Solicitation 70Z03024QCLEV0064 - Statement of Work.pdf

PDF 248 KB Posted

Attached to
70Z03024QCLEV0064 - U. S. Coast Guard Sector Northern Great Lakes Housing Painting Project
Solicitation number
70Z03024QCLEV0064
Issued by

About this file

This document is a Statement of Work (SOW) for a U.S. Coast Guard (USCG) housing painting project at the Sector Northern Great Lakes location. The scope includes preparation, priming, and painting of interior surfaces in two housing units located in Sault Sainte Marie, Michigan. The USCG will provide the paint materials, while the contractor is responsible for all other supplies, tools, and equipment. The work must be completed within one week per unit, with a 5-day start window after unit availability. Contractors will be financially responsible for any damages incurred during performance. All work is subject to the local housing point-of-contact's approval, and must adhere to federal, state, and local regulations. The applicable NAICS code is 238320 (Painting and Wall Covering Contractors) with a $19.0M small business size standard. The total estimated value of this procurement is less than $25,000.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Department of Homeland Security United States Coast Guard

Base Cleveland Housing Division

Scope of Work (SOW) Housing Site

Sault Sainte Marie Coast Guard Housing For

Interior Prep, Prime, and Paint

Point of Contact (POC) DC2 Ian Spaulding (Local POC)

(920-664-4708) Ian.r.spaulding@uscg.mil

Or

DCC Coyet Carter (OHMC)

(443) 760-5034

Site Address

2658 Tahoma Dr. Sault Sainte Marie, MI, 49783 2BDR 2 Story.

2563 Tahoma Way. Sault Sainte Marie, MI, 49783 2BDR 2 Story.

mailto:Ian.r.spaulding@uscg.mil

Solicitation 70Z03024QCLEV0064 USCG Sector Northern Great Lakes Housing Painting Project

Page 2/4

Scope of Work

1.1 The contractor is to prepare all surfaces to protect from paint spatter, drips or accidental contact with the brush or roller, using drop cloths, masking tape or other appropriate means.

1.2 Remove any interference, (i.e., electrical cover plates, window cranks, window treatments, towel bars, stair handrails, light covers, smoke detectors, etc.). Stoves and refrigerators should be moved out far enough to facilitate painting behind them, but should remain hooked up to power, water, and gas connections.

1.3 All surfaces to be painted shall be properly prepared, (i.e., cleaned, sanded, feathered, puttied, primed, etc.) as necessary. Surface preparations will include the repair of damage to walls and ceilings, (i.e., splits, cracks, nail holes, chips, indentations, and holes less than or equal to the size of a quarter). All surfaces shall be free of dirt, grease, loose debris, and any other foreign matter that would adversely affect the appearance.

1.4 Where caulking is required, such as the kitchen/bathroom counters, trim work, and wall to ceiling joints, should be accomplished along with all other preparation work. Caulk will be furnished by the contractor and will be white in color and made of siliconized latex.

1.5 Contractor shall notify the POC listed upon completion of all preparation work before applying paint. After the POC has inspected and accepted the preparation work, paint may be applied.

1.6 Contractor shall paint all previously painted surfaces which include, but not limited to, walls, ceilings, Window sashes and the trim around doors, windows, stairways, and radiators. Paint shall be applied carefully with clean rollers and brushes to produce a complete and even coverage with a smooth finish, free of runs and other defects. Window sashes should be removed and/or positioned so as to ensure no contact with the window frames until the paint is cured.

1.7 Spraying paint to surfaces is not allowed.

1.8 Baseboard heaters will be painted with high temp paint brushed on.

1.9 After painting is completed, the POC needs to be notified to inspect and approve job completion is satisfactory prior to any items being reinstalled.

1.10 The contractor shall ensure that each home painted is left in a clean and orderly condition. All hardware, electrical, and plumbing accessories, to include items listed in 1.2, shall be reinstalled.

1.11 The contractor shall dispose of all waste materials properly and IAW EPA regulations at the contractor’s expense.

1.12 Approximate unit sizes are as listed:

1.12.1 2658 Tahoma Way.: ~1,890 sqft home, est. 8,000 sqft. of walls and ceilings.

1.12.2 2563 Tahoma Way.:; ~1,124 sqft home, est. 5,000 sqft. of walls and ceilings.

1.12.3 All units will become available on a VARIED TIMELINE roughly between the months of April to August; units WILL NOT be available at the same time for work to be performed and contractor cannot wait until all units are available before starting work. All contractors work in the unit must commence within five days of notice from the unit’s final vacancy by the CG POC to the contractor. All

Page 3/4 work must be completed within a one-week (five working days) timeframe from the start date of that unit. If possible, the POC will give the contractor a 30-day notice prior to the availability date.

Local CG Personnel to complete 3 CG Personnel will electrically isolate and move the stove and refrigerator away from the wall prior to painting in kitchen. Once painting has been completed CG Personnel will move items back to normal operating positions after the job walk for acceptability of standard of service is performed.

Material/ Part Information

3.1 All paint (and primer as needed) will be supplied by CG unit to the Contractor.

Trim Paint (Sherwin Williams Promar 200 Semi-gloss – Extra White) Ceiling Paint (Sherwin Williams Promar 200 Flat – Extra White) Wall Paint (Sherwin Williams Promar 200 Egg Shell – White)

Primer (Sherwin Williams Preprite Pro Block)

3.2 All other painting materials, tools, and equipment will be supplied by the contractor.

References

4.1 All work is to be completed shall comply with Federal, State and Local Laws, Codes and Regulations.

4.2 Manufactures’ requirements and recommendations shall be followed for all products used.

Liabilities

5.1 The contractor will be financially responsible for all damages incurred while working on Government property. There will be a pre-work walkthrough with Coast Guard personnel and the contractor at each job site prior to the contract start and contractor must identify any damages in their work area that are pre-existing, or along their access route to their work area. (Doorways, Doors, Walls, Jambs, Flooring, etc.) Contractor must identify the pre-existing damage to the Local Housing Representative in writing and provide a copy of the signed document by both the contractor and the local housing representative dated for the start date of the work performed in said unit or they can be held liable for the damages.

Coordination

6.1 All communications will go through the Local Housing POC listed. CG Personnel will make periodic site visits prior, during and will approve of completion of work. If the POC is unhappy with a section of home, then the contractor has 24 hours to correct discrepancy or provide a plan or timeline to fix discrepancy. No work can be modified or changed without their permission, required items

Page 4/4 identified for correction to an acceptable standard will not affect the final cost of the contract.

6.2 Work to be completed should have minimal impact on the unit’s operation. In the event any of the utilities need to be secured, these items should be well planned out.

6.3 Normal work hours for the unit is 8:00 AM to 3:00 PM, Monday-Friday, excluding all Federal Holidays. Any work outside these times needs to be worked out ahead of time with any change in cost being highlighted upfront and confirmation by contracting officer will have to be approved as an amendment to the contract. Extended work-day timeline can be accommodated as long as the 1 week, 5 work-day window of contractor’s access is maintained. Other contractors are scheduled in the same unit immediately following.

6.4 All required License, Certificates, Accreditation Card, etc. will be submitted with the quote or bid. There is also a minimum of two references being requested for submission with these documents.

Project Completion

6.1 All work completed is up to the POC’s approval. The site is to be at a minimum as clean of a condition it was found in. All trash, debris, materials removed, etc.

should be properly disposed by the contractor.

6.2 All units will become available on a VARIED TIMELINE roughly between the months of May to August; units WILL NOT be available at the same time for work to be performed and contractor cannot wait until all units are available before starting work.

6.3 All contractors work in the unit must commence within five days of notice from the units POC to the contractor of the unit’s availability. All work must be completed within a one-week (five working days) timeframe from the start date of that unit. If possible, the POC will give the contractor a 30-day notice prior to the availability date. All jobs will be completed as the contract is listed or any modifications agreed to with no new additions or modifications allowed to the contract after August 31, 2024, in preparation of the end of FY24.