About this file

This is an AAAP Project Specific Advertisement (PSA) Attachment detailing the post-award schedule for a GSA lease project. The document replaces the attachment referenced in section 1.05 of the RLP (R100) and applies to section 4.01 of the Lease (L100). The post-award schedule commences within 5 working days of lease award and governs the design and construction process through space acceptance.

The schedule establishes the following sequential activities with specified working day durations: Lessor-Provided Design Intent Drawings (15 days), Government review and approval of design intent drawings by GSA and the Client (10 days), Lessor preparation and submission of construction documents (30 days), Government review of construction drawings (20 days), Lessor preparation and submission of TI (Tenant Improvements) and BSAC (Building Standard Alterations and Costs) price proposal (15 days), Government review and approval of pricing (15 days), Government issuance of Notice to Proceed with construction (10 days), Lessor completion of TI construction and other required construction work (90 days), and Government inspection and acceptance of finished space (10 days). The total timeline from lease award to Government acceptance is 215 working days.

View the file

Other files

File Type Posted
6CO0527 - Program of Requirements - final.xlsx XLSX spreadsheet
6CO0527 - Post Award Schedule .pdf PDF
DENVER DELINEATED AREA MAP.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AAAP POST-AWARD SCHEDULE, PAGE 1 OF 1 PSA VERSION - REV (10/22)

AAAP Project Specific Advertisement (PSA) Attachment: Post-Award Schedule

This attachment details the post-award schedule for this project. It hereby replaces the Attachment referenced in section

1.05 of the RLP (R100) and should be used when reviewing section 4.01 of the Lease (L100).

The below post-award schedule commences within 5 working days of lease award. The time frames below apply to the management of the design and construction process, concluding at the date of acceptance for the space.

Activity Working Days

Lessor-Provided Design Intent Drawings 15

Government (GSA and Client) Review and Approval of Lessor Provided Design Intent Drawings

Lessor Preparation and Submission of Construction Documents 30

Government Review of Construction Drawings 20

Lessor Preparation and Submission of the TI and BSAC Price Proposal

Government Reviews and Approves Pricing 15

Government Issues Notice to Proceed with Construction 10

Lessor Completes Construction of TIs and Completion of Other Required Construction Work

Government Inspects and Accepts Finished Space 10

AAAP POST-AWARD SCHEDULE, PAGE 2 OF 2 PSA VERSION - REV (10/22)

Total Work Days from Lease Award to Government Acceptance 215