Questions and answers for the 70FB7026R00000024 Amendment 0002.pdf
PDF 32 KB Posted
- Solicitation number
- 70FB7026R00000024
- Issued by
-
Federal Emergency Management Agency
About this file
This is a Questions and Answers document for federal solicitation 70FB7026R00000024. The document addresses three inquiries from potential contractors regarding equipment specifications and condition requirements.
The primary clarifications concern equipment condition and battery requirements. The government confirmed that only new equipment is acceptable; used or refurbished equipment is not permitted. Regarding battery specifications, the government clarified that two (2) batteries per unit are required and should be included as part of the total estimated cost. This addresses a discrepancy noted by contractors who had previously quoted the requirement with two batteries but did not see battery specifications explicitly stated in the current solicitation. The responses confirm that despite any ambiguity in the solicitation language, the historical requirement of two batteries per lift unit remains in effect for this procurement.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and answers for the 70FB7026R00000024 solicitation
Question #: Please confirm whether used or refurbished equipment is acceptable under this requirement.
Answer: It is not acceptable since the government does not buy used or refurbished equipment.
Question #2: We have quoted this in the past and in those two (2) batteries were requested for each unit. I do not see that on this solicitation so I wanted to make sure that you are looking for One (1) battery for each unit.
Answer: The two (2) batteries are a part of the total estimated cost.
Question #3: Historically your customer needed two batteries per lift. Can you ask them if they would require two batteries per lift?
Answer: Yes, the tw1o (2) batteries are a part of the total estimated cost.