About this file

This document is an AAAP Project Specific Advertisement (PSA) Post-Award Schedule that outlines the timeline for design and construction activities following lease award. The schedule commences within 5 working days of lease award and establishes specific timeframes for each phase of the design and construction process, concluding with government acceptance of the space. The lessor must provide design intent drawings within 15 working days, followed by government (GSA and Client) review and approval within 10 working days. The lessor then has 30 working days to prepare and submit construction documents, with the government requiring 20 working days for review. The lessor must submit the Tenant Improvement (TI) and Building Standard Alterations and Construction (BSAC) price proposal within 15 working days, and the government has 15 working days to review and approve pricing.

Once pricing is approved, the government issues a Notice to Proceed with Construction within 10 working days. The lessor then has 90 working days to complete construction of the TIs and other required construction work. The government conducts final inspection and acceptance of the finished space within 10 working days. The total timeline from lease award to government acceptance is 215 working days. This schedule replaces the Attachment referenced in section 1.05 of the RLP (R100) and should be used when reviewing section 4.01 of the Lease (L100).

View the file

Other files

File Type Posted
6CO0527 - Program of Requirements - final.xlsx XLSX spreadsheet
DENVER DELINEATED AREA MAP.pdf PDF
6MO0265 - Post Award Schedule .pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AAAP POST-AWARD SCHEDULE, PAGE 1 OF 1 PSA VERSION - REV (10/22)

AAAP Project Specific Advertisement (PSA) Attachment: Post-Award Schedule

This attachment details the post-award schedule for this project. It hereby replaces the Attachment referenced in section

1.05 of the RLP (R100) and should be used when reviewing section 4.01 of the Lease (L100).

The below post-award schedule commences within 5 working days of lease award. The time frames below apply to the management of the design and construction process, concluding at the date of acceptance for the space.

Activity Working Days

Lessor-Provided Design Intent Drawings 15

Government (GSA and Client) Review and Approval of Lessor Provided Design Intent Drawings

Lessor Preparation and Submission of Construction Documents 30

Government Review of Construction Drawings 20

Lessor Preparation and Submission of the TI and BSAC Price Proposal

Government Reviews and Approves Pricing 15

Government Issues Notice to Proceed with Construction 10

Lessor Completes Construction of TIs and Completion of Other Required Construction Work

Government Inspects and Accepts Finished Space 10

AAAP POST-AWARD SCHEDULE, PAGE 2 OF 2 PSA VERSION - REV (10/22)

Total Work Days from Lease Award to Government Acceptance 215