QuestionsAnswers and Clarifications.pdf
PDF 428 KB Posted
- Attached to
- THOR Request for Information (RFI) Federal contract opportunity
- Solicitation number
- 70RWMD22RFI00000014
About this file
This document provides questions, answers and clarifications related to a Request for Information from the Department of Homeland Security Countering Weapons of Mass Destruction Office. The RFI seeks an updated rough order of magnitude cost estimate from industry for developing 2-3 Thallium Bromide-based Radioisotope Identification Device prototypes over approximately 12 months. Respondents are asked to complete an online survey by 5 October 2022 to provide their cost estimates and input on proposed contract structure. The RFI also announces an upcoming THOR Industry Day in early 2023 to present status updates on Thallium Bromide detector research and demonstration and gather feedback on the THOR strategy and technical requirements prior to releasing a formal prototype integration solicitation later that year.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Industry Day February 7 through 9 Questions and Answers.pdf | ||
| TlBr Industry Day 2023 Combined Presentations.pdf | ||
| Incoming Foreign National Visit_CWMD (1).doc | DOC document | |
| Industry Event Registration Form (R2).docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
70RWMD22RFI00000014 THOR RFI Questions and Answers
(Q&As) and Clarifications
Q&As
Question #1: “Could you [provide] the latest Foreign National request form for the upcoming THOR industry engagement?”
Answer #1: The Foreign National request form has been provided under the Attachments/Links form on the SAM.gov posting for 70RWMD22RFI00000014.
Question #2: “Can you confirm the location of the Industry Day event?”
Answer #2: Under the Introduction Section of the subject RFI, the location is stated to be “on-line using Microsoft TEAMS.” No travel is required for attending the Industry Day.
Question #3: “Is the Industry Day event 3 full days?”
Answer #3: The Industry Day event is 3 days. The RFI states that February 7, 2023 will be an all-day event. February 8th and 9th will be potential one-on-one sessions that will last approximately 15 minutes.
CLARIFICATIONS
RFI Clarification #1: To sign up for the one-on-one engagements held February 8th and 9th, 2023, email CWMDIndustryEvents@hq.dhs.gov for further instructions
RFI Clarification #2: Sign-up requests for the one-on-one engagements held February 8th and 9th, 2023, should be received by 12 pm (Eastern Time) on February 3, 2023. CWMD will try to accommodate sign-up requests received prior to 12 pm (Eastern Time) on February 3, 2023. Sign-up requests received after 12 pm (Eastern Time) on February 3, 2023, run the risk of not be granted.