This is a Statement of Work (SOW) for the manufacture of NEXRAD Power Supply with Fan Tray units under requisition number 142082-26-0457. The National Weather Service's Logistics Management Branch requires a single-year contract to manufacture nine spare power supply units to support operational radar readiness, maintenance, and repair for the WSR-88D NEXRAD weather radar system operated by the National Logistics Support Center.

The contract deliverables are divided into two Contract Line Item Numbers (CLINs). CLIN 0001 requires the contractor to manufacture two first article (FA) units for quality control testing in accordance with drawing DWG 2210091 within 24 weeks of contract award. Following National Weather Service Quality Control Department approval and acceptance of the first articles, CLIN 0002 requires the contractor to manufacture and deliver seven production units within 12 weeks of FA acceptance. All units must include a Certificate of Compliance or equivalent and be individually packaged according to commercial vendor marking and barcoding instructions for shipment via UPS or FEDEX Ground to the National Logistics Support Center in Grand View, Missouri. The period of performance is 365 days following contract award. Invoices must include the Purchase Order Number, part number, applicable tariff information, and itemized shipping costs. The Government reserves the right to waive the first article requirement if the awarded contractor has previously delivered this supply successfully.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work

NEXRAD Power Supply with Fan Tray

REQUISITION NO: 142082-26-0457

1.0 INTRODUCTION

1.1 Background

The Logistics Management Branch provides overall management of the NWS logistics program.

Responsibilities include developing national logistics policy and guidance; integrated logistics support planning for new systems; inventory management; procurement initiation; repair ordering; cataloging;

source, maintenance, and recovery coding; modifications; customer support and obsolescence programs. It implements computerized systems that interface with military and Governmental systems for logistics data, parts issues, parts receipts and funds transfers. The Branch is the NWS focal point for multi- agency logistics management and serves as a designated Primary Inventory Control Activity (PICA) for the Department of Defense and the Federal Aviation Administration on NEXRAD and ASOS programs.

1.2 Discussion

In order to support the overall life-cycle of the NEXRAD WSR-88D weather radar, the National Logistics Support Center (NLSC), through a Memorandum of Agreement (MOA), provides technical logistics support to agencies within the Department of Commerce (DOC). Emergency shipping, project distribution and other services are provided to DOC field sites at locations world-wide. The NLSC provides highly technical logistical support of equipment spares, critical to the diverse missions of the participating agencies.

1.3 Requirement

The Logistics Management Branch has a requirement for a single year contract to manufacture 09 spare Power Supply with Fan Tray(s) to be used to support the operational radar readiness, maintenance and repair associated with the WSR-88D NEXRAD Radar.

2.0 SCOPE OF WORK

Manufacture two (02) first articles (FA) for quality control testing of Power Supply with Fan Tray(s) in accordance with DWG 2210091within 24 weeks of contract acceptance. Any change to the requested requirements will need prior approval by the National Weather Service. Any change to requested quantity (Vendor “required minimum”) will need prior approval by the National Weather Service. Any deviation from attached DWG 2210091 will need prior approval by the National Weather Service. Once the QC Department has approved and accepted the units for stock, the Manufacture will be contacted to proceed with the production units.

Manufacture seven (07) production units of Power Supply with Fan Tray(s) in accordance with DWG 2210091. The units are to be delivered within 12 weeks of FA acceptance.

Provide a Certificate of Compliance (CoC) or equivalent for each Power Supply with Fan Tray.

Invoice(s) will require Purchase Order Number, part number, tariff (if applicable) and shipping/FOB destination cost, unit and total cost.

Individually package the Power Supply with Fan Tray(s) IAW Instructions to Commercial

Vendors for Marking and Barcoding Supplies for shipments to the National Logistics Support Center, Grand View, MO.

3.0 DELIVERABLES

CLIN 0001: The Contractor shall manufacture two (02) first articles (FA) Power Supply with Fan Tray in accordance with the Specifications and Drawings included in DWG 2210091 within 24 weeks of Contract award. Once the National Weather Service Quality Control Department receives, inspects and accepts the units for stock, the Contractor will be notified to proceed with the seven productions units.

CLIN 0002: The Contractor will package and ship seven (7) production units of the Power Supply with Fan Tray within 12 weeks of program acceptance via UPS or FEDEX Ground services, IAW Instructions to Commercial Vendors for Marking and Barcoding Supplies for shipments to the National Logistics Support Center, Grand View, MO.

The above schedule is an estimate and subject to change by the Contracting Officer.

The Government reserves the right to waive First Article requirement if the awarded contractor has successfully delivered the supply in the past.

3.1 Period of Performance: 365 days after award of Contract/date set by Contracting Officer.

3.2 Delivery Address:

NOAA National Logistics Support Center Attn: Calaina Schneider/Tracye Gregory, 142082-26-0457

14200 MERRITT RD.

GRANDVIEW, MO. 64030

Technical Point of Contact:

NWS NEXRAD LMS/IM

Calaina Schneider 1325 East West Highway Silver Springs, MD 20910 Calaina.Schneider@noaa.gov