Q&A.doc
DOC document 26 KB Posted
- Attached to
- Repair/Overhaul of H-65 Landing Gear
- Solicitation number
- 70Z03818QB2000015
About this file
Q&A 70Z03818QB2000015
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 70Z03818QB2000015_-_SOW.docx | DOCX document | |
| 70Z03818QB2000015_-_Requirements_amendment.xlsx | XLSX spreadsheet | |
| 70Z03818QB2000015_-_Requirements.xlsx | XLSX spreadsheet | |
| Terms_and_Conditions_-_70Z03818QB2000015.docx | DOCX document | |
| 70Z03818QB2000015_-_SOW.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Q&A – 70Z03818QB20000015
1. Can you please confirm the Firm Fixed Price shall include only systematic parts (we can provide a list of those in our reply to the Solicitation) and that parts replaced on attrition shall be quoted separately (i.e. not included in Firm Fixed Price)?
Answer: Section 5.2 of the Statement of Work (SOW) has been amended
2. Is it possible to incorporate the minor and major repair work scopes into the RFP, thus limiting the costs to the USCG?
Answer: We will not be splitting this between minor and major repairs. Now that the SOW has been amended, this should not be an issue.
3. Can you please confirm the expected ARM for Test, Repair or Overhaul?
Answer: The requested delivery date is 30 days. Please quote your desired lead time. Be sure to include the lead time on the Requirements’ Spreadsheet for all three (3) scenarios, 1 – repair, 2 – NFF, and 3 – overhaul
4. The P/N for the LH Piston Tube Assembly in the Requirements spreadsheet is incorrect, it should be 18991-000-02 according to the CMM/SOW.
Answer: Part number has been corrected. Please see the amended requirements page.
File details come from the government source that posted it. Updated .