SOW_Replace_Roll_up_doors_in__Bldg._9_at__BMB.docx
DOCX document 962 KB Posted
- Solicitation number
- 70Z028-19-Q-PMW08600
About this file
Statement of Work for Roll up bay doors
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 52.212-3.docx | DOCX document | |
| 52.212-4.docx | DOCX document | |
| 52.212-1.docx | DOCX document | |
| 15-4543_Dade_Wage_Rate.txt | TXT text file | |
| 52.212-5.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF HOMELAND SECURITY
UNITED STATES COAST GUARD
BASE MIAMI BEACH
SPECIFICATIONS
FOR
Replace Roll up Service Doors At Building 9 RPUID #23070
General: United States Coast Guard Base Miami Beach is accepting proposals for qualified individuals or firms to replace two roll up service doors in Bldg. 9 at Base Miami Beach. Prior to submitting a quote, it is mandatory to examine the scope of work and it is highly recommended to visit the facility to take field measurements, evaluations, etc., and become familiar with existing conditions under which the work will be performed. After the award of contract, a pre-conference will be held prior to starting the work at Coast Guard Base Miami Beach
Location:
United States Coast Guard Base Miami Beach Fl.
100 MacArthur Causeway Miami, FL 33139
I. Continuity of Facilities Operation: Schedule work to minimize interference with the facility’s normal operations. Normal operating hours are from 6:30am to 4:00pm Monday thru Friday except federal holidays. Any work during other hours unless otherwise instructed or permitted shall be scheduled and approved with the Contracting Officers Representative.
II. Notification of Start and Completion of Work: The Contractor shall notify Coast Guard one week prior to start of work.
III. Coast Guard Contracting Officers Representative: The Contractor shall contact the COR to coordinate all construction efforts onboard Coast Guard Facilities.
| Mr. James Barone |
| James.A.Barone@uscg.mil |
| 305-695-2385 |
| CWO Jose A. Calderon |
| Jose.A.Calderon@uscg.mil |
| 305-535-4547 |
| LCDR Nicholas Paparis |
| Nicholas.A.Paparis@uscg.mil |
| 305-535-4589 |
IV: Recycling and Disposal of Refuse: Minor refuse, excess or waste materials resulting from construction operations may be disposed of in base dumpsters. All disposals shall be done in accordance with federal, state, and local laws and regulations. All bulk waste shall be disposed of in contractor provided dumpsters
V: Safety: During the execution of this contract, the Contractor shall conform to the rules and regulations as set forth by OSHA Safety and Health Standards, 29 CFR Part 1926 - Safety and Health Regulations for Construction. The contractor shall have a written safety plan as required in FAR 5.236-13. The plan shall unequivocally assign responsibility and authority for safety to the superintendent by name. Immediate notification to the Contracting Officer’s Representative of lost time due to accidents is required. Provide two copies of workman’s compensation accident reports by noon of the day following the accident. The Coast Guard reserves the right to bar any workers or supervisors from the premises should they be documented as violating set safety standards and regulations.
VI. Inspection: The Contracting Officer’s Representative has the right to reject defective workmanship or materials or work not performed as per the project specifications. Only the Contracting Officer or his/her representative may accept work performed by the contractor.
VII. Operations and Storage: The contractor is to take whatever steps necessary to ensure that his materials are protected. The Coast Guard has no responsibility for receipt, storage, or protection of contractor’s materials. All equipment, materials and supplies shall be addressed to the contractor. The Coast Guard will not accept shipments. The contractor is responsible for the protection of existing structures, utilities, work and vegetation. Any damage shall be repaired at the contractor’s expense.
VIII. Contractor Identification: The contractor and subcontractor personnel shall, at all times, wear company identification.
IX. Existing Utilities: The Contractor shall field verify all utility locations before commencing work. This shall include, but not be limited to, the use of visual, sonic, electronic or magnetic detection devices. Contractor shall be responsible for repairing any utilities damaged during construction at no additional cost to the Government.
X: Regulations while onboard Coast Guard Base Miami Beach:
1. Daily colors and the raising/lowering of the American flag will take place every morning at 0800 and every evening at sunset. All personnel on Base will face the main flag pole & maintain silence and all vehicles & equipment will halt during these brief events.
2. The construction site shall be maintained in a clean condition at all times. This included daily clean-ups of the construction and storage areas (FAR 52.236-12). The site shall be well lit and well barricaded/cordoned off as appropriate.
3. Contractors are welcome to eat breakfast & lunch on Base in the base galley at cost. Breakfast is served from 0600-0730 daily & lunch will be served from 1200-1300 daily in the galley. All personnel desiring meal service shall be in clean, non-soiled clothing. The Coast guard reserves the right to refuse service to anyone it deems dirty.
4. There are two smoking areas on base, one in the central northern parking lot covered by the tiki hut & one in the NW corner of the southern larger parking lot. No smoking is permitted anywhere else on base.
5. Contractors are welcome to utilize the Base’s Exchange store; however, contracted personnel are prohibited from purchasing any uniform, alcohol or tobacco products in it.
6. Traffic Regulations:
a) 10 mph speed limit
b) No use of cell phones is permitted while driving vehicles or operating heavy machinery
c) All personnel shall obey all marked traffic signals including stop signs & stop lights.
7. Absolutely no firearms or weapons of any kind are allowed onboard Base Miami Beach.
8. Only American citizens and permanent resident aliens are allowed onboard Base Miami Beach Facilities. Absolutely no foreign nationals are permitted on the premises.
9. Notice shall be given to the Coast Guard’s representative 1 week in advance of any planned power, water, and sewage or lighting outages.
10. The contractor shall provide a consolidated list of all contracted personnel including their driver’s license numbers (or other valid gov’t issued ID number) who will be working on Base Miami Beach Facilities either the day of or prior to the notice to proceed date.
11. Contractors are welcome to utilize the restrooms on the 1st decks of Buildings 3, 4, and 7 providing they are clean and do not track mud, dirt or any other debris into the restrooms.
12. Should warnings of gale force or stronger winds, or other inbound natural disasters be issued, the contractor shall take every practicable precaution to minimize the danger to persons, to the work, and the adjacent property. These precautions shall include closing all openings, removing all loose materials, tools and equipment from exposed locations, and removing or securing scaffolding, securing field trailers, and other appropriate equipment and other temporary work.
13. No personnel other than the contracting officer has the authority to alter the terms of any contract or to issue any change orders.
14. All contractor vehicles, equipment and gear onboard Coast Guard properties are subject to search at all times. Additionally at all times due to security and operational needs, the contractors is subject to orders to evacuate the property at any time.
15. Due to the compact & dense nature of operations & support functions ongoing on board Base Miami Beach, all efforts within reason to minimize the size and footprint of the contractor’s lay down area shall be taken. Contractors shall carpool as much as possible to minimize the number of vehicles needing parking on Base. At a minimum, the ratio of contractors to contractor vehicles shall be no less than 2:1.
16. All piers on base Miami Beach are load restricted in some form. If contractors need to bring heavy equipment (cranes, forklifts, 18 wheelers, man-lifts, construction equipment, backhoes, excavators or other equipment heavier than standard sedans) closer than 40’ to any pier on base to complete their project the contractor shall submit a request for information (RFI) to the Contractor’s representative.
VIII: SCOPE OF WORK: Contractor shall provide all labor, materials, and equipment necessary to complete the following unless noted below:
1. All work in this contract shall be completed in Building 9 onboard Base Miami Beach in Miami Beach, Fl.
2. Remove & dispose of paint booth rolling service door (approximately 20x20) in Building 9. Remove all accessories including but not limited to the door’s controls, rails, rail guides, motors & manual crank chains.
3. Remove & dispose of side rolling service door (approximately 12x11) in Building 9. Remove all accessories including but not limited to the door’s controls, rails, rail guides, motors & manual crank chains.
4. Provide & install a new Miami Dade County hurricane rated rolling service doors in locations specified.
5. Replacement doors are to be 18 gauge or stronger, galvanized steel rolling doors. Galvanized slats shall have a baked-on coating of epoxy-modified polyester.
6. Doors is to be furnished with electric safety edge bottom bars, which upon contact with obstruction, are to stop and reverse the downward travel.
7. Door operators shall be replaced in kind with respect to the style, i.e., pull chain doors shall be replaced with pull chain doors & motor operated doors shall replace motor operated doors. All pull chains shall be replaced with galvanized pull chains. All motor are to have integral gearing to provide for door locking. All hand chains shall be installed with locking bracket, which shall be mounted on guide angle to allow for hand chain locking.
8. Doors shall be fully weather stripped at the sill, hood & along the guides.
9. Rolling doors counterbalance roller shaft shall be of steel pipe of sufficient diameter to reduce deflection so as not to exceed 0.03 inch per foot of span. Springs are to be grease packed and are to be mounted on a cold rolled steel inner shaft. Springs shall be capable of producing sufficient torque to assure easy operation of the door curtain from any position. Spring tension shall be adjustable by means of an adjusting wheel on the end bracket.
10. Bracket plates shall be of minimum ¼" thick hot dipped galvanized steel designed to form an end closure support for the hood and fitted with self-lubricating bronze bearings or permanently lubricated sealed ball bearings.
11. Hoods shall be not less than 24 gauge hot dipped galvanized steel formed to fit contour of end brackets in a neat manner and reinforced with stiffening rolls at top and bottom edges. Hoods over 12' shall be laterally reinforced with internal hood supports to prevent sagging.
12. Door guides shall be hot dipped galvanized steel angles minimum 3/16" thickness and of sufficient depth to retain curtain in place under specified wind load (Miami Dade County Hurricane Rated). Guides shall be attached to jambs, plumb and true by bolts of not less than 3/8 " diameter, spaced not more than 30 inches on center.
13. Doors shall be interior mounted between jambs and under lintel where possible. If not possible, doors shall be interior face mounted.
14. Doors shall not interfere with the operations inherent to the facility (golf cart access, maintenance access, ingress/egress of key equipment in the facility, use of weight rails, vehicle access, use of blast booth, forklift access etc…).
15. Required delivery 60 days after award.
16. Contractor must provide Notice of Acceptance by Miami Dade County product control section certifying that all proposed products meet the requirements of the Florida Building Code, including the High Velocity Hurricane Zone.
17. Contractor shall provide dumpster and shall be responsible for all cleanup of the project area.
18. Contractor shall be responsible for the removal of the dumpster once the project is complete.
19. Contractor shall protect all equipment and merchandise in work locations.
20. All work must be approved by the Contracting Officer’s Representative.
Paint booth Rolling Door Approx: 20ft Approx: 20ft
Side Rolling Door Approx: 11ft Approx: 12ft image2.jpeg image3.jpeg image4.jpeg image5.jpeg image1.jpeg
File details come from the government source that posted it.