QUESTIONS AND ANSWERS.pdf

PDF 596 KB Posted

Attached to
Fuel Tank Transition Sump Replacement at USCG Station Brunswick, GA
Solicitation number
70Z036-25-Q-0004
Issued by

About this file

This document is a Questions and Answers file for a federal contract opportunity for the United States Coast Guard (USCG) to replace a transition sump at USCG Station Brunswick in Georgia. The solicitation (70Z036-25-Q-0004) is a small business set-aside with a $19M size standard for NAICS code 238990, seeking a firm fixed-price purchase order with a Lowest Price Technically Acceptable evaluation method.

Key details include a quote submission deadline of 5:00 PM EST on April 30, 2025, with quotes to be emailed to Adam.S.Hitchcox@uscg.mil. The project requires completion within 60 days of award, and potential bidders are strongly encouraged to conduct a site visit Monday-Friday between 8:00 AM and 3:00 PM EST by scheduling with station personnel. The solicitation includes several supporting documents such as a Statement of Work, Davis-Bacon Wage Determination, SF-1449, and related provisions and clauses. The government reserves the right to award to a single contractor or potentially not award at all, depending on proposal quality and fund availability.

View the file

Other files

File Type Posted
SF-1449.pdf PDF
SF-30 SOLICITATION EXTENSION.pdf PDF
Davis-Bacon Act WD GA20250293.pdf PDF
SF-1449.pdf PDF
Provisions and Clauses.pdf PDF
Statement of Work.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TRANSITION SUMP REPLACEMENT FOR USCG STATION BRUNSWICK

Solicitation #70Z036-25-Q-0004

Questions and Answers

Published: April 21, 2025

Question 1: Is there a cost estimate, budget, or ballpark figure for this project?

Answer: We cannot disclose the government’s cost estimate.

Question 2: Is there an actual start date for the project?

Answer: The project needs to be completed within 60 days of receiving the award.

Question 3: Would it be possible to have a few pictures of the transition sump in and around its location including one inside?

Answer: Yes, pictures have been added to the end of this document.