700-WR-2027-WR-03 -Addendum 1.pdf

PDF 105 KB Posted

Attached to
Water, Sewer, and Electric SCADA Master Plan
Solicitation number
700-2027-WR-03
Issued by
Jackson County, Cleveland Town, North Carolina

About this file

This Addendum 1 clarifies requirements and procedures for RFQ 700-2027-WR-03, issued by the Town of Clayton, North Carolina, for the development of a Water, Sewer, and Electric SCADA Master Plan. The addendum addresses 20 questions submitted during the Q&A open period and affirms that all other terms and conditions in the RFQ remain in full force and effect. Key clarifications include: relevant experience from named subconsultants may count toward the minimum three water/wastewater SCADA projects and one electric distribution project requirement, provided the respondent documents the relationship and partnership history between the prime and subcontractor; listed certifications for key personnel (PE, GICSP, CISSP, ISA/IEC 62443) are non-exhaustive examples rather than minimum requirements; the OT cybersecurity assessment should consider non-intrusive methods while following best practices given that systems support daily operations; cybersecurity interviews, workshops, and document review may be conducted remotely through Town-approved secure means; the assessment includes all Town SCADA systems (Distribution, Collection, Reclamation, and Electric) without anticipated access restrictions beyond standard remote access controls; a subconsultant performing Part A cybersecurity assessment is eligible to perform Part B implementation support provided it does not supply hardware or software; and the 40-page limit excludes resumes, covers, tables of contents, dividers, and required attachments but includes all other content.

The addendum further specifies that the lead firm's $2,000,000 Cyber/Technology Errors and Omissions insurance coverage may satisfy subconsultant requirements with written confirmation from the carrier; the Professional Services Agreement and NDA need not be signed or submitted with the SOQ but will be required upon contract award; experience in SCADA master planning, system design, and comprehensive OT/SCADA work demonstrates qualification, with assessment and planning phases of ongoing implementation programs qualifying when they demonstrate the respondent's ability to evaluate existing infrastructure and develop improvement recommendations; experience collectively demonstrated by the prime consultant and subconsultants is acceptable, with experience from personnel's prior employment evaluated equally provided it is documented as applicable to the scope; Section 15.8 permits Part B professional services including controls design, standards development, configuration review, FAT/SAT witnessing, commissioning oversight, cybersecurity implementation support, managed security monitoring, and owner's advisory services, provided the consultant does not supply hardware or software for projects it specified where it has a financial interest; and architecture diagrams should be produced in Visio or like software. For site investigations, respondents should assume one elevated storage tank out of four for Distribution, three lift stations out of 27 for Collection, one reclamation facility out of two for Reclamation, and one substation and one load shedding generator site for Electric. Funding for Part A has been planned and approved; Part B funding is contingent on CIP project development and future Town Council appropriation decisions. The Town clarified that the notice period for material breach remedies in Article 8.2 is thirty (30) days, correcting a typographical error.

View the file

Other files

File Type Posted
RFQ 700-2027-WR-03.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Date: 11/19/2026

Project: Water, Sewer, and Electric SCADA Master Plan

RFQ # 700-2027-WR-03

Addendum No. 1

Please note that this Addendum answers questions submitted during the Q&A open period. All other terms and conditions given in the RFQ are in full force and effect.

QUESTIONS & ANSWERS

Number Question Response

Q.1 Relevant experience (Section 9.D): May projects performed by a named subconsultant count toward the minimum of three water/wastewater SCADA projects and one electric distribution project, or must the lead firm have performed all of them?

The Town of Clayton has a desire to work with firms who have prior experience with master planning for SCADA systems in both the electric and water/sewer utility space. In the event the respondent is relying on a subcontractor, the respondent should discuss, in relevant detail, the previous relationship between the prime and subcontractor, and to what extent the two parties have worked in partnership on projects similar in scope.

Q.2 Key personnel credentials (Section 9.C):

Are the listed certifications (PE, GICSP, CISSP, ISA/IEC 62443 certificates) examples, or minimum requirements for specific roles? In particular, may the OT cybersecurity lead be provided by a subconsultant, and will equivalent credentials (e.g., CISSP, CISM, ISA/IEC 62443) satisfy the OT cybersecurity lead role?

The listed certifications are not a set of minimum requirements for personnel, but rather a non-exhaustive list of potential credentials that might speak to a respondent (and their staffs’) ability to adequately meet the needs of the Town.

In the event that no staff (whether they be prime or sub) hold any of the listed credentials or any other relevant certifications, special attention should be paid in documenting the approach the firm takes in assuring cybersecurity and other relevant issues are addressed by the respondent.

Q.3 Cybersecurity assessment depth (Task 3, item 7): Does the Town expect the OT cybersecurity assessment to be non-intrusive (document review, interviews, configuration review, passive network observation), or does it anticipate active testing such as vulnerability scanning or penetration testing of SCADA and substation networks?

The town is relying on the selected respondent to assess and follow best practices in this matter. Town SCADA systems currently support daily operations, as such, special consideration should be given to any activity that may disrupt day to day operation of the systems and service provision.

Q.4 Remote work: Beyond the required site visits in Task 2, may cybersecurity interviews, workshops, and document review be conducted remotely through Town-approved secure means?

The Town supports any and all measures to reduce the amount of Town funded travel and on-site hours to ensure its needs are met in the most affordable way possible. This includes the provision of remote meetings, workshops, interviews, and the like as practicable.

Q.5 Electric assets: Does the cybersecurity assessment include the SEL RTAC/substation networks and any assets supported by ElectriCities or Pungo Engineering, and are there access restrictions for those systems?

Yes, the cybersecurity assessment should include all Town SCADA systems (Distribution, Collection, Reclamation, and Electric). We do not envision any access restrictions beyond standard remote access controls to the electric SCADA system.

Q.6 Vendor neutrality (Section 15.8): Would a subconsultant that performs the Part A cybersecurity assessment be eligible to perform Part B cybersecurity implementation support (e.g., segmentation design, incident response planning, tabletop exercises), provided it does not supply hardware or software?

Yes.

Q.7 Insurance (Section 14.3 and Attachment B, Article 5): Must each subconsultant independently carry the $2,000,000 Cyber/Technology Errors and Omissions coverage, or may the lead firm's coverage satisfy this requirement?

The lead firm’s coverage may satisfy this requirement, provided the Town receives written confirmation from the insurance carrier that the applicable services performed by its subconsultants are covered under the lead firm’s policy and subject to the required coverage limits

Q.8 Page limit and forms (Sections 9 and 9.I):

Do the resume appendix and required forms count toward the 40-page limit?

Section 9.I references Attachments A through C, while the submittal checklist lists only Attachment A. Should the Professional Services Agreement (Attachment B) and NDA (Attachment C) be signed and included with the SOQ, or only upon selection?

The 40-page limit is inclusive of resumes, covers, tables of contents, and dividers but excludes required attachments. The Professional Services Agreement (Attachment A) and NDA (Attachment B) do not need to be signed or submitted as executed documents with the SOQ and are provided for informational purposes at this point. Execution of both will be required as a condition of contract award.

Q.9 Section 9.D requires three water/wastewater SCADA master plans or major assessments completed within seven years. Would the same apply to the electric distribution SCADA, distribution automation, or ADMS/OMS planning project requirement? Will completed assessment or planning phases of ongoing implementation programs qualify? Will a comprehensive OT/SCADA

Like work does satisfy the requirement.

The Town has a desire to understand a respondent’s prior experience in SCADA master planning, to include system design and implementation. Projects in this scope include those aforementioned.

However, it should be noted that, as this is a master planning scope of work, the Town is most interested in examples that demonstrate the respondent’s ability to critically evaluate existing infrastructure, cybersecurity assessment qualify as a major SCADA assessment?

identify needed improvements, and develop budgetary and other deliverables that assist the town in implementing those improvements.

Q.10 Can the required experience be demonstrated collectively by the prime consultant and proposed subconsultants?

How will experience performed by proposed personnel while employed by another firm be evaluated?

Yes, please refer to the answer in Q.1 for more information. Experience performed by personnel while they were employed at another firm will be evaluated equally to experience at the respondent firm provided it is documented as applicable to the scope of work provided.

Q.11 Please clarify §15.8’s restriction on serving as system integrator or supplier.

Does it permit the selected consultant to perform detailed controls design, programming-standard development, configuration review, FAT/SAT witnessing, commissioning oversight, cybersecurity implementation support, and owner’s advisory services under Part B? If a firm discloses technology partner or reseller agreements under Section 9.B and does not supply hardware or software for projects it specified, does that satisfy §15.8? Does the restriction extend to recurring services such as managed security monitoring

Section 15.8 is intended to preserve vendor-neutral recommendations and avoid financial conflicts of interest. The selected consultant may be considered for Part B professional services, including controls design, standards development, configuration review, FAT/SAT witnessing, commissioning oversight, cybersecurity implementation support, managed security monitoring, and owner’s advisory services. All technology partner, reseller, or similar financial relationships must be disclosed under Section 9.B. Disclosure alone does not satisfy §15.8 or waive its restrictions. A consultant may not supply hardware or software for a project it specified where the consultant has a financial interest in, or would financially benefit from, the recommended product or solution.

Q.12 Has funding been planned and approved for Part A, and can the Town provide its anticipated planning budget or funding range? Are any near-term Part B projects already funded or included in the capital improvement program?

Funding has been planned for Part A.

Part B funding is in part CIP project dependent, part contingent on the development and specifics of the master plan, and subject to the desire of this and future Town Councils. The Town, like all North Carolina local governments, must follow applicable law as to non-appropriation of funds in contracting.

Q.13 Will the Town consider reasonable exceptions addressing professional standard of care, limitation of liability, The Town may consider reasonable exceptions to the proposed contract terms during contract negotiations with mutual consequential-damages waiver, payment withholding, insurance, and compensation for changes or delays?

Must respondents provide replacement language with their SOQ?

the selected respondent, including provisions concerning standard of care, limitation of liability, consequential damages, payment withholding, insurance, and compensation for changes or delays. Any exception is subject to negotiation, applicable law, and any required legal approval, and the Town is not obligated to accept a proposed exception. Respondents are not required to submit replacement contract language with their SOQ.

Q.14 What number and types of remote facilities should respondents assume for representative site investigations? Please distinguish existing, planned, unmonitored, and soon-to-be-decommissioned facilities.

For Distribution: 1 out of 4 elevated storage tanks

For Collection: 3 out of 27 lift stations (2 to be retired 2027)

For Reclamation: 1 out of 2 reclamation facilities (1 to be retired Q1 2027)

For Electric: 1 of 2 substations

1 load shedding generator site Q.15 Is Part A intended to include documentation review, interviews, configuration review, and passive observation, or also active scanning and penetration testing? Will evaluation against the listed frameworks use a consolidated assessment approach?

See Q.3.

Q.16 Without disclosing security-sensitive information, please describe the availability and completeness of asset inventories, network diagrams, PLC/RTU programs, I/O lists, control narratives, software-license records, and prior assessments. Are these records accessible to the Town under existing integrator agreements?

For water distribution and collection, the original project manual is available upon contract and NDA execution. This includes an asset inventory although it is not up to date. Additional asset information is available as an export from the CMMS. PLC/RTU programs and I/O lists are available as extracts or requests from our existing SCADA integrator.

At the Sam’s Branch Water Reclamation facility in particular, more information is readily available given its recent addition to the utility.

For the Electric Department, we do not currently maintain comprehensive documentation of SCADA asset inventories or network diagrams. Upon execution of an appropriate contract and non-disclosure agreement (NDA), the Town can provide configuration files for SEL communications devices and RTACs, which include communications settings, device mappings, and I/O assignments.

Q.17 Section 9.I lists "Completed Attachments A through C" under the Statement of Qualifications contents, whereas the submittal checklist on Attachment A only requires "Attachments A completed and signed". Furthermore, Section 3.5 and Section 15.7 state that the Non- Disclosure Agreement (Attachment C) and detailed data are only provided to or executed by the "selected firm". Could the Town please confirm whether Attachments B and C must be submitted with the SOQ or executed only upon award?

See Q.8.

Q.18 Section 9 states that the entirety of the SOQ shall not exceed 40 single-sided pages, while Section 9.C mentions that "Resumes of no more than two pages each shall be provided in an appendix". Please confirm if the resume appendix, table of contents, covers, dividers/tabs, and required forms (Section 9.I) are excluded from the 40-page limit.

See Q.8.

Q.19 In Attachment B (Standard Agreement), Article 8.2 states: "After ten (30) days written notice to the other party of its material breach of the Agreement, this Agreement may be terminated by the noticing party...". Could the Town clarify whether the notice period to remedy a breach is intended to be 10 days or 30 days?

The intended notice period is Article 8.2 is thirty (30) days. The reference to ten

(30) days is a typographical error and should read thirty (30).

Q.20 Section 6 mandates drawings in "Visio or like format and PDF; spatial data in Esri-compatible formats; and inventories and cost models in Microsoft Excel", whereas Attachment B, Section 10.7 requires that all drawings be "CAD generated and shall be provided on electronic media downloadable onto an AutoCAD based system" and adhere to alternate text tagging under 34 characters for web accessibility. Please confirm which drafting software format is required for Master Plan architecture diagrams.

Respondents should plan on producing architecture diagrams in Visio or like software.