6MA0225 Boston - AAAP Post Award Schedule (1).pdf

PDF 59 KB Posted

Attached to
Lease of Office Space in West Boston / East Worcester, MA - Request for Lease Proposals (RLP) #25REG01 - Office Space
Solicitation number
6MA0225
Issued by

About this file

This is a Post-Award Schedule attachment for an AAAP (Acquire America Act Project) federal lease opportunity that replaces the standard attachment referenced in section 1.05 of the RLP (R100) and applies to section 4.01 of the Lease (L100).

The schedule establishes a 140 working day timeline commencing within 5 working days of lease award for the design and construction process, concluding at government acceptance of the space. The timeline is sequenced as follows: Lessor-Provided Design Intent Drawings (10 days), Government review and approval by GSA and Client (15 days), Lessor preparation and submission of Construction Documents (10 days), Government review of Construction Drawings (5 days), Lessor preparation and submission of TI and BSAC Price Proposal (10 days), Government review, negotiation, and approval of pricing (15 days), Government issuance of Notice to Proceed (5 days), Lessor acquisition of Construction Permit (30 days), Lessor completion of Tenant Improvements and other required construction work (30 days), Government inspection of finished space (5 days), and Lessor punchlist completion with Government acceptance (5 days). This schedule applies specifically to the management of design and construction activities from lease award through final government acceptance of the leased space.

View the file

Other files

File Type Posted
Delineated Area 6MA0225 (2) (1).pdf PDF
POR 6MA0225 (1).xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AAAP Project Specific Advertisement (PSA) Attachment: Post-Award Schedule

This attachment details the post-award schedule for this project. It hereby replaces the Attachment referenced in section

1.05 of the RLP (R100) and should be used when reviewing section 4.01 of the Lease (L100).

The below post-award schedule commences within 5 working days of lease award. The time frames below apply to the management of the design and construction process, concluding at the date of acceptance for the space.

Activity Working Days

Lessor-Provided Design Intent Drawings 10

Government (GSA and Client) Review and Approval of Lessor Provided Design Intent Drawings 15

Lessor Preparation and Submission of Construction Documents 10

Government Review of Construction Drawings 5

Lessor Preparation and Submission of the TI and BSAC Price Proposal 10

Government Reviews, Negotiates, and Approves Pricing 15

Government Issues Notice to Proceed with Construction 5

Lessor Obtains Construction Permit 30

Lessor Completes Construction of TIs and Completion of Other Required Construction Work 30

Government Inspects Finished Space 5

Lessor Completes Punchlist and Government Accepts Finished Space 5

Total Work Days from Lease Award to Government Acceptance 140

AAAP POST-AWARD SCHEDULE, PAGE 1 OF 1 PSA VERSION - REV (10/22)