Contractor’s Berthing Trailer questions and answer:
Has the site historically been prone flooding?
Historically, no. But that is the reason why the berthing trailers are being requested. During the month of June and July the Arkansas River valley experienced elevated levels of rain over a short time frame and caused the river to swell.
Utilities: in relation to trailer site where will sewer/water/electric be? What distance? Are we have to trench anything or will connection and tie in be very close?
Please refer to attached picture. Sewer connection is in within 15 ft. of potable water connection on the building.
Could you send aerial shots and grounds shots of location will sure need prep? Grading? Pathways etc. Would 1 trailer for berth/ kitchen and then another trailer for bathrooms and showers be acceptable?
Space is somewhat limited. Please have the CTR forward pictures of the previous configurations.
Create an L- formation and possible deck that communal space with a tent?