Attachment-8_SPC-HWX_II_QuestionsandClarificationsForm_CombinedGovtResponses_A00005.xlsx

XLSX spreadsheet 19 KB Posted

Attached to
Special Purpose Craft - Heavy Weather 2nd Generation (SPC-HWX II)
Solicitation number
70Z02325R93250001
Issued by

About this file

This file is a Questions and Clarifications form for the Special Purpose Craft - Heavy Weather 2nd Generation (SPC-HWX II) solicitation. The document addresses a specific inquiry about the design phase timeline and process for the project. The government clarified that design reviews will be used to refine the plan and establish final configuration and certification status of the engines, without changing the original design phase timeline or Design and Development Plan.

The solicitation, issued by the U.S. Coast Guard, requires delivery of the first boat within 18 months of the first boat delivery order, with a total project delivery timeline of 550 calendar days from the award date. The Statement of Work (SOW) establishes a milestone-based sequencing of four project phases, with flexibility for alternative delivery schedules through bilateral agreement. The project involves the development of a next-generation Special Purpose Craft designed for heavy weather operations.

View the file

Other files

File Type Posted
SF30_SPC-HWX II_A00005_4-8-2025.pdf PDF
Attachment-8_SPC-HWX-II_QuestionsandClarificationsForm_CombinedGovtResponses_A00004.xlsx XLSX spreadsheet
SF30_SPC-HWX II_A00004_3-25-2025.pdf PDF
Attachment-1_SPC-HWX-II_SPEC_A00004_03-24-2025.pdf PDF
SF30_SPC-HWX II_A00003.pdf PDF
Attachment-3_SPC-HWX-II_PriceSchedule_A00003.xlsx XLSX spreadsheet
RFP_70Z02325R93250001_A00003.pdf PDF
Attachment-2_SPC-HWX-II_SOW_02-21-2025_A00003.pdf PDF
Attachment-8_SPC-HWX II_QuestionsandClarificationsForm_CombinedGovtResponses_A00003.xlsx XLSX spreadsheet
Attachment-1_SPC-HWX-II_SPEC_02-21-2025_A00003.pdf PDF
SF30_SPC-HWX II_A00002_1-27-2025.pdf PDF
Attachment-8_SPC-HWX II_QuestionsandClarificationsForm_GovernmentResponses_A00002.xlsx XLSX spreadsheet
Attachment-3_SPC-HWX-II_PriceSchedule_A00001.xlsx XLSX spreadsheet
SF30_SPC-HWX II_A00001_1-13-2025.pdf PDF
SF1449_70Z02325R93250001_A00001_1-13-2025.pdf PDF
Attachment-8_SPC-HWX-II_QuestionsandClarificationsForm_GovernmentResponses_A00001.xlsx XLSX spreadsheet
Attachment-6_SPC-HWX-II_GFI_12-05-2024.zip ZIP file
Attachment-8_SPC-HWX II_QuestionsandClarificationsForm_RFP.xlsx XLSX spreadsheet
Attachment-5_SPC-HWX-II_Past Performance Questionnaire_RFP.pdf PDF
Attachment-3_SPC-HWX-II_PriceSchedule_RFP.xlsx XLSX spreadsheet
Attachment-1_SPC-HWX-II_SPEC_RFP.pdf PDF
Attachment-2_SPC-HWX-II_SOW_RFP.pdf PDF
Attachment-4_SPC-HWX-II_CDRLs_RFP.pdf PDF
Attachment-7_SPC-HWX-II_FAQ_RFP.pdf PDF
SF1449_70Z02325R93250001_12-10-2024.pdf PDF
Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Q&Rs

Question No.ReferenceQuestionsResponses
34Amendment 00004The Government has indicated the amended specifications will be further defined in the Design Review process. However, there was no amendment to the design phase timeline or allowance for this definition in the Design and Development Plan. The only reference to these definition periods were found in the narrative on SAM. Does the Government intend to amend the scope and timeline of the Design Phase?No. In A00004 the government indicated that design reviews will be used to refine the plan to establish final configuration and certification status of the engines. This is not intended to have bearing on the design phase timeline or Design and Development Plan. The government does not intend to amend the scope and timeline of the Design Phase.

SOW 068 Integration and Engineering establishes a milestone-based (not time based) sequencing of the four phases of the project.

SOW 040-7.1 states that the first boat shall be delivered no later than 18 months after issuance of the first boat delivery order.

Section III, (2) Required Delivery Schedule of the RFP indicates that the contractor shall delivery Phase 1: Design, Phase 2: Development, the first boat, and any ancillary items ordered no later than five hundred fifty (550) calendar days from the date of award but also states that alternative delivery schedules may be established through bi-lateral agreement.