This document provides an amendment to a request for proposals for perimeter security assets and solutions for National Special Security Events and other protective events. The amendment responds to vendor questions by clarifying requirements for pricing of labor, equipment, installation and other costs to be included in ceiling prices for perimeter security assets. Ceiling prices will establish maximum amounts for future task order negotiations under multiple-award contracts to small businesses in NAICS code 561990 with a period of performance of five years and ceiling amounts of $76 million for Tier 1 contracts and $5 million for Tier 2 contracts from the Department of Homeland Security's US Secret Service. Subcontracting and teaming arrangements are permitted. The deadline to acknowledge receipt of the amendment was February 18, 2020.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Perimeter Assets Estimated Quantities.xlsx | XLSX spreadsheet | |
| Other Protective Event Ceiling Price Worksheet.xlsx | XLSX spreadsheet | |
| NSSE Ceiling Price Worksheet.xlsx | XLSX spreadsheet | |
| RFP 70US0920R70090003 PUB.pdf | ||
| Previous Quantities for an NSSE.xlsx | XLSX spreadsheet | |
| Place of Performance Worksheet.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
70US0920R70090003
x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT
THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
WASHINGTON DC 20223
PRO-PROCUREMENT DIV
BLDG T-5
245 MURRAY LANE, SW
COMMUNICATIONS CENTER (PRO)
PRO-PROCUREMENT DIV
WASHINGTON DC 20223
PRO-PROCUREMENT DIV
BLDG T-5
245 MURRAY LANE SW
COMMUNICATIONS CENTER (PRO)
PRO-PROCUREMENT DIV
02/18/20200001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
02/06/2020
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The purpose of Amendment 0001 is to provide responses to questions.
Offerors shall complete Block 15 of this Standard Form 30 and submit it with their proposals.
All terms and conditions remain unchanged.
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Michael B. Velez
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
NSN 7540-01-152-8070
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
Request for Proposals 70US0920R70090003 Perimeter Security Assets Questions and Responses
1. Is it the intent of the USSS to award multiple contracts to vendors for each tier type and then issue task order bids as each event approaches?
Response: Yes. Task orders will be issued subject to ordering procedures.
2. Should suppliers and installers to the “Main Vendor” show labor pricing on the pricing submittal sheets? Typically, second tier vendors provide pricing to supply and install assets as a turnkey price as opposed to perpetually broken down prices due to the various items that go into completing the projects. IE, material and labor are not the only items that would go into furnish and install.
Response: Offerors shall submit pricing for perimeter security assets that includes the labor associated with the installation and tear down of those assets.
Fully burdened labor rates shall be submitted separately for consultative services.
Subcontractors: The request for proposals is designed for proposals from prime contractors (to the Government only). Prospective subcontractors should submit proposals to prospective prime contractors.
3. When necessary, or when improved/better assets are available, will we be able to substitute assets?
Response: At the issuance of a task order, contractors will not be permitted to substitute assets unless approved by the Government. If the assets are not already included in the contract, a contract modification will be required.
4. Can we “co-bid” with companies who have previously secured NSSE contracts?
Response: To be eligible for an award, the offeror needs to be a small business under North American Industry Classification System (NAICS) code 561990 - All Other Support Services.
The proposal submittal strategy is up to the offerors.
5. Can we use personnel that pass E-Verify work on the project?
Response: All work must be performed by U.S. Citizens.
6. Should we price assets as individual units or based on the estimated scale for the events?
Response: Perimeter security assets shall be priced for one (1) unit of issue for one (1) day. The price shall be the ceiling unit price realizing that task order prices may vary depending on the scale and location of an event.
7. I am assuming after reading the attached link - that this bid process is taking the place of how you had been doing it for the last three years?
Response: That is correct.
8. I am assuming that you need me to complete all of the attachments to the best of my ability and send back to you asap?
Response: Offerors shall follow the instructions in the request for proposals and ensure the proposals are received by the date and time stipulated in the request for proposals.
9. When you request a "Fully Loaded/Burdened Rate" for labor, are we to assume that this includes Rate Per Hour and Overhead only? Per Diem should not be included in the "Fully Loaded Rate", correct (as it will change from year to year)?
Response: Per Diem and travel costs shall not be included in the fully loaded/burdened rate and will be reimbursed per the Federal Travel Regulations (FTR).
All labor costs shall be included in the fully loaded/burdened rate with the exception of travel and per diem.
10. When you request a "Fully Loaded Rate" for labor, would you like to see the Double Time ONLY rates or would you like to see Straight Time, Overtime, Double Time and Holiday rates for each position?
Response: Offerors shall submit for each position one (1) fully burdened firm fixed-price labor rate that is a ceiling labor rate.
The fully burdened labor rates associated with all labor categories shall be the ceiling prices for all task order negotiations; no proposed task order labor hour pricing shall exceed the Ceiling Price Worksheet (CPW) fully burdened rates, but contract awardees may propose lower fully burdened rates during task order solicitation.
11. The RFP States "Perimeter security asset unit pricing shall be all inclusive with the exception of delivery/transportation:"
a) Do you want us to include the price of heavy equipment that will be required for the installation/operation of the asset? (e.g. to load/unload a 20' portable vehicle barrier we require a specialized forklift - which isn't listed under "Heavy Machinery/Major Items" on the Ceiling Price Worksheet).
Response: Offerors shall include all costs associated with the installation and operation of the asset to include heavy machinery.
The proposed prices for the perimeter security assets shall be firm fixed-price ceiling prices for all task order negotiations; no proposed future task order pricing shall exceed the CPW prices, but contract awardees may propose lower prices during task order solicitation.
b) Does "all inclusive with the exception of delivery/transportation" mean that you want us to include the cost of labor to install and strike the asset?
For Example: For Anti-Scale Fencing, to install 1 piece of anti-scale fencing in a union town, we would require several departments and personnel.
Response: Offerors shall include all costs associated with the installation and operation of the asset to include labor to install and strike the assets.
The proposed prices for the perimeter security assets shall be firm fixed-price ceiling prices for all task order negotiations; no proposed future task order pricing shall exceed the CPW prices, but contract awardees may propose lower prices during task order solicitation.
c) Please confirm that we are not expected to include any travel/lodging/per diem costs for crew required to install/operate/strike the asset.
Response: Per Diem and travel costs shall not be included in the ceiling price and will be reimbursed per the Federal Travel Regulations (FTR).
12. There are specific pieces of equipment (e.g. heavy-duty forklift for portable vehicle barriers) that are not listed under the Heavy Machinery/Major Items category on the CPW. If these items are not to be included in the unit price (Question 3A above), how would you like us to show the price for these items, if at all?
Response: Offerors shall include these costs in the ceiling prices.
13. This RFP specifies only one of the two primary types of Anti-Scale fencing used by USSS. This does not address the Anti-Scale/Anti-Pass-Through fencing (8' tall x 8' wide Steel fence with diamond mesh) that has been used previously by USSS. Should we include pricing for this type of anti-scale as well, or is this what you mean by "Steel Fence" in the CPW?
Response: The steel fence included in the CPW refers to the Anti-Scale/Anti-Pass-Through fencing.
14. Is the ceiling amount for each Tier 1 or Tier 2 contract as listed in the RFP ($76,000,000 and $5,000,000 respectively) the ceiling amount per vendor contract or for ALL Tier 1/Tier 2 events that fall within the contracted 5-year period?
Response: The ceiling amount is the per vendor contract maximum award amount over the full duration of the contract, for each Tier.