance for review? Is there any indication of scheduled Engine or Prop component replacement at this time? No.
12 SOW SOW - 2.2.5.7
Can the drawing packages for Block 8.1 referenced in SCTO HC-130J T-I-4577 be provided at this time for estimating purposes?
Yes. These will be provided upon written request.
13 SOW 2.2.5
Should contractor provided repair material costs be applied to CLIN 0003 or CLIN
0005?
Materials for CLIN 0003 will be paid for with the material CLIN. Materials for CLIN 0005 Paint should be included within CLIN 0005.
If this is the case and SOW section 2.1 states that “Aircraft deficiencies noted on the Aircraft Condition Report (CG-103) that are not covered by the PSI shall be considered non-routine repairs.” Can the Aircraft Condition Report be provided so as to include incoming deficiencies in the FFP and consider another CLIN to be provided to capture this. Otherwise incoming aircraft deficiencies should be treated as “Unexpected Work”.
16 SOW 2.1, 2.3.3
Common embodied products including hardware (such as standard nuts, bolts, rivets), sealants, fluids, etc. Are these paid for as part of the material CLIN or are they to be included within the Contractor Firm Fixed Price and/or burdened Labour Rate.
This will be paid for as part of the material CLIN.
SOW
SOW
Yes, all non-routine work should be considered within the FFP CLINs. A CG-
103 will be provided 30 days prior to the induction of the aircraft. These repairs will be considered part of the FFP non-routine repairs. "Unexpected Work" will be if replacement of major structural fittings; as these are not expected on aircraft of this age.
Shop supplies should be included in the FFP CLINs and the burdened labor rate for the Unexpected work CLIN.
Shop supplies such as tape, gloves, masks, cleaning fluids, etc that are used by the technicians to perform the maintenance but do not fly away with the aircraft. Are these paid for as part of the material CLIN or are they to be included within the Firm Fixed Price and/or burdened Labour Rate.2.1, 2.3.2
1.5 and 2.1
SOW Section 1.5 defines the term “Non- Routine” as “Work within scope of estimated hours”. Can the contractor assume that this means that all Non-Routine work is to be within the FFP CLINs?