This is a Statement of Work for the complete replacement of an obsolete Load Moment Indicator (LMI) System on an Appleton Marine crane, model EB190-80-40, serial number 11213, installed aboard the self-propelled crane barge MARY ANN. The project consists of two primary phases: removal of the existing Markload LMI System and installation of a new 24-volt DC system.
The removal phase requires the contractor to strip all existing sensors, junction boxes, cabling, display units, and control unit wiring from the crane. The installation phase requires the contractor to purchase a complete new LMI system from Appleton Marine, Inc., including updated technical and assembly drawings and operation manuals, and engage Appleton Marine Field Engineer support for on-site technical assistance during installation and programming. Following component installation and connection, the contractor must conduct operational testing to the satisfaction of both the Appleton Marine Field Technician and customer, provide OSHA crane inspector services for re-certification, and manage all handling, storage, and disposal of hazardous waste generated during the work in compliance with local, state, and federal regulations at the contractor's expense.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| QandAs 07.30.26.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work
0001.0 Core Services
The Core Services of this project is to replace in its entirety the existing, obsolete Load Moment Indicator (LMI) System on an Appleton Marine crane, model number EB190- 80-40, serial number 11213. The crane was manufactured and installed aboard the self-propelled crane barge MARY ANN in 1999.
0001.1 Removal of Existing System
A. Remove all existing sensors, junction boxes, and cabling pertaining to the obsolete
Markload LMI System from crane.
B. Remove existing Display and Control Unit (Human Interface) and system wiring located in crane cab.
0001.2 Installation of New Load Monitoring System
A. Purchase a new, complete 24-volt DC Load Moment Indicator (LMI) system from the crane manufacturer, Appleton Marine, Inc. Included with the system are updated technical drawings, assembly drawings, and installation and operation manuals.
B. Employ the services of Appleton Marine, Inc to provide on-site technical support for the installation and programming of the LMI system.
C. Install and connect all LMI components as directed by Appleton Marine Field Engineer.
Upon completion of the LMI system installation:
D. Perform operation testing of the LMI system to the satisfaction of the Appleton Marine Field Technician and the customer to recommission the crane.
E. Provide the services of an OSHA crane inspector to re-certify the crane for use.
F. Handling, storage, and disposal of hazardous waste, if any, generated as a result of the work stated above shall be the responsibility of the contractor, as being the generator. Disposal of any hazardous waste shall be at the contractor’s expense and in accordance with all local, state and federal regulations.
| Statement of Work |
| 0001.0 Core Services |
0001.1 Removal of Existing System