6991PE25Q000013 QandAs 09.09.25.pdf

PDF 131 KB Posted

Attached to
SBRF Parking Lot Stormwater Treatment Vault Service and Maintenance
Solicitation number
6991PE25Q000013
Issued by

About this file

This document is a Questions and Answers (Q&As) file for Solicitation Number 6991PE25Q000013 regarding Parking Lot Stormwater Treatment Vault Service and Maintenance. The Q&A addresses a potential vendor's inquiry about the scope of work, specifically confirming the annual cleaning requirements for multiple stormwater infrastructure components. The government's response confirms that the Statement of Work (SOW) requires inspection and maintenance of the media filtration system, with all listed devices (Small Pump Station, Large Pump Station, MFS Cartridge Vault, Retention Trough, and Crescent filter) to be cleaned once per year during the September-October timeframe.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

6991PE25Q000005 Q&As Page 1

Questions and Answers (Q&As) Solicitation Number: 6991PE25Q000013

FOR:

Parking Lot Stormwater Treatment Vault Service and Maintenance

1. Question: I wanted to get clarification on a few items –

You want all these devices CLEANED one time per year:

a. Small Pump Station

b. Large Pump Station

c. MFS Cartridge Vault – cleaned and new cartridge media installed

d. Retention trough

e. Cleaning of Crescent filter inside the trough

Please confirm I have the scope correct. We usually would do INSPECTIONS on some of these devices, but if you want them cleaned, we can do that.

Answer: The Government’s requirement is to inspect and maintain the media filtration system. Yes, the SOW requires that all of the items listed to be cleaned once a year during the September – October timeframe. Refer to the SOW for further details.

**End of Q&As.**