Attachment 2 - SOW.pdf

PDF 528 KB Posted

Download PDF, 528 KB

Attached to
RFP - Maloney Canine Vet Clinic Addition
Solicitation number
70US0927R70094253
Issued by

About this file

This is a Statement of Work (SOW) for a design-build project to construct an addition to the Maloney Canine Training Center (K9 facility) at the James J. Rowley Training Center (JJRTC) in Laurel, Maryland, a United States Secret Service facility. The project scope encompasses a 2,479-square-foot addition on the southeast corner of the existing Kennel Building, with a 410-calendar-day performance period from Notice to Proceed.

The addition must include fifteen functional spaces: exam room (285 sq ft), X-ray room (126 sq ft), unisex restroom (59 sq ft), treatment area/surgery prep/dental area (386 sq ft), break area (73 sq ft), quarantine corridor (108 sq ft), veterinarian office (58.5 sq ft), veterinary technician office (112 sq ft), surgery (215 sq ft), underwater treadmill (140 sq ft), treadmill pump (70 sq ft), laundry/wash (366 sq ft), plumbing (44 sq ft), mechanical/electrical (70 sq ft), and storage (240 sq ft). The contractor must provide all design and construction services on a turn-key basis, including site preparation, exterior construction with specific metal panel siding options (Petersen Aluminum PAC-3000 RS, Highline S1, and HWP products with custom color matching), roof systems with pre-engineered steel trusses, interior walls, doors and frames, electrical and low-voltage systems, plumbing with specific materials (Type L copper or PEX prohibited), mechanical and HVAC systems with MERV 13 filtration, fire suppression and alarm systems compatible with existing Notifier equipment, communications infrastructure with Cat6A cabling, and comprehensive commissioning. The contractor must also conduct existing conditions surveys, obtain all permits, comply with Maryland environmental regulations and stormwater management requirements, provide weekly progress meetings and detailed scheduling using critical path method, establish quality control and safety programs per Army Corps of Engineers standards, and deliver as-built documentation including GIS data, CAD drawings, and IT systems information. All work must meet 2024/2026 International Building, Mechanical, Electrical, and Plumbing Codes, achieve 95% compaction density on foundations, and incorporate sustainable energy practices including 30% reduction below ASHRAE energy consumption levels. Key personnel requirements include a project manager with 15 years' experience, Designer of Record with 15 years' experience, construction superintendent with 10 years' experience, Quality Control Manager with 10 years' experience, Site Safety and Health Officer with 10 years' experience, and commissioning manager with 7 years' experience. All contractor personnel must be U.S. citizens and undergo Secret Service facility access clearance with minimum 14 working days' notice. A $175,000 allowance is provided for anticipated Baltimore Gas & Electric utility connection costs.

View the file

Other files

File Type Posted
Attachment 5 - Drawings.pdf PDF
Attachment 4 - Pre bid RFI .xlsx XLSX spreadsheet
Attachment 3 - Price Template.xlsx XLSX spreadsheet
Attachment 1 - K9 Vet Clinic Addition A-M.pdf PDF
RFP SF1442.pdf PDF

On GovTribe

Work with this file

  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

To Statement of Work (SOW)

Maloney Canine Vet Clinic Expansion

Project Background and Requirements

A. Project Background

1. The James J. Rowley Training Center (JJRTC) is the primary training facility for the United States

Secret Service (USSS). The campus is located at 9200 Powder Mill Road in Laurel, Maryland, approximately 490 acres. The United States Secret Service, James J. Rowley Training Center (JJRTC) is the main training facility for USSS personnel. The facility consists of multiple buildings including classrooms, offices, and tactical training venues spread over the campus. JJRTC must provide the best training environment for USSS law enforcement Agents, Officers and civilian support personnel.

2. The purpose of this project is to provide turn-key services for a design/build project to construct an addition to the Maloney Canine Training Center located on the JJRTC. This new footprint will be located on the southeast corner of the existing Maloney Canine building. The venue shall include several key spaces that will enable the care and treatment of the K9 occupants. The dimension of the base design will be 71’-6” x 34’-8” [2,479 square feet].

B. Period of Performance - The period of performance for this task order is 410 calendar days from date of ‘Notice to Proceed’ (NTP).

C. Project Requirements

1. Key Contact Entities

a. This contract shall be administered by USSS Procurement with construction management by

USSS RTC Facility Branch. For this statement of work, “Government” refers to the KO, the CS, or the COR: and “Contractor” refers to the Design/Build Contractor.

As a Minimum, the Following Guidelines Shall Apply to the Base Project A conceptional design showing a Top, Side, and Front View of the entire construction project with dimensions site capturing minimum requirements for size, dimensions, and slopes shall be included in the Technical Proposal.

b. The Maryland Standards and Specifications for Soil Erosion and Sediment Control standards put forth by the Maryland Department of the Environment (MDE) for erosion control shall be used throughout the project consisting primarily of silt fence placement, unless more stringent measures are deemed necessary by MDE.

c. All requirements stated in detail in the RTC MS4 JJRTC permit and applicable MDE regulations shall be followed

d. Manufacturers’ requirements and recommendations shall be followed.

e. Manufacturer’s full material and equipment warranty shall be extended to the USSS and will not begin until the project is finalized and closed.

f. Only high-quality commercial-grade materials and sealants shall be used.

g. All applicable Local, State, and Federal building regulations shall be followed.

h. All debris and unsalvageable materials shall be removed and sustainably disposed of from the

Campus as per applicable regulations daily.

i. All areas disturbed by construction shall have grass seed applied at a rate of 3 pounds per 1,000

sq. ft. to topsoil prepared to a depth of 4 inches. Topsoil shall be fertile, natural, and free of extraneous matter.

j. All construction sites for structures, roads, etc. shall have their subgrade tested prior to base material being placed to show they meet minimum Local, State, and Federal requirements.

k. All construction sites for structures, roads, etc. shall be nuclear density tested and achieve 95% of maximum dry density per standard proctor ASTM D698

l. All construction sites for structures, roads, etc. shall have a geotechnical evaluation conducted to ensure they meet minimum Local, State, and Federal requirements

m. All structures and supporting infrastructure shall be designed to withstand heavy rain, snow, and

2 | P a g e wind, accounting for a ten-year storm event

n. All work shall be turn-key.

o. Necessary power, water, gas, and communication utility requirements shall be verified prior to work start.

p. All utility outages shall be routed through the USSS COR with a minimum lead time of 14 calendar days.

q. All hot work shall be routed through the USSS COR with a minimum lead time of 3 business days.

r. All labor, personnel, equipment, supplies, facilities, transportation, tools, materials, engineering, and supervision necessary to meet the requirements established in this SOW shall be provided by the Contractor.

2. Remove existing door, concrete slab and fencing: The contractor shall remove the existing door and adjacent concrete slab.

a. The contractor shall remove an existing door, door frame and all associated mechanical items.

The remaining infrastructure reinforced (as needed) to ensure the facility’s structure soundness and compliance with local, state, and International Building Code Criteria.

b. The contractor shall remove the concrete slab that is located at the door on the southeast corner of the Kennel Building [staging area (room #429)], and out in break yard #2.

c. The contractor shall detach and remove all fabric, mesh, pickets, rails, gates, and mounting hardware along the designated fence line.

D. Scope

1. Construct an addition to the Kennel Wing of the Maloney Cannie (K9) (See Attachments for

Guidance) The contractor shall construct a facility addition that closely resembles the existing structure per the design, building materials, color of the interior and exterior of the perimeter walls, and all other characteristics of the existing facility.

a. The contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to construct the addition to the Maloney Cannie Facility. The listed square footages shall be at a minimum and shall be designed in a manner that will successfully accommodate the end users. The facility shall include the following spaces:

i. Exam Room

a) The space is approximately 285 square feet

b) The space shall include a desk and a wrap-around countertop and a sink.

ii. X-Ray room

a) The space is approximately 126 square feet

iii. Unisex Restroom

a) The space is approximately 59 square feet

b) The space shall have a small vanity

c) The space shall have a water closet

iv. Treatment area/Surgery Prep/Dental Area

a) The space is approximately 386 square feet

b) The space shall have two (2) large sinks and a countertop that stretches the length of the room.

c) The space shall have a dental wet table

d) The space shall have sufficient space for a Dry/Prep mobile table

v. Break area

a) The space is approximately 73 square feet

b) The space shall have an area for a sink, countertop, and cabinets

c) The space shall have an area that will accommodate a small refrigerator.

vi. Quarantine Corridor (Isolation Room)

a) The space is approximately 108 square feet

b) The space shall include a sink and a small countertop

c) The space shall include ample space to accompany two (2) cages (30” x 48”) and a pantry cabinet.

3 | P a g e

vii. Vet office

a) The space is approximately 58.5 square feet

viii. Vet Tech Office

a) The space is approximately 112 square feet

ix. Surgery

a) The space is approximately 215 square feet

b) The space shall have one (1) large sink and a countertop that is the length of the exterior wall

x. Underwater treadmill

a) The space is approximately 140 square feet

xi. Treadmill pump

a) The space is approximately 70 square feet

xii. Laundry/Wash

a) The space is approximately 366 square feet

b) The space shall consist of Mop station and a Wash Station

c) The space shall include a suitable location for a washer and dryer to include the proper utilities and drainage.

xiii. Plumbing

a) The space is approximately 44 square feet

xiv. Mechanical/Electrical

a) The space is approximately 70 square feet

xv. Storage

a) The space is approximately 240 square feet

2. Site Preparation

i. Establish erosion and sediment controls, clear vegetation, and excavate utility trenches according to civil design drawings.

ii. Install a 4-inch to 6-inch PVC gravity-fed sanitary sewer lateral.

iii. Install a domestic water service line and a separate dedicated fire service main (if required by local fire code for fire sprinklers)

iv. Lay down storm concrete pipes, catch basins, and tie into the site's retention pond or municipal storm system.

v. Excavate and install Schedule 40/80 PVC electrical conduits and telecom/fiber banks from the utility poles or transformers.

vi. Backfill trenches in 6-to-8-inch lifts, compacting to 95% Modified Proctor density under paved areas to prevent future sinking.

vii. Installation of an outdoor, accessible sampling manhole or inline solids interceptor basket on the sewer lateral to trap animal hair and plaster sediment from veterinary casting before it hits the JJRTC complex main.

viii. Extra exterior backflow preventers and dedicated shut-off valves for isolation, ensuring medical procedures are not disrupted by mainline municipal maintenance.

3. Construct of the exterior of the addition to the Kennel Wing of the Maloney Cannie (K9) (See Attachments for Guidance) The contractor shall construct a facility addition that closely resembles the existing structure per the design, building materials, color of the interior and exterior of the perimeter walls, and all other characteristics of the existing facility.

i. The siding of the exterior walls shall include the following:

a. Ground face CMU finish

b. Precast Water table finish

c. Metal panel (MP) siding (MP-2, MP-3, MP-4) (or similar)

1) MP-2 MANUF: PETERSEN ALUMINUM CORP – PAC CLAD

1) Product Line: Composite Wall Panel PAC-3000 RS

4 | P a g e

2) Color: Custom Color Match EMF-2

3) Panel Size: ~ 30” x 6’- 0”

4) Fush Panels W/~ 1” Wide Grid

2) MP-3 MANUF: PETERSEN ALUMINUM CORP – PAC CLAD

1) Product Line: Highline S1 (W/ ~ 12” coverage)

2) Color: Custom Color Match EMF-3

3) Horizontal Rib Panel – One 10” rib with ~ 2” reveal

3) MP-4 MANUF: PETERSEN ALUMINUM CORP – PAC CLAD

1) Product Line: HWP (W/~ 16” coverage)

2) Color: Custom Color Match EMF-4

3) Horizontal Rib Panel Ribs Space equally at ~ 3” to 4” O.C.

d. Metal Panel siding (MP-5 color band)

1) Metal color band of formed profile contour

2) Custom color matching EMF-5

e. Metal Panel Siding (MP-6)

1) Custom color matching EMF-5

ii. Exterior wall of the addition shall encompass the entire newly built foundation pad from Section A and shall be approximately 71’-6” long by 34’-8” wide overall.

iii. Ceiling height of at least a 9-foot minimum shall be maintained throughout the addition considering the ductwork, fire suppression, etc.

iv. The Contractor’s services shall consist of a single company capable of providing Architectural/Engineering (A/E) design services related to the design of this addition in its entirety.

v. American Society for Testing and Materials (ASTM) Standards for Manufactured Masonry Units shall be followed for constructing this addition

vi. Portland cement and aggregates used shall comply with the minimum requirements of

ASTM

vii. Minimum compressive strength, minimum water absorption, and minimum modular dimension requirements of concrete masonry units shall comply with the minimum requirements of ASTM

viii. Minimum face shell, web thickness, and equivalent web thickness requirements shall comply with the minimum requirements of ASTM

ix. Concrete masonry shapes, sizes, and colors shall match the existing structure

x. Materials such as admixtures and colors are not covered by these minimum requirements and shall be approved by the USSS COR during the Design Phase

xi. Contractor shall be responsible for all defects, including cracking outside of designated saw-cuts and any other such defects that may interfere with the proper alignment or impair the strength of a concrete masonry element

xii. Materials Testing and Evaluation shall be done before, during, and after construction to verify compliance with this SoW using ASTM Standard Test Methods of Sampling and Testing Concrete Masonry Units

xiii. Mortar shall follow ASTM requirements for selection, quantity and use of specified ingredients in masonry mortar. When neither proportion nor property specification is specified, the proportion specification governs.

xiv. Blocks shall be properly laid on a full-bed of mortar, keeping the courses levelled and vertically aligned.

xv. Wall ties and fasteners shall be used as specified by the manufacturer

xvi. Where built-in items are to be embedded in masonry units, reinforcement shall be placed as per the manufacturer.

xvii. Masonry shall be constructed to accommodate the work of other trades, as required for subsequent installation of utilities, equipment, and services.

xviii. W here cutting is required, the Contractor shall provide clean, sharp, and unchipped edges

xix. Complete masonry units and mortar materials shall be covered or shaded whenever ambient air temperature reaches destructive levels as per the manufacturer’s specifications

5 | P a g e

xx. Incomplete masonry elements shall be covered with waterproof sheet material when masonry work is not underway

xxi. Curing shall be provided as per the manufacturer’s specifications

xxii. Interior CMU blocks shall be painted with a high-quality acrylic latex. The paint color and type shall be approved by the USSS COR prior to beginning painting.

Block skirting on the exterior wall measuring 57 linear feet long by 15 inches wide shall match the shape, size, color, and design of the existing structure All vent pipes shall have special metal caps or heavy-duty mesh (1/4-inch stainless steel over wire cloth) fitted over roof/attic vents to stop wildlife from entering through these openings All holes or gaps larger than 1/2 inch in soffits, fascia, or walls shall be sealed with durable materials to prevent wildlife intrusion into the facility.

4. Construct Roof System

i. Framing

a. Install a pre-engineered steel truss system configured for a 4/12 roof pitch.

ii. Decking and Underlayment

a. Install structural metal roof decking followed by a high-temperature, self-adhering waterproof underlayment.

iii. Insulation

a. Lay down rigid polyisocyanurate (polyiso) board insulation across the deck roof to achieve energy code compliance

iv. Roof Panels

a. Install a 24-guage standing-seam metal roof system with concealed chips and stainless-steel fasteners.

v. HVAC Curbs:

a. Flash, seal, and structurally reinforce curb(s) to support the specified rooftop HVAC unit(s).

vi. Snow Guards

a. Mount heavy-duty, color-matched pad or rail snow guard along roof eaves directly above all main entrances.

vii. Drainage

a. Install commercial-grade aluminum gutters, downspouts, and heavy-duty edge flashing.

5. Construct interior walls

i. Wall framing

a. Install 3 5/8” gauge structural steel studs 16” on center. Install heavy duty blocking for wall mounted equipment.

b. Secure blocking for heavy surgical lights and monitors

c. Reinforce tracks at all major high-traffic corners.

ii. Insulation and Soundproofing

a. Install R-11 fiberglass blanket insulation in exam room

b. Place sound attenuation blanket insulation in surgical suite

c. Seal top and bottom tracks with acoustic sealant

iii. Drywall Installation

a. Hang 5/8” Type x fire rated drywall standard

b. Use monture resistant (greenboard) drywall in wet areas

c. Install abuse-resistant drywall in hallways and high traffic areas

d. Prevent cross-contamination between rooms via ceiling plenums

iv. Finishings and Wall Protection

a. Tape and mud to level 4 finish

b. Level 5 finish in Surgery and Treatment and surgery prep/Dental room

c. Install high-impact plastic corner guards at intersections.

6 | P a g e

6. Doors and Frames

i. Frames

a. Securely anchor 16-guage knocked-down or welded hollow metal frames into the metal stud plumbing.

ii. Doors and Specialty Doors

a. Hang 1 ¾” solid-core wood doors for exam rooms.

b. Commercial hollow metal doors for high-impact zones.

c. Install a lead-lined door and matching frame for the X-ray room to ensure radiation safety.

iii. Hardware and Seals

a. Mount commercial-grade heavy-duty hinges, silencers, kickplates, and level locksets.

b. Add perimeter smoke seals and automatic drop seals on isolation (Quarantine Corridor), and surgery doors for sound and odor control.

7. Electrical and Low-Voltage Path

i. Service Panel

a. Install a commercial-grade 400A, 120/240V, 3-phrase main distribution electrical panel.

ii. Wiring

a. Provide dedicated circuits and drop connections for heavy medical veterinary equipment, including x-ray machine, surgical lights, autoclaves, and oxygen concentrators.

iii. Lighting

a. Install recessed, dimmable LED cleanroom-rated lights troffers in Surgery and

Treatment/Surgery Prep/Dental.

b. Install moisture-resistance LED fixtures in Rehab/Laundry/Mop/Storage, Underwater Treadmill, Quarantine Corridor and other wet areas.

iv. Outlets

a. Install code-complaint GFI outlets along counter backsplashes and emergency backup-powered orange outlets (generator-ties in applicable) in Surgery and other key rooms.

v. Low-Voltage Paths

a. Run conduit and pull strings for clinic-wide internet data drops, IP security cameras, and intercom paging stations.

8. Plumbing Systems

i. Drainage

a. Install commercial cast iron or schedule 40 PVC waste lines. Plumb heavy-duty trench drains or floor drains in kennel zones and grooming rooms.

ii. Lint/Hair Interceptors

a. Install inline hair/sediment traps in the wash stations floor drains to prevent main sewer line blockage.

iii. Water Supply

a. Run hot and cold type L copper or PEX water lines to the exam room, treatment/surgery prep/dental, and the surgical sinks.

iv. Specialty Medical Gas:

a. Install and certify central medical gas lines (Oxygen and Nitrous Oxide) piped from a secure manifold tank room directly into the surgery and treatment/surgery prop/dental rooms.

9. Mechanical and HVAC system

i. Equipment

a. Furnish and install all required high-efficiency commercial rooftop unit(s), split

7 | P a g e systems, or heat pump(s).

ii. Dedicated Outdoor Air Systems (DOAS)

a. Install and dedicated 100% outside air exhaust/supply systems serving the Quarantine Corridor and boarding wards to prevent air recirculation to general clinic spaces.

iii. Roof Curbs and Structural Supports

a. Supply and install all engineered roof curbs, vibration isolation rails, and equipment mounting pads.

iv. Exhaust Systems:

a. Install independent, heavy-duty exhaust fans for high-moisture/high-odor zones, including bathing areas, lab spaces, and janitorial closets.

v. Air distribution and Filtration

a. Ductwork Fabrication: Fabricate and install supply, return, and exhaust duct network compliant with SMACNA Seal Class standards to minimize leakage.

b. Install external or internal fiber-free acoustic duct insulation on all supply lines to ensure quiet operation in treatment and recovery rooms.

c. Filtration Systems

1) Install dedicated, independent HEPA filtration racks for surgical suites

2) Install minimum MERV 13 filtration systems for all general use and waiting areas

d. Supply and install supply diffusers, linear slots, and return grilles positioned to maximize MERV 13 filtration systems for all general use and waiting areas.

vi. Pipping Controls and Electrical connections

a. Run insulated copper refrigerant lines and hard-piped PVC condensate drain lines tied directly into the building's drainage system

b. Install a centralized, programmable digital Building Automation System

(BAS) or commercial multi-zone thermostats featuring remote monitoring and humidity readouts

c. Complete all low-voltage control wiring. Coordinate final high-voltage hookups with the project's electrical contractor.

Note: Compliance: All work must adhere to the 2024/2026 International Building, Mechanical, Electrical, and Plumbing Codes (IBC/IMC/NEC/IPC).

Testing: The contractor must perform and document duct-blaster leak tests, electrical load balancing, and plumbing pressure tests prior to drywall enclosure.

10. Communications

i. Pathways installation: Install J-hooks, conduits, and bridle rings above drop ceilings every 4 or 5 feet or as recommended.

ii. Run Plenum-rated Category 6A (Cat6A) unshielded twisted pair (UTP) cabling to ensure fast transfer of large digital X-ray and ultrasound files

iii. Build a centralized Intermediate Distribution Frame (IDF) network closet with a 4-post rack, patch panels, and wire managers

iv. Terminate cables using T568B standards and certify all lines with a Fluke cable analyzer

v. Apply a consistent alphanumeric labeling system at the patch panel, cable ends, and faceplates

vi. 4 data drops for workstations/VoIP phones, 1 drop for digital signage

vii. 2 data drops per room (1 for the veterinarian's workstation, 1 for a wall-mounted client education screen or smart scale)

viii. 6 data drops for the central treatment island, laboratory equipment (in-house blood analyzers), and pharmacy refrigerators

ix. 4 dedicated Cat6A drops for digital X-ray (CR/DR) modalities, PACS viewing stations, and physiological monitoring equipment

x. 4 data drops for IP security cameras to monitor recovering animals and smart infusion

8 | P a g e pumps.

11. Fire Suppression

i. Material and Equipment

a. Piping – Schedule 40 steel or CPVC fire-blaze piping

b. Sprinkler Heads – Quick response wet pipe heads (concealed or pendant style)

c. Specialized Zones - Clean agent systems (like FM-200 or Novec) for surgical/X-ray suites to protect expensive medical gear.

d. Backflow Preventer - Code-compliant valve to protect municipal water.

ii. Installation

a. Create necessary ceiling and wall penetrations

b. Secure pipe hangers to structural beams

c. Install overhead grid network

d. Cut and install drops to finished ceiling heights.

e. Connect flow switches and tamper switches to Maloney Cannie main fire alarm panel.

iii. Testing and commissioning

a. Pressure test system at 200 PSI for two hours

b. Clean underground and overhead lines of debris

c. Coordinate and pass the final visual and functional inspector walkthrough

d. Label all control, rain, and test valves.

12. Install Garage Door (access into the storage area)

i. The Contractor shall install a powered 10 foot tall by 12-foot-wide garage door on the addition centered on the wall facing the new concrete driveway. Location shall be submitted to the USSS COR for approval during the design phase and verified prior to installation.

ii. Garage door model shall be Extreme 1024 High Performance Door Model EPI1024 or equal, commercial grade, insulated motorized door with industrial 1 phase 240V motor, and rated for 30 PSF maximum wind load with perimeter sealing guides on both sides of the door

iii. Garage door shall seal on the concrete foundation and have pull chain backup

iv. Wall-mounted garage door opener shall be installed beside the entry door on the interior side of the addition

v. An LED Floodlight shall be installed centrally above the garage door on the exterior side of the addition with automatic sensors

vi. Steel bollards shall be installed: 1 on each side of the garage door and 1 beside the farthest edge of the addition, closest to the road. Bollards shall be painted with epoxy yellow paint to match the existing bollards on site.

13. Pre-Bid Site Investigations

a. Offerors who submit a proposal must attend a pre-bid site visit that will be scheduled during the solicitation period to verify field conditions referenced in this SOW. If additional clarification is necessary, the bidders must submit in writing a formal request for information (RFI) to the Contracting Officer.

Administrative Project Requirements A. Safety Requirements

1. Health and Safety Standards: The facilities, systems, and commercial-grade equipment design standards of the Occupational Safety and Health Act, Code of Federal Regulations, Title 29, Chapter XVII, Parts 1910 and 1926 as applicable shall be incorporated by the Architect-Engineer into all engineering design and analyses furnished pursuant to this contract. Any problems in incorporating these standards due to conflicts with other technical criteria shall be promptly submitted to the Safety, Health and Environmental Programs Division and Contracting Officer for decision.

9 | P a g e

2. Accident Prevention Plan (APP) and Activity Hazard Analysis (AHA): Before initiation of any work, the Contractor shall develop and submit to the Safety, Health and Environmental Programs Division and COR for acceptance a comprehensive site specific Accident Prevention Plan (APP) and Activity Hazard Analysis (AHA), in accordance with EM-385-1-1, U.S. Army Corps of Engineer Safety and Health Requirements Manual (latest edition at time of solicitation on website): http://www.usace.army.mil/SafetyandOccupationalHealth.aspx).

3. Site Safety and Health: The Contractor shall comply with FAR 52.236-13 and all site/safety/health/ environmental/personal protection and pedestrian/vehicular traffic control plans. The APP and AHA shall comply with Occupational Safety & Health Administration (OSHA) rules/regulations/laws, Corps of Engineers Safety and Health Requirements EM 385-1- 1, Federal Highway Administration (FHWA) standards/recommendations (if applicable), Uniform Federal Accessibility Standards (UFAS), Architectural Barriers Act (ABA) and all other laws, codes, rules, regulations, executive orders, Authority Having Jurisdiction (AHJ) and guidelines applicable or associated with the type of work required under this contract prior to the start of on-site work. In the event of conflict between any requirements the more stringent requirement shall apply.

4. Other Government Contractor’s Construction Zone: In the event the Contractor’s activities require them to traverse into an Other Government Contractor’s (OGC) construction zone, the Contractor and their subcontractors shall be responsible for participating in the OGC’s safety training program.

5. First Response Coordinator for Emergency Services: The Contractor’s Site Safety and Health

Officer (SSHO) shall ensure that all their employees are aware that for emergencies inside the campus are to call 911. All injuries or incidents shall be reported to the COR and Government Safety Representative within one hour of the occurrence. The Contractor is required to use the USACE ENG 3394 Accident Reporting Form and submit within 5 business days of an accident/incident.

6. The Contractor must limit production of particulates during construction and ensure that no airborne particles leave the space in question. High Efficiency Particulate Air (HEPA) vacuums are required.

7. The Contractor shall take all reasonable measures to protect USSS personnel and property from exposure, injury or damage resulting from their operations. The Contractor shall be responsible for the cost of restoration work to the Government’s property.

B. Existing Conditions Survey, Testing, and Reports

1. Existing Conditions Survey: The Contractor shall conduct an existing conditions survey of areas which have direct impact on the project. The survey shall include all systems affected by the scope of work including those not functional at the time the survey was conducted. The Contractor shall evaluate the availability, capacity, location, and connections of existing utilities including telecommunications and sources of temporary utilities. The Contractor shall survey all components of the architectural (including exterior perimeter walls) and technical requirements.

2. Existing Conditions Tests: The Contractor shall be responsible for performing any testing necessary to confirm the existing conditions are adequate for the full execution of all planned work (e.g. structural capability, geotechnical investigation, mechanical commercial-grade equipment, power). If the Contractor proceeds with the work before testing and confirmation have been completed, any rework due to issues with unsuitable existing conditions shall be at the cost of the Contractor. This includes implementation of manufacturer’s recommendations, recommended tests, and validation of product’s installation requirements.

3. Existing Conditions Reports: The Contractor shall provide existing conditions report for http://www.usace.army.mil/SafetyandOccupationalHealth.aspx

10 | P a g e

Government acceptance. The existing conditions report shall summarize the findings from the existing conditions survey. All deficiencies and any modifications to the existing conditions shall be identified in the existing conditions report and the report shall be presented within 60 calendar days from Notice to Proceed (NTP). Failure to identify deficiencies in the existing conditions reports shall indicate the Contractor’s concurrence that such systems are in good working condition or shall be brought to acceptable working conditions by the Contractor according to the technical requirements of this RFP. The Contractor shall include utilities. All necessary modifications to the existing systems shall be identified in the existing conditions report and included in the Contractor’s design

C. Design and Construction Submissions

1. Design Work: The Contractor shall provide a design for the work under this contract in accordance with the requirements of this RFP, any referenced attachments, and all applicable local, state, and federal codes. The design shall be functional, compatible with existing systems, and shall meet the overall project scope, cost, and schedule. The design for this project shall be coordinated with existing conditions in adjacent spaces as to not cause any safety hazards or adverse impacts to existing systems. All systems, devices, doors and other work, commercial-grade equipment and commercial-grade materials designed, modified and/or installed by the Contractor shall be compatible with and operate in conjunction with existing systems.

2. Obligating the Government: The Contractor cannot obligate the Government. The Contractor shall not assume any design components that holds the U.S. Government financially liable.

3. Designer of Record (DOR): The Contractor shall obtain the services of a designated Registered Architect/Professional Engineer defined in Unified Facilities Criteria UFC 1-300-09N to serve as the Designer of Record (DOR). The DOR must have proven experience in design, installation, and commissioning in projects of similar scope and is the design-certifying authority throughout the project. The DOR shall be involved at every step of the project and is responsible for design work of his or her respective discipline.

4. Design Packages: The Contractor shall produce a design package in accordance with industry standards and UFC 1-300-09N.

5. For the Issue for Construction (IFC) submission and all submissions during construction, the DOR shall seal, date, and sign all components of the submission in hard copy form as released for construction and provide copies for distribution from the original set. The DOR shall electronically sign and date Issue for Construction (IFC) submissions in accordance with UFC 1- 300-09N.

6. Design documentation and specifications shall not be proprietary.

7. The Contractor shall provide Erosion and Sedimentation controls as required by Federal, State and local laws and regulations. General Permit for Stormwater Associated with Construction Activity (if >1 acre of land disturbed) and the MS4 Phase II General Permit for State and Federal Agencies (if > 5,000 square feet or > 0.1 acres of land area or 100 cubic yards or earth movement are involved.

8. Reforestation plan.

9. Government review or acceptance of any design submission under this contract shall not relieve Contractor of its sole responsibility to perform all contract requirements and deliver a product that in all respects conforms to the contract requirements. Acceptance/review by the Government shall not constitute a waiver or change to the contract requirements unless that change or waiver is expressly approved in writing by the Contracting Officer.

11 | P a g e

10. Submittals: All construction submittals such as Pre Construction, design, shop-drawings and close-out documents shall be reviewed by the DOR and contain the DOR approval stamp with signature and date along with corresponding specification number and paragraph, variation / deviation notification, and whether the submittal is For Information Only (FIO) or Government Acceptance (GA). All submittals shall also be reviewed by the Contractor’s Quality Control Manages (QCM) and contain the QCM’s stamp with signature. The stamp(s) shall also identify the specific project, transmittal number, submittal description and corresponding date of submittal. If the information is not complete, the submittal shall be rejected and returned to the Contractor. Submittals that contain deviations from the SOW must be specifically identified as containing a deviation from the SOW and contain a detailed explanation for the deviation.

Government review or approval of any design document submittal, shop drawing or plan shall not be deemed to approve any deviation from the SOW unless the deviation is specifically identified in the submittal and expressly approved in writing by the Government.

11. Design Coordination with Other Government Contractors (OGCs) and Other Government

Agencies: The Contractor shall coordinate work with OGCs and shall carefully adapt its design (as applicable), schedule and performance of the work to accommodate the work of the OGCs.

The Contractor shall take coordination direction from the COR. The Contractor shall make every reasonable effort to avoid interference with the performance of work by the OGCs, as scheduled by the OGCs or by the Government. The Contractor shall be responsible for coordinating the work of OGCs and other Government agencies into their design package (as applicable).

12. Telecommunications: T he Contractor shall be responsible for designing, providing, and installing all fiber, copper, power and pathways to support IT infrastructure including but not limited to conduits, pull boxes, cable trays, wall outlet boxes, classroom floor boxes, pull strings, column boxes, rough-ins, grounding, bonding, and power requirements. The CIO office shall provide the Contractor with tie-in locations. The Contractor shall be responsible for all wiring and connections. The Contractor shall install/terminate 48 Pair/96 Stands Single-mode Fiber (SMF) optic cable. All fiber optic cables will be rack mounted in fiber distribution panels and will utilize SM LC connectors for all terminations.

13. Paint Requirements: Shall conform to the James J. Rowley Master Plan. Applicable section is attached.

14. Stormwater Management: The Contractor must follow requirements stated in detailed in the RTC MS4 permit and applicable Maryland regulations.

15. Plumbing Requirements.

a. Insulate and heat trace all water lines that occur outside the building envelope, including in unconditional spaces. No Armor Flex. Provide Fiber-Glass insulation with PVC jacketing.

Provide in all uncondoned spaces. Insulate all water lines.

b. PVC pipe (schedule 40 or 80) or Fernco couplings with shear bans are acceptable

c. No PEX or CPVC is allowed.

d. The Contractor shall provide access panel to the chase with shut-off valves.

e. The Contractor shall provide isolation valves at every floor (for hot, cold, return) with access on the inside. Ball valves are acceptable. Gate and butterfly valves are acceptable for pipes greater than 2”.

f. The following is acceptable for water lines. Underground to be ABS black poly.

Underground pipe above 2” blue brute is acceptable. Provide tracer wires for all

12 | P a g e underground water pipes. Must provide isolation valves. Type L copper is acceptable for inside conditioned buildings and structures.

g. Waste piping. PVC (schedule 40 and 80), SDR are acceptable when underground. Provide tracer wire when underground. Cast iron no hub is acceptable in buildings and structures.

h. USSS must have access to all plumbing and commercial-grade equipment for maintenance throughout the project lifecycle.

16. Utilities and Underground pipes

Contractor shall be responsible for verifying and accounting for utilities as a part of this contract during design and construction. Contact Miss Utility for markings. Refer to the GIS schematic for known utilities at the project site include.

a. Provide detectable aluminum plastic backed tape for detachable magnetic plastic taped manufactured specifically for waring and identification of direct buried piping. Tape must be detectable by an electrical detection instrument. Warning tape to be color-coded with waring and identification of utility type imprinted in bold black letter continuously over the entire tape length. Warning and identification to read “CAUTION, BURIED (utility type) LINE BELOW” or similar wording.

b. All utilities shall be sized to accommodate future expansion.

c. The contractor is responsible for the connection of all utilities and the proper coordination with the applicable utility authority; utility connections include but not limited to power, communications, potable water and sewer.

d. No utility marking resources are available on-site, therefore, at the contractor’s expense, he/she shall arrange separately the services of a private utility locating company. At a minimum, utility marking scanning should (or shall) be accomplished with GPR and/or appropriate equipment, and the surfaces where existing underground utilities are found should (or shall) be marked. Also, elevations and existing piping/utilities discovered during scanning should (or shall) be verified.

e. Contractor is responsible for verifying and accounting for removal and/or relocation of all utilities as a part of this contract during design and construction.

f. All utilities and controls shall tie into the head end unit at the Eytchison Building and be compatible with the Honeywell Niagara N4 framework.

g. HVAC

i. The entire building shall utilize a Heating Ventilation Air Conditioning (HVAC) system.

As a minimum, the system shall be a roof-top high-capacity central system to handle rapidly varying occupant & equipment load, manage high carbon dioxide levels and use forced air equipped with electronically controlled motorized dampers within the ductwork. The system shall be designed with variable speed drives and have increased fresh-air rates, and advanced filtration and UV sanitization to maintain minimum indoor air quality of MERV 13 or better filtration. Furthermore, the system shall utilize the campus building automation system to handle different heating/cooling needs for the bathrooms and other spaces simultaneously. To maintain a quiet environment, the system shall implement the required techniques so to not interrupt venue event experiences.

17. Electrical Requirements:

a. Electrical panels serving the project area shall have a minimum 50% spare capacity.

b. All low voltage wiring, including security, IT, and controls, shall be in continuous pathways.

These pathways shall be furnished and installed by the Contractor after fully coordinating and documenting the locations with Other Government Contractors (OGC) as applicable.

Pathways shall be of rigid conduit or cable tray and installed in accordance with the applicable code.

13 | P a g e

c. All lighting shall be LED.

d. Baltimore Gas Electric (BG&E) is the local utility provider for the JJRTC. The Contractor is responsible for all aspects related to coordination, providing temporary & permanent power, lighting poles, fixtures and providing turn-key electrical services for the project. The Government has allocated $175,000 allowance for anticipated costs from BG&E to provide new or additional electrical services to the project.

18. Fire Protection and Life Safety

a. Applicable code requirements.

b. Fire Alarm and Mass Notification Systems

i. The RTC fire alarm and mass notification system is manufactured by Notifier®. Any new commercial-grade equipment shall be manufactured by or fully compatible with Notifier® to operate accurately and reliably with the existing system. Modifications to the existing system and new systems shall incorporate mass notification requirements and be compatible with the existing system network.

ii. Fire Alarm and Mass Notification System Shop Drawings: The Contractor shall provide complete information on system additions and modifications per NFPA 72, including specifications, type of system, shop drawings, input/output matrix, battery calculations, point-to-point wiring diagrams for initiating devices and notification appliance circuits, and notification appliance circuit voltage drop calculations submitted for approval.

iii. Fire Alarm As-Built shop drawings shall be provided including source files. There shall be no exclusion of documenting small diameter wires as applied specifically to fire alarm initiating circuits and fire alarm notification appliance circuits. Although these fire alarm wires have a smaller diameter, they are essential for maintaining the fire alarm system.

c. Fire Suppression Systems

i. The Contractor shall provide complete information on system additions and modifications in accordance with the appropriate NFPA Standard (e.g., NFPA 13, 15, 20, 2001) submitted for approval.

ii. Fire Suppression as-built shop drawings shall be provided including source files.

19. Emergency Egress Plans: The Contractor shall include Emergency Egress Plans in all design packages.

20. Design Deliverables

a. The Government shall provide a base file for design once a base file is available.

b. The Contractor’s design and specifications shall document correct size, capacity, location, and connections to meet project requirements.

c. Unless specified otherwise, the Contractor shall provide commercial-grade materials and equipment that are products of the manufacturer regularly engaged in the production of such products which are of equal commercial-grade material, design and workmanship. Products shall be in satisfactory commercial or industrial use for 2 years prior to bid opening. The 2-year period shall include applications for commercial-grade equipment and materials under similar circumstances and of similar sizes. Commercial-grade materials and equipment shall not be end-of-life products or in the final stages of a product’s existence.

d. The Contractor’s design deliverables shall comply with UFC 1-300-09N and requirements listed within the RFP.

14 | P a g e

e. Basis of Design (BOD): The Contractor shall develop a BOD for all design submissions and include all disciplines. The BOD narrative, broken out by discipline, shall include design and engineering calculations and assumptions in support of the design and shall describe the systems, components, conditions, and methods chosen to meet the project requirements and design intent.

f. Specifications: The Contractor shall provide project specifications that, in conjunction with the drawings, demonstrate compliance with commercial-grade materials, commercial-grade equipment, execution, field quality control requirements. The Contractor shall provide location and project-specific Division 01 specifications. The products specified shall include commercial-grade equipment, fixtures, devices, and systems to be utilized in the construction of this project. Per ER-1110-1-8155, specifications shall follow CSI Master Format® (latest edition).

g. Design Quality Control (DQC) Plan: The Contractor shall provide a project-specific DQC

Plan for acceptance by the Government. No design submission shall be received until the DQC Plan is accepted by the Government. The DQC shall include a brief presentation of internal controls and procedures that the Contractor shall use to ensure that a quality design is produced, including:

i. Design management approach.

ii. Coordination of in-house disciplines and subcontractor participation in design.

iii. The DQC Plan shall ensure that all services required by this contract are performed and provided in a manner that meets professional architectural and engineering standards.

iv. Design quality control procedures.

v. Design-to-cost control.

vi. Value engineering.

vii. The DQC Plan shall also include project-specific checklists for each discipline to be used during the design and quality control of each design submission.

viii. Design Team organization: The DQC Plan shall clearly demonstrate that the Contractor’s design team members and any significant consultants have appropriate experience by listing the years of experience of each design team member, including a list of related project experience.

h. Design Package Submissions: Each design submission shall demonstrate that all the project requirements are met prior to the full development of the Construction Documents (CD). The Contractor shall ensure that each of the design submissions adhere to the approved DQC Plan and shall include dual approval signatures of both the DOR and the QCM prior to submission to the Government for each review

i. Design Charette: Upon contractual award of the Design-Build project, the contractor is responsible for coordinating and planning for a design charrette. The contractor along with the government representative shall assemble all the stakeholders for a workshop. This meeting shall be an intensive, collaborative workshop where all design problems and issues shall be identified and discussed. The purpose of this charette is to share ideas, build consensus, and create a feasible plan. The goal is to produce a comprehensive and balanced design that reflects the input of all concerned stakeholders.

j. Design Concept Package Submission: The design concept package shall include.

15 | P a g e

i. Report outlining the project’s objectives, purpose and overall operation.

ii. Conceptual Layout: Sketches, 3D models and site plans.

iii. Site Analysis

iv. Initial Feasibility Analysis

v. Design Alternatives

k. 50% Design Package Submission: The intent is to provide a complete set of design documents. These documents shall address all design aspects that must be incorporated into this project in sufficient detail to show that all systems are defined and developed. These systems shall be compatible with and work effectively with the existing Site systems. All deliverables shall incorporate all design concept package design comments, project-related findings, such as testing, investigations and verifications necessary to complete the final design. The submission shall include:

i. Drawings, including title sheet and index, following the AIA Electronic Drawing

Standards.

ii. Basis of Design including all applicable design calculations.

iii. Specifications: At a minimum, an outline of proposed specification sections applicable to this project and location shall follow the CSI MasterFormat.

iv. Design and Construction Submittal Registers.

v. Copies of the discipline-specific DOR quality control checklists (provided in Contractor’s

DQC Plan).

vi. Drawings, including title sheet and index, following the RTC Electronic Drawing

Standards (attached).

vii. Specifications shall be project and location specific

viii. Commissioning Design Requirements shall be in accordance with the Commissioning section of this RFP.

ix. Finish (color) board for all finishes and FFE. Finish boards shall contain actual commercial-grade materials at least 12” x 12” in size.

x. Updated Design and Construction Submittal Registers, reflecting each specification’s submittal requirements.

i. Complete Site Civil package: The contractor shall submit a complete submission package to MDE to obtain the erosion and sediment control permit necessary when submitting the 50% design package to the Government. The contractor shall mobilize within two (2) calendar weeks once the MDE permit is approved

l. 100% Design Package Submission: The intent is to provide a complete set of design documents. These documents shall address all design aspects that must be incorporated into this project in sufficient detail to show that all systems are defined and developed. These systems shall be compatible with and work effectively with the existing Site systems. All deliverables shall incorporate any and all 50% design comments, project-related findings, such as testing, investigations and verifications necessary to complete the final design. The submission shall include:

i. All items listed in the 50% design submission.

ii. Copies of the discipline-specific DOR quality control checklists (provided in

Contractor’s DQC Plan).

iii. 50% comment incorporation back check, using comment spreadsheet from 50% OBR.

iv. Basis of Design including all applicable calculations.

v. Drawings, including title sheet and index, following the RTC Electronic Drawing

Standards (attached).

vi. Specifications shall be project and location specific

vii. Updated Design and Construction Submittal Registers, reflecting each specification’s submittal requirements.

viii. Updated finish (color) boards for all finishes and FFE, if necessary.

ix. Commissioning Design Requirements shall be in accordance with the Commissioning section of this RFP.

16 | P a g e

m. Issue for Construction (IFC) Requirements: All comments from 100% Design Package must be resolved in the IFC Submission. Any Contractor initiated changes to the drawings or specifications after the Government acknowledges receipt of the IFC Documents shall require Government review and acceptance. Changes to these drawings and/or specifications shall include the condition or change, any revised calculations, and any impacts to the cost, schedule, or performance.

n. Drawing Revisions for Field Changes: On a monthly basis, the Contractor shall submit updated drawings, BOD, and specifications revised due to field changes and contract modifications. These revisions shall also reflect engineering changes by OGC components.

Whole packages are not required, only drawing sheets and/or sections impacted. Field copies of drawings shall include all slip sheets with all updates.

21. Design Submissions Reviews

a. The Government shall have a total of 7 calendar days to review all design package submissions. The Contractor shall schedule an over the shoulder review to deliver the design package. The Contractor shall review the design with the Government, capture comments, and address all comments. Additional comments may be submitted by the end of the review period.

This is the start of the file's text. The full file is on GovTribe.