This is a Women-Owned Small Business (WOSB) Solicitation/Contract/Order for Commercial Products and Services issued by the Department of Homeland Security, Federal Law Enforcement Training Centers (FLETC) at Glynco, Georgia. The contract number is 70LGLY26QGLB00058, with an offer due date of September 19, 2026 at 1600 ET. The contracting officer is Maritza L. Jennings, telephone 912-267-3537.
The contract requires generator inspection, maintenance, and certification services for 15 generators located across various FLETC buildings, with services performed by trained, qualified technicians in accordance with manufacturer recommendations. The base period runs from October 1, 2026 through September 30, 2027, with four option years extending through September 30, 2031. Services include three minor inspections and one major inspection per generator annually, plus one annual load bank test per NFPA 110 standards. The contract includes up to twelve troubleshooting service calls and eight minor repairs (not to exceed $2,000 each) annually on a firm-fixed price basis. Generators are primarily Generac natural gas units ranging from 35-625 KW, one Onan unit, and one propane Generac unit. Delivery is FOB Destination. The contractor must obtain FLETC identification badges for all personnel, comply with facility safety directives and OSHA requirements, maintain comprehensive general liability insurance ($200,000 per person/$500,000 per accident), automobile insurance, and workers' compensation insurance. All inspection reports must be submitted within two business days of service completion, and annual certifications within five business days of load testing. The contract is set aside for women-owned small businesses and requires contractor compliance with combating trafficking in persons requirements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment 2 70LGLY26QGLB00058 0002.pdf | ||
| Amendment 1 70LGLY26QGLB00058 0001.pdf | ||
| Wage Determination No 2015_4477 Rev 36.txt | TXT text file |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WOMEN-OWNED SMALL
BUSINESS (WOSB)
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES
PAGE 1 OF
2. CONTRACT NUMBER 3.AWARD/EFFECTIVE
DATE
4. ORDER NUMBER 5. SOLICITATION NUMBER 6. SOLICITATION ISSUE
DATE
7. FOR SOLICITATION
INFORMATION CALL:
a. NAME b. TELEPHONE NUMBER (No collect calls)
8. OFFER DUE DATE/
LOCAL TIME
9. ISSUED BY
13b. RATING
14. METHOD OF SOLICITATION
CODE
15. DELIVER TO 16. ADMINISTERED BY CODE
18a. PAYMENT WILL BE MADE BY CODE17a. CONTRACTOR/
OFFEROR
CODE
FACILITY
CODE
CODE
TELEPHONE NUMBER
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN
OFFER
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK
BELOW IS CHECKED
REQUEST
FOR QUOTE
(RFQ)
INVITATION
FOR BID
(IFB)
REQUEST
FOR
PROPOSAL
(RFP)
SEE ADDENDUM
19.
ITEM NO.
20.
SCHEDULE OF SUPPLIES/SERVICES
21.
QUANTITY
22.
UNIT
23.
UNIT PRICE
24.
AMOUNT
(Use Reverse and/or Attach Additional Sheets as Necessary)
25. ACCOUNTING AND APPROPRIATION DATA 26. TOTAL AWARD AMOUNT (For Government Use Only)
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN 29. AWARD OF CONTRACT: REFERENCE
. YOUR OFFER ON SOLICITATION
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:
30a. SIGNATURE OF OFFEROR/CONTRACTOR
30b. NAME AND TITLE OF SIGNER (Type or print) 30c. DATE SIGNED
31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)
31b. NAME OF CONTRACTING OFFICER (Type or print) 31c. DATE SIGNED
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
STANDARD FORM 1449 (REV. 11/2021)
Prescribed by GSA - FAR (48 CFR) 53.212
10. THIS ACQUISITION IS UNRESTRICTED OR
NORTH AMERICAN
INDUSTRY CLASSIFICATION
STANDARD (NAICS):
SIZE STANDARD:
13a. THIS CONTRACT IS A
RATED ORDER UNDER
THE DEFENSE PRIORITIES
AND ALLOCATIONS
SYSTEM - DPAS (15 CFR 700)
SET ASIDE: % FOR:
11. DELIVERY FOR FREE ON
BOARD (FOB) DESTINATION
UNLESS BLOCK IS MARKED
SEE SCHEDULE
12. DISCOUNT TERMS
ARE ARE NOT ATTACHED
ARE ARE NOT ATTACHED
27a. SOLICITATION INCORPORATES BY REFERENCE (FEDERAL ACQUISITION REGULATION) FAR 52.212-1, 52.212-4.
FAR 52.212-3 AND 52.212-5 ARE ATTACHED.
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED.
8(A)
ECONOMICALLY
DISADVANTAGED
WOMEN-OWNED SMALL
BUSINESS (EDWOSB)
SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
(SDVOSB)
HUBZONE SMALL
BUSINESS
SMALL BUSINESS
NOTE: OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30.
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH
AND DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND
ON ANY ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS
SPECIFIED
DATED.
OFFER
ADDENDA
ADDENDA
70LGLY26QGLB00058
DEPARTMENT OF HOMELAND SECURITY
FEDERAL LAW ENFORCEMENT TRNG CTR
1131 CHAPEL CROSSING RD
ATTN: BLDG:
GLYNCO GA 31524
DEPARTMENT OF HOMELAND SECURITY
FEDERAL LAW ENFORCEMENT TRAINING CENTERS
1131 CHAPEL CROSSING RD
Attn: Maritza Jennings
GLYNCO GA 31524
DEPARTMENT OF HOMELAND SECURITY
FEDERAL LAW ENFORCEMENT TRAINING CENTERS
1131 CHAPEL CROSSING RD
Attn: Maritza Jennings
GLYNCO GA 31524
09/19/2026 1600 ET
1. REQUISITION NUMBER
Maritza Jennings 912-267-3537
70LGLY
70LGLY
Maritza L. Jennings
811310
$8.00
09/15/2026
FLETC GL
Offerors shall provide a statement of compliance with FAR 52.222-50, Combating
Trafficking in Persons, requirements and confirm subcontractors will accomplish a statement of compliance upon award.
Continued...
STOCK RECORD (S/R)
STANDARD FORM 1449 (REV. 11/2021) BACK
19.
ITEM NO.
20.
SCHEDULE OF SUPPLIES/SERVICES
21.
QUANTITY
22.
UNIT
23.
UNIT PRICE
24.
AMOUNT
32a. QUANTITY IN COLUMN 21 HAS BEEN
RECEIVED INSPECTED AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED:
41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT
32b. SIGNATURE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32c. DATE
41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE
42a. RECEIVED BY (Print)
42b. RECEIVED AT (Location)
42c. DATE RECEIVED (MM/DD/YYYY) 42d. TOTAL CONTAINERS
40. PAID BY
32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f. TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE
32g. EMAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE
33. SHIP NUMBER 34. VOUCHER NUMBER 35. AMOUNT VERIFIED
CORRECT FOR
PARTIAL FINAL
37. CHECK NUMBER
38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER
36. PAYMENT
COMPLETE PARTIAL FINAL
ACCEPTED,
Period of Performance: 10/01/2026 to
09/30/2031
0001 1 YRBG0001 Generator
Period of Performance: 10/01/2026 to
09/30/2027
0002 1 YRBG0003 Generator PM
Period of Performance: 10/01/2026 to
09/30/2027
0003 1 YRBG0075 Generator
Period of Performance: 10/01/2026 to
09/30/2027
0004 1 YRBG0091 Generator
Period of Performance: 10/01/2026 to
09/30/2027
0005 1 YRBG0092 Generator
Period of Performance: 10/01/2026 to
09/30/2027
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
NSN 7540-01-152-8067
70LGLY26QGLB00058
0006 1 YRBG0093 Generator
Period of Performance: 10/01/2026 to
09/30/2027
0007 1 YRBG0146 Generator
Period of Performance: 10/01/2026 to
09/30/2027
0008 1 YRBG0252 Generator
Period of Performance: 10/01/2026 to
09/30/2027
0009 1 YRBG402E Generator
Period of Performance: 10/01/2026 to
09/30/2027
0010 1 YRBG0147 Generator
Period of Performance: 10/01/2026 to
09/30/2027
0011 1 YRBG0198 Generator
Period of Performance: 10/01/2026 to
09/30/2027
0012 1 YRBG0201 Generator
Period of Performance: 10/01/2026 to
09/30/2027
0013 1 YRBG0099 Generator
Period of Performance: 10/01/2026 to
09/30/2027
0014 1 YRBG101 Generator
Period of Performance: 10/01/2026 to
09/30/2027
0015 1 YRGate 10 Generator
Period of Performance: 10/01/2026 to
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
09/30/2027
0016 1 YRGenerator Repairs
Troubleshooting with minor repairs in accordance with PWS Section 2.1.5 SERVICE CALLS
FOR REPAIR
Twelve (12) Troubleshooting calls and up to eight (8) Minor Repairs (not to exceed $2,000 each), Firm-Fixed Price (FFP)
Contractor shall submit price proposal for supplies, parts, and equipment to the
Government for approval prior to contract performance on service repairs. Submit invoice after completion of each Service Contract Work
Requests (SCWR) for emergency repairs.
CLIN will be funded at lump sum drawdown
Not-To-Exceed (NTE) Amount. The Government does not guarantee all funding will be used. The contractor will be paid for only work performed.
Period of Performance: 10/01/2026 to
09/30/2027
1001 1 YRBG0001 Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2027
FOB: Destination
Period of Performance: 10/01/2027 to
09/30/2028
1002 1 YRBG0003 Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2027
FOB: Destination
Period of Performance: 10/01/2027 to
09/30/2028
1003 1 YRBG0075 Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2027
FOB: Destination
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
Period of Performance: 10/01/2027 to
09/30/2028
1004 1 YRBG0091 Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2027
FOB: Destination
Period of Performance: 10/01/2027 to
09/30/2028
1005 1 YRBG0092 Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2027
FOB: Destination
Period of Performance: 10/01/2027 to
09/30/2028
1006 1 YRBG0093 Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2027
FOB: Destination
Period of Performance: 10/01/2027 to
09/30/2028
1007 1 YRBG0146 Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2027
FOB: Destination
Period of Performance: 10/01/2027 to
09/30/2028
1008 1 YRBG0252 Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2027
FOB: Destination
Period of Performance: 10/01/2027 to
09/30/2028
1009 1 YRBG402E Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2027
FOB: Destination
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
1010 1 YRBG0147 Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2027
FOB: Destination
Period of Performance: 10/01/2027 to
09/30/2028
1011 1 YRBG0198 Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2027
FOB: Destination
Period of Performance: 10/01/2027 to
09/30/2028
1012 1 YRBG0201 Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2027
FOB: Destination
Period of Performance: 10/01/2027 to
09/30/2028
1013 1 YRBG0099 Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2027
FOB: Destination
Period of Performance: 10/01/2027 to
09/30/2028
1014 1 YRBG0101 Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2027
FOB: Destination
Period of Performance: 10/01/2027 to
09/30/2028
1015 1 YRGate 10 Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2027
FOB: Destination
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
1016 1 YRGenerator Repairs
Troubleshooting with minor repairs in accordance with PWS Section 2.1.5 SERVICE CALLS
FOR REPAIR
Twelve (12) Troubleshooting calls and up to eight (8) Minor Repairs (not to exceed $2,000 each), Firm-Fixed Price (FFP)
Contractor shall submit price proposal for supplies, parts, and equipment to the
Government for approval prior to contract performance on service repairs. Submit invoice after completion of each Service Contract Work
Requests (SCWR) for emergency repairs.
CLIN will be funded at lump sum drawdown
Not-To-Exceed (NTE) Amount. The Government does not guarantee all funding will be used. The contractor will be paid for only work performed.
(Option Line Item)
Anticipated Option Exercise Date 09/30/2027
Period of Performance: 10/01/2027 to
09/30/2028
2001 1 YRBG0001 Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2028
FOB: Destination
Period of Performance: 10/01/2028 to
09/30/2029
2002 1 YRBG0003 Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2028
FOB: Destination
Period of Performance: 10/01/2028 to
09/30/2029
2003 1 YRBG0075 Generator
(Option Line Item)
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
Anticipated Option Exercise Date 09/30/2028
FOB: Destination
Period of Performance: 10/01/2028 to
09/30/2029
2004 1 YRBG0091 Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2028
FOB: Destination
Period of Performance: 10/01/2028 to
09/30/2029
2005 1 YRBG0092 Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2028
FOB: Destination
Period of Performance: 10/01/2028 to
09/30/2029
2006 1 YRBG0093 Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2028
FOB: Destination
Period of Performance: 10/01/2028 to
09/30/2029
2007 1 YRBG0146 Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2028
FOB: Destination
Period of Performance: 10/01/2028 to
09/30/2029
2008 1 YRBG0252 Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2028
FOB: Destination
Period of Performance: 10/01/2028 to
09/30/2029
2009 1 YRBG402E Generator
(Option Line Item)
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
Period of Performance: 10/01/2028 to
09/30/2029
2010 1 YRBG0147 Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2028
FOB: Destination
Period of Performance: 10/01/2028 to
09/30/2029
2011 1 YRBG0198 Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2028
FOB: Destination
Period of Performance: 10/01/2028 to
09/30/2029
2012 1 YRBG0201 Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2028
FOB: Destination
Period of Performance: 10/01/2028 to
09/30/2029
2013 1 YRBG0099 Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2028
FOB: Destination
Period of Performance: 10/01/2028 to
09/30/2029
2014 1 YRBG0101 Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2028
FOB: Destination
Period of Performance: 10/01/2028 to
09/30/2029
2015 1 YRGate 10 Generator
(Option Line Item)
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
Period of Performance: 10/01/2028 to
09/30/2029
2016 1 YR
Generator Repairs
Troubleshooting with minor repairs in accordance with PWS Section 2.1.5 SERVICE CALLS
FOR REPAIR
Twelve (12) Troubleshooting calls and up to eight (8) Minor Repairs (not to exceed $2,000 each), Firm-Fixed Price (FFP)
Contractor shall submit price proposal for supplies, parts, and equipment to the
Government for approval prior to contract performance on service repairs. Submit invoice after completion of each Service Contract Work
Requests (SCWR) for emergency repairs.
CLIN will be funded at lump sum drawdown
Not-To-Exceed (NTE) Amount. The Government does not guarantee all funding will be used. The contractor will be paid for only work performed.
(Option Line Item)
Anticipated Option Exercise Date 09/30/2028
Period of Performance: 10/01/2028 to
09/30/2029
3001 1 YRBG0001 Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2029
FOB: Destination
Period of Performance: 10/01/2029 to
09/30/2030
3002 1 YRBG0003 Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2029
FOB: Destination
Period of Performance: 10/01/2029 to
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
09/30/2030
3003 1 YRBG0075 Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2029
FOB: Destination
Period of Performance: 10/01/2029 to
09/30/2030
3004 1 YRBG0091 Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2029
FOB: Destination
Period of Performance: 10/01/2029 to
09/30/2030
3005 1 YRBG0092 Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2029
FOB: Destination
Period of Performance: 10/01/2029 to
09/30/2030
3006 1 YRBG0093 Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2029
FOB: Destination
Period of Performance: 10/01/2029 to
09/30/2030
3007 1 YRBG0146 Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2029
FOB: Destination
Period of Performance: 10/01/2029 to
09/30/2030
3008 1 YRBG0252 Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2029
FOB: Destination
Period of Performance: 10/01/2029 to
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
3009 1 YRBG402E Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2029
FOB: Destination
Period of Performance: 10/01/2029 to
09/30/2030
3010 1 YRBG0147 Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2029
FOB: Destination
Period of Performance: 10/01/2029 to
09/30/2030
3011 1 YRBG0198 Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2029
FOB: Destination
Period of Performance: 10/01/2029 to
09/30/2030
3012 1 YRBG0201 Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2029
FOB: Destination
Period of Performance: 10/01/2029 to
09/30/2030
3013 1 YRBG0099 Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2029
FOB: Destination
Period of Performance: 10/01/2029 to
09/30/2030
3014 1 YRBG0101 Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2029
FOB: Destination
Period of Performance: 10/01/2029 to
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
3015 1 YRGate 10 Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2029
FOB: Destination
Period of Performance: 10/01/2029 to
09/30/2030
3016 1 YRGenerator Repairs
Troubleshooting with minor repairs in accordance with PWS Section 2.1.5 SERVICE CALLS
FOR REPAIR
Twelve (12) Troubleshooting calls and up to eight (8) Minor Repairs (not to exceed $2,000 each), Firm-Fixed Price (FFP)
Contractor shall submit price proposal for supplies, parts, and equipment to the
Government for approval prior to contract performance on service repairs. Submit invoice after completion of each Service Contract Work
Requests (SCWR) for emergency repairs.
CLIN will be funded at lump sum drawdown
Not-To-Exceed (NTE) Amount. The Government does not guarantee all funding will be used. The contractor will be paid for only work performed.
(Option Line Item)
Anticipated Option Exercise Date 09/30/2029
Period of Performance: 10/01/2029 to
09/30/2030
4001 1 YRBG0001 Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2030
FOB: Destination
Period of Performance: 10/01/2030 to
09/30/2031
4002 1 YRBG0003 Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2030
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
Period of Performance: 10/01/2030 to
09/30/2031
4003 1 YRBG0075 Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2030
FOB: Destination
Period of Performance: 10/01/2030 to
09/30/2031
4004 1 YRBG0091 Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2030
FOB: Destination
Period of Performance: 10/01/2030 to
09/30/2031
4005 1 YRBG0092 Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2030
FOB: Destination
Period of Performance: 10/01/2030 to
09/30/2031
4006 1 YRBG0093 Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2030
FOB: Destination
Period of Performance: 10/01/2030 to
09/30/2031
4007 1 YRBG0146 Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2030
FOB: Destination
Period of Performance: 10/01/2030 to
09/30/2031
4008 1 YRBG0252 Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2030
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
09/30/2031
4009 1 YRBG402E Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2030
FOB: Destination
Period of Performance: 10/01/2030 to
09/30/2031
4010 1 YRBG0147 Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2030
FOB: Destination
Period of Performance: 10/01/2030 to
09/30/2031
4011 1 YRBG0198 Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2030
FOB: Destination
Period of Performance: 10/01/2030 to
09/30/2031
4012 1 YRBG0201 Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2030
FOB: Destination
Period of Performance: 10/01/2030 to
09/30/2031
4013 1 YRBG0099 Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2030
FOB: Destination
Period of Performance: 10/01/2030 to
09/30/2031
4014 1 YRBG0101 Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2030
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
09/30/2031
4015 1 YRGate 10 Generator
(Option Line Item)
Anticipated Option Exercise Date 09/30/2030
FOB: Destination
Period of Performance: 10/01/2030 to
09/30/2031
4016 1 YRGenerator Repairs
Troubleshooting with minor repairs in accordance with PWS Section 2.1.5 SERVICE CALLS
FOR REPAIR
Twelve (12) Troubleshooting calls and up to eight (8) Minor Repairs (not to exceed $2,000 each), Firm-Fixed Price (FFP)
Contractor shall submit price proposal for supplies, parts, and equipment to the
Government for approval prior to contract performance on service repairs. Submit invoice after completion of each Service Contract Work
Requests (SCWR) for emergency repairs.
CLIN will be funded at lump sum drawdown
Not-To-Exceed (NTE) Amount. The Government does not guarantee all funding will be used. The contractor will be paid for only work performed.
(Option Line Item)
Anticipated Option Exercise Date 09/30/2030
Period of Performance: 10/01/2030 to
09/30/2031
Funds are not presently available. The
Government’s obligation under this contract is contingent upon the availability of appropriated funds from which payment for contract purposes can be made. No legal liability on the part of the Government for any payment may arise until funds are made available to the Contracting Officer for this
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C) contract and until the Contractor receives notice of such availability, to be confirmed in writing by the
Contracting Officer in accordance with FAR
Clause 52.232-18, Subject to Availability of
Funding (SAF).
SECTION B PRICE SCHEDULE
1. PERIOD OF PERFORMANCE (POP). Service dates are as follows:
Base Period:
Option Year 1:
Option Year 2:
Option Year 3:
Option Year 4:
October 1, 2026 thru September 30, 2027 October 1, 2027 thru September 30, 2028 October 1, 2028 thru September 30, 2029 October 1, 2029 thru September 30, 2030 October 1, 2030 thru September 30, 2031
CLIN Description Minor Major Load Test
Repairs Totals
Base Year
0001 Building 1 Generator 0002 Building 3 Generator 0003 Building 75 Generator 0004 Building 91 Generator 0005 Building 92 Generator 0006 Building 93 Generator 0007 Building 146 Generator 0008 Building 252 Generator 0009 Building 402E Generator 0010 Building 147 Generator 0011 Building 198 Generator 0012 Building 201 Generator 0013 Building 99 Generator 0014 Building 101 Generator 0015 Gate 10 Generator 0016 Repairs Base Year Totals
Option 1 1001 Building 1 Generator 1002 Building 3 Generator 1003 Building 75 Generator 1004 Building 91 Generator 1005 Building 92 Generator 1006 Building 93 Generator 1007 Building 146 Generator 1008 Building 252 Generator 1009 Building 402E Generator 1010 Building 147 Generator 1011 Building 198 Generator 1012 Building 201 Generator
CLIN Description Minor Major Load Test
Repairs Totals
1013 Building 99 Generator 1014 Building 101 Generator 1015 Gate10 Generator 1016 Repairs Option Year 1 Totals
Option 2 2001 Building 1 Generator 2002 Building 3 Generator 2003 Building 75 Generator 2004 Building 91 Generator 2005 Building 92 Generator 2006 Building 93 Generator 2007 Building 146 Generator 2008 Building 252 Generator 2009 Building 402E Generator 2010 Building 147 Generator 2011 Building 198 Generator 2012 Building 201 Generator 2013 Building 99 Generator 2014 Building 101 Generator 2015 Gate10 Generator 2016 Repairs Option Year 2 Totals
Option 3 3001 Building 1 Generator 3002 Building 3 Generator 3003 Building 75 Generator 3004 Building 91 Generator 3005 Building 92 Generator 3006 Building 93 Generator 3007 Building 146 Generator 3008 Building 252 Generator 3009 Building 402E Generator 3010 Building 147 Generator 3011 Building 198 Generator 3012 Building 201 Generator 3013 Building 99 Generator 3014 Building 101 Generator 3015 Gate10 Generator 3016 Repairs Option Year 3
CLIN Description Minor Major Load Test
Repairs Totals
Totals Option 4 4001 Building 1 Generator 4002 Building 3 Generator 4003 Building 75 Generator 4004 Building 91 Generator 4005 Building 92 Generator 4006 Building 93 Generator 4007 Building 146 Generator 4008 Building 252 Generator 4009 Building 402E Generator 4010 Building 147 Generator 4011 Building 198 Generator 4012 Building 201 Generator 4013 Building 99 Generator 4014 Building 101 Generator 4015 BGate 10 Generator 4016 Repairs Option Year 4 Totals
Total for Base and All Options
Performance Work Statement Generator Service and Certification
PART 1 – GENERAL
1.1 Introduction. This Performance Work Statement (PWS) is for the Department of Homeland Security (DHS), Federal Law Enforcement Training Centers (FLETC). The FLETC Glynco campus is located approximately five minutes north of Brunswick, Georgia in Glynn County and is equal distance between Savannah, Georgia, and Jacksonville, Florida. The FLETC (Center) is situated on approximately 2,000 acres in southeast Georgia with modern conventional facilities such as classrooms, dormitories, administrative and logistical support structures. Additionally, Glynco has 18 firearm ranges, including a state-of-the-art indoor range complex with 146 separate firing points;
and eight highly versatile semi-enclosed ranges with 200 additional firing points.
Other training assets include a sprawling complex of driver training ranges, a physical techniques facility, explosives range, fully functional mock port of entry, and numerous other structures which support the entire training effort.
1.2 DESCRIPTION OF SERVICES/SCOPE OF WORK. The Contractor shall Inspect and Service Portable and Fixed standby Generators. The work described shall be performed by trained, qualified technicians in accordance with the manufacturer's recommendations. The maintenance shall consist of three (3) minor and one (1) major inspection per generator per year; and one load bank test annually. Contractor will check in with the COR or Facility Maintenance Supervisor each day before starting work. All items listed below will be completed every quarter unless specified otherwise.1.3
1.3 Period of Performance:
Base Period: October 1, 2026 – September 30, 2027 Option 1: October 1, 2027 – September 30, 2028
Option 2: October 1, 2028 – September 30, 2029
Option 3: October 1, 2029 – September 30, 2030
Option 4: October 1, 2030 – September 30, 2031
1.4 Normal Working Hours. The normal business working hours are available between the hours of 7:00 a.m. and 5:00 p.m., seven days a week.
PART 2
2.1 WORK COVERED BY CONTRACT DOCUMENTS
For Deisel and Propane Generators
2.1.1 Engine for Deisel and Propane Generators
2.1.1.1 Lubrication System
• Perform complete oil change (Annually).
• Change filters (Annually).
• Inspect for evidence of dilution or contamination.
If there is a problem, then draw oil sample for analysis.
• Inspect for leaks.
• Check all engine controls for proper adjustments.
2.1.1.2 Fuel System
• Change engine fuel filters (Annually).
• Check fuel supply for quantity, contamination, quality.
• Inspect fuel supply manifolds for leaks, condition, and security.
• Check operation of transfer pumps and day tanks.
• Inspect engine fuel lines, pump, and filters for leaks, condition, and security.
• Inspect and lubricate governor actuator to rack and ball joints.
• Drain condensation (if possible).
2.1.1.3 Air System
• Change air filter (Annually).
• Inspect louvers and duct work for condition and proper operation.
• Inspect air filters for condition and security;
tighten clamps and brackets as needed.
• Inspect turbo outlet hoses and pipes for condition and security: tighten clamps and brackets as needed.
• Inspect and lubricate blower by-pass actuators.
• Inspect and lubricate air box damper operating mechanism.
• Service crankcase breathers and air box drains as required by OEM maintenance requirements.
2.1.1.4 Cooling System
• Chemical test corrosion protection (Annually).
• Check coolant level.
• Check and record freeze protection.
• Inspect fan shrouds, guards, and brackets for condition and security.
• Inspect radiator core for cleanliness, condition, and security.
• Inspect fan drive belt for condition, security, and proper tension.
• Inspect idler and fan drive bearings. Check condition and security of mounts, brackets, and adjusters, tightening as needed.
• Inspect coolant hoses and pipes for condition and security, tightening clamps and brackets as needed.
• If problem is found with coolant, then take coolant sample for laboratory testing.
2.1.1.5 Exhaust System
• Inspect exhaust pipe and flexes when accessible, tightening clamps and flange bolts as required.
• Inspect muffler supports and operate drains.
• Inspect turbocharger clamps and brackets, tightening as required.
2.1.1.6 Engine Electrical System
• Inspect starter cables, wire, and connectors for condition and security.
• Check and record starting battery float voltage and electrolyte level.
• Check charger for proper operation and output.
• Load test starting batteries to 450 amps/cell for 15 seconds and record voltage.
• Inspect electrical control and sensor wire termination, tightening as required.
• Check operation of jacket water heater, control thermostats, and oil pressure disconnect switch.
• Inspect all engine protective devices including oil pressure, coolant temperature, over crank, over speed shutdowns, and all other applicable devices.
• Inspect ignition system for signs of deterioration.
2.1.2 Generator
2.1.2.1 Mechanical
• Inspect mounting bolts.
• Inspect drive flex fastening bolts.
• Inspect fan guard for condition and security.
• Inspect air inlet screen for cleanliness, condition, and security.
• Inspect mechanical connections for tightness, condition, and security.
2.1.2.2 Electrical
• Check and record residual, no load, and full load voltages (voltages under load can only be checked with building load or load back service below).
• Inspect cable wire termination at generator for condition and security.
• Inspect end bell enclosure for cleanliness and device interference with rotating assembly.
• Inspect and test generator protective devices (circuit breaker, safeguard breaker).
2.1.2.3 Controls and Transfer Switch
• Transfer Switch will be cycled to take the building load for 15 minutes semiannually.
• Check operation of auto start and remote controls.
• Check operation of generator, associated indicators, lights, and alarms.
• Check and adjust system frequency and voltage.
• Inspect relays and contacts for excess wear and cleanliness.
• Check soundness of linkages and load cables.
• Inspect condition of control panel wiring.
• Review switch for overall cleanliness and condition.
2.1.3 Maintenance for all Generac Natural Gas Generators
Quarterly Inspections
• Inspect for oil, coolant, fuel and exhaust leaks
• Inspect oil and coolant levels
• Inspect battery for corrosion and ensure terminations are clean and tight.
• Verify after Preventative Maintenance is performed generator is in Auto and check for any warning lights.
Semi-Annual Maintenance
• Perform a full battery check, including voltage and charging rate.
• Examine AC wiring and DC electrical systems
• Check pliability, wear, or looseness in belts: inspect hoses for leakage
• Clean air intake screen and cooling inlets to prevent debris buildup.
Annual Maintenance
• Replace engine oil and oil filter (like in kind)
• Inspect gas connections for leaks using a bubble solution and replace fuel filters
• Replace spark plugs and check/adjust engine valves
• Perform a 4-hour load test to ensure the unit can operate under full load.
• Test all safety shutdowns and verify correct voltage and frequency.
2.1.4 Final Test Run
The generator shall be subjected to a load bank test (Annually). The test run will run for a minimum of 4 hours. A record of the test and the operating conditions and reading along with personal observations and comments on the condition of the generator set shall be recorded in the service report. This yearly test will be in acquittance with NFPA 110 Sec. 8.2.4.3; If a generator fails the monthly test, it should be operated under a load supplied by a load bank (i.e. load bank tester) for two continuous hours each year. Because our generators are not tested monthly, this will be done. During this two-hour period, the unit should be operated as follows:
• At 25% of the nameplate Kilowatt rating for 30 minutes.
• At 50% of the nameplate Kilowatt rating for 30 minutes.
• At 75% of the nameplate Kilowatt rating for 60 minutes.
The “exercise” supplies by load bank test can improve a generator’s operating capacity, making it more responsive during a real power outage.
2.1.5 NORMAL SERVICE CALLS FOR REPAIR:
The CO/COR will contact the contractor for repairs of any generator that has malfunctioned. The contractor will respond to the call within 24 hours of an email or phone call. Once acknowledged the contractor must be onsite within 5 business days to troubleshoot and order any parts or materials needed to repair generator. Repairs are to be performed within 15 days of approved Service Contract Work Request (SCWR). Contractor shall notify CO/COR if parts or materials will be delayed beyond 15 business days.
Any additional work, required repairs or parts not covered under this preventative maintenance agreement shall not be performed unless specifically authorized by the
CO.
The contractor shall perform incidental service repairs in Not-to Exceed Amount $2,000.00 (per call or month, year).
Major repairs exceeding the $2000.00 threshold should be quoted to the CO/COR and approved prior to any work being performed.
2.1.5 Inspection Reports
After each inspection, the COR will be furnished with a written report detailing condition of the equipment and advising of further services required (if any) to assure operating dependability of the equipment.
2.1.6 Generator/Engine Specs
See Attachment 1- Generator Location and Specifications
2.1.7 Major Preventative Maintenance tasks
Major preventative maintenance tasks include all identified tasks in 1.1.1 and 1.1.2.
Minor Preventative maintenance tasks does not include items identified as “Annual” requirements.
2.2 COORDINATION, QUALITY CONTROL / ASSURANCE
The services shall be performed only when requested by the Contracting Officer (CO), the COR or the Maintenance Supervisor designated by the CO, during the performance period of this contract.
2.3 QUOTES
The Contractor shall provide quotes as requested by the CO, or COR, for any additional repairs, not covered by this PWS, required to ensure the proper operation of the generators.
PART 3 – PRODUCTS / MATERIALS
3.1 The Contractor shall provide all parts required for repairs at a cost mutually agreed to between the Contracting Officer or COR and the Contractor. Parts that are replaced shall be new or equivalent and are to be warranted against defects in material and workmanship for at least 90 days. Major components replaced shall be warranted against defects in material and workmanship for at least one (1) year. Should parts not be available immediately, the Contractor will notify the Contracting Officer or COR and provide an estimated time of receipt of the part(s). Parts removed during replacement shall become the property of the government. All parts and materials shall be of the original manufacturer's design and specification, or equal thereto. All lubricants shall be as recommended by the manufacturer.
All products and/or materials shall conform to the requirements of this Performance
Work Statement and specification attached, and shall be first quality, complying with all standards and applicable codes.
3.2 Quality Assurance Surveillance Plan
The COR will evaluate the Contractor's performance quarterly against performance standards established in this PWS. Evaluations will be to the extent practical to assure the contractor provides quality services IAW the requirements of the contract.
Evaluations could be validation of contractor supplied performance data. In addition, evaluations can be used as analysis of Customer feedback for performance trends and validation that customer concerns are resolved in a timely manner.
If at any time the COR receives indicators (e.g., valid customer complaints or notes performance standards are not being met) that the Contractor's performance is less than acceptable, the COR will investigate to determine if this is a onetime issue that has been promptly corrected, or if the discrepancy is systemic in nature. If the issue is determined to be an isolated occurrence, the COR will continue with quarterly evaluations. If the issue is recurring and systemic in nature, the COR will notify the Contract Employee to have the issue corrected and the COR will perform more frequent evaluations.
If a systematic problem cannot be corrected between the COR and the Contract Employee, the COR will notify the Contracting Officer to contact the Contractor to correct the problem. The COR will submit to the Contracting Officer the specific deficiency to the requirement, the date and time it was discovered. The Contractor will be given two (2) working days after notification from the Contracting Officer to correct the deficiency in accordance with requirements of the contract. Deficiencies that cannot be corrected within two working days will be reported to the Contracting Officer
PART 4 – EXECUTION
4.1 FLETC IDENTIFICATION BADGE/PIV CARD AND VEHICLE PASS
All contractor employees working on or requesting access must obtain prior authorization to enter FLETC. The FLETC badge, or PIV card, is required to be worn visibly on the outside clothing between the neck and waist always displaying the photograph side of the badge/card while on the FLETC premises.
Those contractors who need to operate or park vehicles on FLETC property are required to obtain a vehicle pass. Vehicle passes will only be issued to Contactor and subcontractor personnel for vehicles maintained in a safe operating condition.
Those seeking a vehicle pass shall provide the following documents;
1. Valid Driver’s License
2. Valid Vehicle Registration
3. Proof of Insurance
4. FLETC Identification Badge
4.2 DELIVERY AND STORAGE
All products and/or materials shall be delivered in accordance with state and federal regulations and stored in an approved manner for the specific application.
Contractor shall verify all conditions prior to beginning work or ordering materials.
Contractor should review conditions with Project Manager, COR or Maintenance Supervisor designated by the CO, prior to ordering materials and starting work.
5.0 Deliverables
Deliverable Frequency Recipient Description Inspection Report After each visit COR Condition, findings, recommendations Annual Load Bank Test Report Annually COR Test results, readings, observations
Preventative Maintenance Log Quarterly/Annually COR Completed tasks, compliance
Quotes for Repairs As requested, CO/COR Itemized quote for additional repairs/parts
Certification of Service Annually COR Statement of generator certification
6.0 Performance Requirements Summary (PRS)
Performance Requirement Standard/Metric Surveillance
Method Acceptable Quality
Level (AQL) Quarterly Minor Inspection
Complete all required tasks per SOW
Inspection/Report Review 100% completion
Annual Major Inspection
Complete all required tasks per SOW
Inspection/Report Review 100% completion
Annual Load Bank Test Conduct per NFPA 110, record/report results
Inspection/Report Review 100% completion
Inspection Report Submission
Submit within 2 business days after inspection Report Review 100% on-time
Certification of Service Submit annually within 5 business days of test Report Review 100% on-time
Quotes for Additional Repairs
Provide within 3 business days of request Review 100% on-time
Personnel Badging/Vehicle Pass
All personnel properly badged/passed Spot Check 100% compliance
7.0 ATTACHMENT
Attachment 1- Generator Locations and Specifications
CLN Building Fuel Type Manufacturer Model Number Serial Number KW
1 1 NG Generac SG0100AG269.ON18HPYYG 3015129211 100
2 3 NG Generac SG0040AG264.%S18SPYYA 3015177620 40
3 75 NG Generac SG0200GG201.14258PPYYG 3015838264 200
4 91 NG Generac SG0625KG02339N18PPYYG 3016749413 625
5 92 NG Generac SG0100G269.ON18HPYYG 3015137052 100
6 93 NG Generac SG0050K264.5S18TPYYA 3015098573 50
7 146 NG Onan DSHAD9767821 A120291216 230
8 252 NG Generac SG0035GG264.5S18SPSPYYA 3015098562 35
9 402E Propane Generac 13597280400 2113081 35
10 147 NG Generac SG0100GG269.ON18HPYYG 3015129204 100
11 198 NG Generac SG0060AG264.5S18TPYYA 3015512205 60
12 201 Diesel Echo SSG-3125S1-4KIX D18601 000283 125
13 99 NG Generac SG0350GGG0219N18PPYYG 3018018974 350
14 101 NG Generac SG0035GG264.5S185PPYYA 3015118681 35
15 Gate 10 NG Generac SG0050G264.5S18TPYYA 3015103028 50 pzucco Cross-Out
7.1 Attachment 2
ATTACHMENT 2
Maintenance Schedule
BLGD# KW Major Load Bank Minor 1 Minor 2 Minor 3 1 100 April April January July October 3 40 April April January July October
75 200 April April January July October 91 650 April April January July October 92 100 April April January July October 93 50 April April February August November
146 230 April April February August November 147 35 April April February August November 198 40 April April February August November 201 107 April April February August November 252 35 April April March September December
402E 35 April April March September December 99 350 April April March September December
101 10 April April March September December Gate10 10 April April March September December
SECTION H - SPECIAL CONTRACT REQUIREMENTS
FLETC STATEMENTS
H.1 Directives, Regulations, And Instructions The Contractor, its personnel, subcontractors, their personnel, and representatives shall become acquainted with and fully comply at all times with the Federal Law Enforcement Training Centers (FLETC) Regulations, Directives, and Instructions.
Any individual shall be subject to removal from the Center for noncompliance.
In the event of a conflict between this contract and any FLETC Directive, Regulation or Instruction the contract prevails.
H.2 Operation on The Facility Safety The Contractor shall conduct the operation(s) under this contract in strict conformance with all FLETC safety directives and Federal, State, and local requirements and with all applicable provisions of 29 CFR Part 1910 and 1926 of the Occupational Safety and Health Act (OSHA) and USACE EM-385-1-1.
The Contractor shall conform to all safety rules and requirements in effect on the award date of this contract and shall take such additional precautions as the Contracting Officer (CO) may reasonably require for safety and accident prevention purposes while performing any work under this contract. The Contractor agrees to take all reasonable steps and precautions to prevent accidents and preserve the life and health of Contractor and Government personnel performing in any way under this contract.
The Contractor shall make contract personnel available for Government furnished safety and occupational training for an estimate of two (2) hours to four (4) hours annually per individual. Government furnished training may include Quality, Safety and Occupational requirements.
H.2.1 Accident Reports Within 24-hours of occurrence, the Contractor shall prepare a report of all job-related accidents and injuries occurring on FLETC property. The Contractor shall deliver the report to the Contracting Officer Representative (COR). The Contractor shall maintain an accurate record of all accidents resulting in personal injury, death, trauma, or occupational illness or disease; exposure to hazardous materials (asbestos, lead, etc.); and all injuries reported on the Occupational Safety and Health Administration (OSHA) Form 300, Log of Work-Related Injuries and Illnesses.
H.2.2 Occupational Hazards The Contractor shall comply with all elements of OSHA Safety and Health Standards, the FLETC Safety & Health Directives and all other Federal, State and Local regulatory requirements.
H.2.3 Fire Prevention Contract personnel shall report fires immediately upon detection.
1. Glynco Security
a. Dispatch x2911
b. (912) 267-2911
2. Artesia Security
a. Dispatch x8136
b. (575) 748-8136
3. Charleston Security
a. Dispatch x911
b. (843) 974-6305
4. Cheltenham Security
a. Dispatch x911
b. (301) 877-8400
The Contractor shall observe all OSHA, FLETC, and National Fire Prevention Association (NFPA) requirements for handling and storage of combustible supplies, materials, waste, and trash. If combustible materials are to be stored on the premises, the Contractor shall obtain Government approval, label the containers with the fire hazard potential of the materials and store the containers in fire-rated locking metal cabinets.
H.2.4 Traffic Regulations Contractor and subcontractor personnel operating motor vehicles on FLETC shall observe traffic regulations and posted speed limits except as defined elsewhere in this contract. The only exception to posted speed limits is passing jogging formations, when speed shall be reduced to 15 mph. Traffic laws are enforced on the Center and violations shall be assessed penalty points, which can result in revocation of driving privileges on Center.
H.2.5 Weapons Contractor and subcontractor personnel are not permitted to bring privately owned firearms, weapons, or ammunition on the Center. This restriction includes handguns, rifles, shotguns, hunting bow and arrows, etc. All privately owned firearms, weapons, and ammunition must be surrendered/checked in at the main gate upon entry to FLETC.
H.2.6 Supervision of Contractor Personnel The Contractor's personnel shall remain under the Contractor's direct supervision at all times. Although the Government will coordinate direction within the scope of the contract, detailed instructions for the Contractor's personnel's performance and supervision shall remain the sole responsibility of the Contractor.
H.3 Medical Treatment Only emergency medical care is available in Government facilities to Contractor personnel who suffer on-the-job injury. The Government will NOT perform physical examinations on Contractor personnel except as specified elsewhere in this contract.
Government emergency vehicles and medical personnel may be used as the first point of treatment in emergency situations affecting Contractor personnel suffering pain or whose life or limb may be in danger.
Transfer to other than Government medical treatment facilities shall be affected by the Local Rescue Squad or Security Vehicle as determined necessary by attending medical authorities. The Contractor shall render payment for care at the rates established by the CO as equitable with like services rendered in the local community. Upon receipt of a statement of charges, reimbursement will be made by the Contractor as a credit to the next billing invoice. Cost of these emergency services shall be incurred and borne by the Contractor as non-reimbursable by the Government.
H.4 Subcontracting The Government reserves the right to approve or disapprove subcontractors for any work required by this contract. The Contractor shall obtain the CO's written approval of all subcontractors and provide copies of approved subcontracts.
H.5 Order of Work The Contractor shall arrange the work so that it will not cause interference with the normal conduct of Government business or with the progress of other Contractors' projects. The Contractor shall submit all work schedules for approval by the COR.
The Contractor shall adhere to the established schedules.
H.6 Other Contracts The Government may award third party contracts for additional work at or near the site of work under this contract. The Contractor shall fully cooperate with the other contractors and with Government employees and shall carefully adapt scheduling and performing the work under this contract to accommodate the additional work, heeding any direction that may be provided by the CO. The Contractor shall not commit or permit any act that will interfere with the performance of work by any other contractor or by Government employees.
H.7 Disruption of Contractor Work Schedule The Contractor shall promptly notify the CO and the COR when it appears that Government activities or personnel or other contractor's projects are hindering the effective execution of its work efforts.
H.8 Rights of The Government to Perform Functions With Its Own Personnel The Government reserves the right to perform or supplement performance of contract functions with Government personnel during periods of disaster, war emergencies, police actions, or acts of God. Such performance shall not constitute a breach of contract by the Government within the meaning of the contract clause FAR 52.212-4 entitled "Termination for Cause".
The Contractor agrees under such circumstances to permit the Government to use any essential Contractor-furnished property. The Government will equitably compensate the Contractor for use of such property.
H.9 Government Performance of Services During Labor Strikes Because the services called for under this contract are of critical importance to FLETC, the Government reserves the right to take over or supplement performance of this contract in the event of a labor strike by the Contractor's personnel which impairs the Contractor's ability to satisfactorily perform the contract. Under such circumstances and at the direction of the CO, the Contractor agrees not to interfere in any way with Government performance. The Contractor further agrees under such circumstances to permit the Government to use any essential contractor-furnished property. The Government will equitably compensate the Contractor for use of such property.
The Contractor will not be entitled to payment for any performance period, in part or in total, during which the Government assumes performance under this clause. This clause does not limit the Government's rights under any other clause of this contract, including but not limited to, "Termination for Cause”; “Termination for Convenience”, and "Inspection/Acceptance” in accordance with FAR 52.212-4(a).
H.10 Conservation Contractor and subcontractor personnel shall actively participate in all energy conservation efforts and programs applicable to work performed under this contract. The Contractor shall instruct its personnel and subcontractors in utilities conservation policies.
H.11 Labor Relations The Contractor shall maintain satisfactory labor relations with its personnel. Representatives of the Contracting Office will not participate in labor relation matters unless disputes develop that interfere with the proper performance of the contract, at which time the representative may endeavor to assist in settling the difficulty.
The Contractor shall provide the CO with a copy of any collective bargaining agreement applicable to personnel performing on this contract.
H.12 Affirmative Procurement Of Biobased Products Under Service And Construction Contracts The Contractor shall provide a complete list of biobased products purchased to carry out the contract requirements.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .