This document contains questions and answers regarding a solicitation to install copper and fiber optic cables at a new simulated border wall facility in Artesia, New Mexico. The solicitation is a small business set-aside issued by the Federal Law Enforcement Training Center seeking quotes to trench and install approximately one mile of ductbank and pull cable to create a new fiber optic and copper network. The solicitation includes responses that no as-built drawings are available, the preferred manufacturers for materials, and clarification that no underground splices will be permitted for the fiber optic cable. The document provides location details for where excess soils can be dumped and notes a non-disclosure agreement is required to receive a site map showing the routing of the new cables and pathways.

View the file

Other files

File Type Posted
70LGLY22QSSB00022 Amend 3.pdf PDF
70LGLY22QSSB00022 Amend 2.pdf PDF
dhs_form_11000-6.pdf PDF
70LGLY22QSSB00022.pdf PDF
Wage Determination.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

70LGLY22QSSB00022

x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

GLYNCO GA 31524

70LGLY

ATTN: Lynda Bush

1131 CHAPEL CROSSING RD

FEDERAL LAW ENFORCEMENT TRAINING CENTERS

DEPARTMENT OF HOMELAND SECURITY

06/17/20220001

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

06/17/2022

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

2022 FLETC OPERATIONS AND SUPPORT 70 0509

The purpose of this amendment is to provide responses to questions and to extend the closing date to July 28, 2022 at 1:00 pm.

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Lynda A. Bush

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

NSN 7540-01-152-8070

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

TEL: EMAIL: 912-267-3128 lynda.a.bush@fletc.dhs.gov

1. When can a site visit be scheduled? Call to set access and time. (575)748-8179, Ron Easterling

2. As-built drawings are needed, when can we anticipate receipt of current as builts? There are no as built drawings.

3. Is there a preferred manufacturer for the materials? Patch Panels – Superior with 12 port high density inserts. Rack – APC Netshelter.

4. Is there a verified clear underground path from building #58 to the simulated new border wall facility? No.

5. 5.7. is this fiber expected to be a ‘home run’ or will there be splices associated? Home run. No underground splices are allowed, 10 foot service loop required in each manhole/handhole.

6. 5.9. Are there a clear and defined pathway’s to existing handholes? Yes

7. 5.10.

a. During the installation of the 6-pair OSP will there be splice locations depicted on the prints to contractors. No splices

b. Will splice locations be identified for the 6 pair? No splices

8. Page 7 of SOW, Per 4. Task 1, 4.1.1 Materials and Task 2 Labor, Can government approximate the distance of trench line needed to be excavated? Can gov please provide drawing or layout of digging work. Approximately one mile,

9. Page 7, 4, 4.1.7, Is this the cabinet described in 5, Task 2, 5.5 ? or is an additional cabinet needed? Yes

10. Does new trench pathway have any pavement or sidewalks that need to be crossed? No

11. Is item # 4.1.3 need to be all dielectric or armored fiber jacket? Yes

12. Please state the placement depth required for new ductbank Minimum 36”

13. Is there an area on FLETC where excess soils generated from hand hole installation can be dumped? Yes

14. With regards to solicitation 70LGLY22QSSB00022, can a site map or some kind of marked up drawing be provided to show the routing of these new fiber and copper cabling and pathways?

That will greatly help in putting together our estimate. Yes. A Non-Disclosure Agreement(NDA) must be completed before the map is provided.