"Gundlach" Demolition of Existing Structure & Site Restoration
Solicitation number
RFP 102-2026
Issued by
St. Louis City, Missouri

About this file

This is a Scope of Work and Hazardous Material Identification document for the St. Louis Public Schools (SLPS) Board of Education regarding the demolition of the Gundlach School located at 2931 Arlington Avenue, St. Louis, Missouri 63120. The project encompasses the complete razing of all buildings and structures on the 69,579 square foot main building and 8,500 square foot addition constructed in 1931. The scope of work includes removal of asbestos-containing materials (ACMs) prior to demolition, including felt paper under wood flooring (28,500 SF), flooring and mastic (38,750 SF), chalkboards and adhesives (325 items), window systems, and door caulk. Additionally, 410 lighting fixtures, 190 hydraulic door closures, 28 water fountains containing CFCs, and all HVAC systems containing CFCs/Freon must be removed as USEPA RCRA regulated hazardous materials. The project includes two allowances: $100,000 for unforeseen ACM conditions and $20,000 for lab packing of household, office, and boiler chemicals. Work also includes removal of foundations, slabs, footings, below-grade structures, surface improvements, debris hauling and disposal, backfill and compaction, selective salvage coordination, and site stabilization. The target project duration is 30 working days per site with standard work hours from 6:30 AM to dusk.

The contractor is responsible for obtaining all required permits, regulatory notifications, environmental filings, air quality notifications, street and traffic permits, hauling permits, and disposal approvals. Environmental compliance must adhere to all federal, state, and local regulations with coordination of hazardous material abatement sequencing and provision of disposal manifests. Site protection requirements include protection of adjacent buildings, sidewalks, utilities not designated for removal, and the public right of way, with damage repairs at contractor expense. The contractor must provide continuous dust suppression, temporary construction fencing with locked gates, portable sanitation facilities, and maintain on-site supervision at all times with weekly safety meetings. Traffic control measures include shaker plates at exits, street cleanup, and approved truck routes. Required submittals with proposals include company qualifications and demolition experience, similar project history, safety records and EMR, City of St. Louis demolition contractor certification, violations and penalties from the past three years, proposed schedule, equipment list, key personnel, permit strategy, waste disposal plan, dust control plan, and traffic control plan. Closeout deliverables include permit copies, disposal receipts and manifests, safety reports, daily or weekly progress logs, and final completion certification.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Scope of Work and Hazardous Material Identification for:

Gundlach School — 2931 Arlington Avenue, St. Louis, MO 63120

Age of Construction 1931

Approximate Square Footage 69,579 SF Main Building

8,500 SF Addition

Asbestos Containing Materials (ACMs) to be removed PRIOR to demolition under base bid contract:

Felt Paper under Wood Flooring 28,500 SF

Flooring and Mastic 38,750 SF

Chalkboards and Adhesives 325 items

Window Systems All

Door Caulk All

ACMs to remain with structure during demolition:

Roofing Systems 81,500 SF

Miscellaneous mastics not identified above.

USEPA RCRA regulated hazardous materials to be removed PRIOR to demolition under base bid contract:

Lighting Fixtures 410 lighting fixtures

Hydraulic Door Closures 190 units

CFCs – Water Fountains 28 units

CFCs/Freon – HVAC Systems All

Allowance #1: Include an allowance within the base bid contract of $100,000 for unforeseen conditions to address other ACMs not identified within the above scope of work.

Allowance #2: Include an allowance within the base bid contract of $20,000 for lab packing of household hazardous chemicals, office chemicals, and boiler chemicals.

Demolition Work Includes Complete razing of all buildings and structures at each site

Removal of all building contents and non-salvageable materials

Removal of foundations, slabs, footings, and below grade structures unless otherwise directed

Removal of attached or adjacent covered walkways, pads, and sidewalks connected to demolished structures

Removal of surface improvements designated by SLPS

Loading, hauling, and lawful disposal of all debris

Backfill of voids

-ADD Backfill Specifications and Clean Fill Specifications

-ADD Specific details for Hempstead

Rough grading and compaction of disturbed areas

Site stabilization and hazard elimination

Selective salvage, if directed, shall be coordinated with SLPS prior to demolition.

Selective salvage to include the following items where applicable

-historical monuments

-time capsules

-brick

-hardwood floors

SLPS and contractor to meet to discuss these items in detail prior to start of work. Contractor to salvage, clean, and stage in a manner useful to SLPS.

PERMITS AND REGULATORY REQUIREMENTS

Contractor Responsibilities

Contractor shall obtain and pay for all required:

Demolition permits

Agency notifications

Environmental filings

Air quality notifications

Street and traffic permits

Hauling permits

Disposal approvals

Pre-Work Documentation

Prior to start of demolition, Contractor shall provide SLPS with:

Copies of all approved permits

Copies of all required notifications

Proof of regulatory filings

Utility disconnect confirmations

No demolition may begin until SLPS authorizes notice to proceed

ENVIRONMENTAL AND HAZARDOUS MATERIAL CONTROLS

Compliance-Contractor shall comply with all federal, state, and local environmental regulations

Hazardous Materials

SLPS will provide available environmental reports

Contractor shall coordinate required abatement sequencing

No regulated materials shall be disturbed without proper controls

Disposal manifests shall be provided when applicable

Dust and Emissions Control

Contractor shall:

Provide continuous dust suppression

Use wet methods and misting

Prevent off-site dust migration

Control airborne particulates

Dust control water may be supplied by SLPS from designated hose bibs only. Fire hydrant use is prohibited.

SITE PROTECTION REQUIREMENTS

Contractor shall protect:

Adjacent buildings

Sidewalks and stairs

Greenspace and landscaping

Utilities not designated for removal

Public right of way

Damage caused by demolition operations shall be repaired at Contractor expense.

TEMPORARY CONTROLS AND FACILITIES

Fencing and Security

Contractor shall provide:

Temporary construction fencing around demolition zones

Locked access gates

Controlled entry points

Barrier protection as required

Fence layout must be approved by SLPS

Laydown Areas

Staging areas must be inside fenced zones

Equipment storage outside fence is prohibited

Locations subject to SLPS approval

Sanitation Facilities

Contractor shall provide:

Portable toilets and wash stations

Trash receptacles

Placement subject to SLPS direction

SAFETY REQUIREMENTS

Supervision

A designated supervisor shall be on-site at all times

Supervisor must have demolition authority

Safety Program

Contractor shall:

Conduct weekly on-site safety meetings

Maintain safety logs

Enforce PPE requirements

Follow OSHA standards

Worker Identification

All workers shall wear:

High visibility safety vests or identifying shirts

Required personal protective equipment

Vehicle Escorting- When SLPS staff, students, or authorized personnel are present nearby, Contractor shall escort or spot vehicles entering and exiting the site.

TRAFFIC AND TRACK OUT CONTROL

Contractor shall:

Provide shaker plates or equivalent at exits

Prevent soil and debris track out

Perform immediate street cleanup when needed

Follow approved truck routes

Maintain safe pedestrian passage

UTILITIES

Contractor shall coordinate:

Utility identification

Shutoff verification

Disconnection and capping

Written clearance before demolition

No structure shall be demolished until utilities are confirmed safe

WORK HOURS AND SCHEDULE

Standard hours are 6:30 AM to dusk

Saturday work permitted

Sunday and holiday work require approval

Target duration is 30 working days per site unless otherwise approved

Contractor shall submit a:

Site specific demolition schedule

Sequencing plan

Crew loading plan

CLEANUP AND SITE RESTORATION

Upon completion Contractor shall:

Remove all demolition debris

Backfill and compact Rough grade for drainage

Eliminate hazards

Remove temporary controls when directed

Final acceptance subject to SLPS inspection.

SUBMITTALS REQUIRED WITH PROPOSAL

Bidders shall submit:

Company qualifications and demolition experience

Similar project history

Safety record and EMR

Proof of certification as a demolition contractor with the City of St. Louis

All violations, fines, penalties, and lawsuits within the last three (3) years of business

Proposed schedule

Equipment list

Key personnel

Permit strategy

Waste disposal plan

Dust control plan

Traffic control plan

CLOSEOUT DELIVERABLES

Contractor shall provide:

Permit copies

Disposal receipts and manifests

Safety reports

Daily or weekly progress logs

Final completion certification per site