70133 - Fort Smith GSA Elevator Modernization - Waste Mgmt Plan - AR0021ZZ.xlsx

XLSX spreadsheet 20 KB Posted

Attached to
Amendment 001 - Elevator Modernization, Isaac Parker Federal Building and Courthouse, Fort Smith, AR
Solicitation number
47PH0522R0029
Issued by

About this file

This document provides details for a federal construction contract opportunity to modernize elevators in the Isaac Parker Federal Building and US Courthouse in Fort Smith, Arkansas. The General Services Administration is seeking proposals to modernize one existing traction passenger elevator. The scope of work involves completing the modernization within 365 calendar days, which includes 45 days for security clearances and pre-work activities. Liquidated damages are $250 per day for late completion. The estimated value of the contract is between $500,000 and $1,000,000. Davis Bacon wage determinations apply. Proposals are due by May 10, 2022 and must include pricing using the provided bid schedule form. The awarded contract will have a 120-day guarantee period. Evaluation criteria are technical approach, experience, schedule, past performance, and preventative maintenance approach. A pre-solicitation site visit will be held on April 20, 2022.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Waste Diversion Plan

: +christopher.clever@gsa.gov +walter.tersch@gsa.gov

(For consideration as an alternate). Anticipated sections match Actual to the right for 1:1 comparison.

-Jake Begnaud - WPIDBB Fine with either, will defer to +walter.tersch@gsa.gov Seems like it only boils down to estimating method or not.

-Christopher Clever - PCBL That's correct.

-Jake Begnaud - WPIDBBProject Waste Management PlanSubmittal Type:Waste Diversion Plan (Anticipated):Waste Diversion Report (Final) :
The general info in these gray cells replicates onto the Report tabs.
Project Name:Fort Smith GSA Elevator ModernizationFort Smith GSA Elevator ModernizationFort Smith GSA Elevator ModernizationECC (estimated construction cost):Project Manager:Lauren Young
ePM/ePMX Project # :70133
Project Short Description:FY22 Baseline Project. Elevator ModernizationFY22 Baseline Project. Elevator ModernizationFY22 Baseline Project. Elevator ModernizationFY22 Baseline Project. Elevator ModernizationFY22 Baseline Project. Elevator ModernizationFY22 Baseline Project. Elevator ModernizationPM email or phone:lauren.j.young@gsa.gov
gBUILD Project # :
Building Number:AR0021ZZAR0021ZZAR0021ZZService Center / Field Office:P07250A1P07250A1Budget Activity:(list all applicable)RWA # :RAR10542

Anticipated Waste Diversion Plan To be filled out and submitted Pre-Construction, with final Construction Documents (PM or contractor populates this pink section) Actual Waste Diversion Report To be submitted during Project Close-Out (Reports tab figures auto-populate this green section)

Material*
(see weight conversion factors below)Diversion MethodTarget Diversion Rate for each material, by weight
(Change to actual target(s) as needed)Diverted (lbs)Landfilled (lbs)Total C&D material weight (Diverted + Landfilled) (lbs)Diversion

Rate

Reuse*Recycle or CompostDonation
Asphalt50%000n/a
Brick, Masonry, and Tile50%000n/a
Cardboard50%000n/a
Carpet, including Padding50%000n/a
Ceiling tile50%000n/a
Concrete50%000n/a
Drywall/ sheetrock (unpainted)50%000n/a
Metals50%000n/a
Painted wood, drywall, or plywood50%000n/a
Reusable items50%000n/a
Roofing50%000n/a
Soil, Rock, Land Clearing Debris50%000n/a
Wood (unpainted)50%000n/a
Other: ____________________50%000n/a
Other: ____________________50%000n/a
Other: ____________________50%000n/a
Total**:000n/a
Reuse is encouraged. Please list any items such as cabinets, doors, shelves, bricks, framing lumber, siding, fill material, misc. millwork, etc. planned for reuse.
ItemReuse OnsiteReuse OffsiteOff-Site Recipient or Salvage/ Deconstruction Company
Volume-to-Weight Conversion Factor Reference Table
If a hauler reports materials by volume, this table enables conversion to weight, for reporting actual diversion and disposal.
Asphalt paving: 1 cubic yard = 773 lbsDirt or sand: 1 cubic yard = 929 lbs
Asphalt or composite roof shingles: 1 cubic yard = 731 lbsFiberglass insulation, loose: 1 cubic yard = 17 lbs
Brick, laid flat: 1 flat square foot = 20 lbsMixed (composite) C&D material: 1 cubic yard = 417 lbs
Brick, loose: 1 cubic yard = 3,200 lbs. (1 cubic foot = 120 lbs)Sheetrock (drywall), loose: 1 cubic yard = 393.5 lbs
Ceramic tile, scrap, loose: 1 cubic yard = 1,214 lbsRock, crushed: 1 cubic yard = 2,570 lbs
Concrete: 1 cubic yard = 860 lbsWood: 1 cubic yard = 169 lbs
*Only non-hazardous materials need to be included in this document. C&D mandates governing GSA exclude hazardous materials such as asbestos or lead-containing paint.
**At substantial completion, the final number of (a) diverted tons, and (b) total non-hazardous C&D material tons must be reported via the ePMXpress Project Detail tab. ePMXpress powers GSA's tracking metrics.

File details come from the government source that posted it. Updated .