FS-65 Mary Ann DDX Page 1

FS-65 MARY ANN

Drydocking, Grit Blasting, Coating, and Other Repairs

GENERAL INFORMATION and REQUIREMENTS

A. The FS-65 MARY ANN is a craft of the US Navy Yard Salvage Derrick (YSD) type. It is a self-propelled crane barge, displacing approximately 220 tons, length 103 ft., beam 30 ft., draft 4 ft., emergency draft approximately 5.5 ft., and an overall depth of 7 ft.

B. The contractor shall provide all labor, tools, special tools, material, and equipment necessary to make all removals and restorations; remove and replace interference’s; rig and unrig; make all disassembly and subsequent reassembly to accomplish the work specified herein. All work shall be in compliance with the latest Regulatory Body requirements. The term, “Regulatory Bodies” includes the American Bureau of Shipping (ABS), United States Coast Guard (USCG), United States Public Health Service, the Department of Labor (DOL) Occupational Safety and Health Administration (OSHA), and the Institute of Electrical and Electronic Engineers.

C. If, in the performance of any work required in these Specifications, it becomes necessary to remove or disturb any structural part of the vessel, the contractor shall, upon completion of that work, reinstall or renew if necessary any affected structural part and restore to original conditions of durability, appearance, and seaworthiness. All temporary removals in the way of the work shall be replaced in good order.

D. Any and all removed equipment or parts remain the property of the government and are to be left aboard the vessel, or dispose for scrap credit, as directed by the Contracting Officer’s Representative (COR). The contractor shall re-deliver the vessel in the same clean and orderly condition as when received.

E. The term “or equal” following a Brand Name means that components, equipment or material shall be equivalent in terms of performance, services required, compatibility with interrelated systems and arrangements and supportability over the service life of the components or equipment material. Or Equal shall meet salient characteristics given. Contractor shall take full contractual and technical responsibility for ensuring installation of components or equipment or both and take responsibility for the compatibility with interrelated systems. Reference is given to FAR 52.211-6 Brand Names or Equal incorporated within the terms and conditions. Substitutions are a pre-award evaluation. No substitutions are allowed after award, unless approved by the Contracting Officer.

F. The terms “Replace” or “Renew” mean to remove the existing unit, equipment, or systems, including all interferences and to install a new unit, equipment or system which is either identical to or equal to that which was removed; the installation shall include at a minimum all hook-up, supports, and adapters which are required to effect a fully operational installation complete in all respects.

FS-65 Mary Ann DDX Page 2

G. Any repairs or other work resulting from recommendations or other discoveries after the vessel is docked are to be brought to the attention of the COR and CO immediately by use of a contractor generated inspection report. Any such additional work may be subject to a contract delivery order under Supplement Work or a contract modification. Additional work shall be accomplished ONLY WHEN AUTHORIZED IN WRITING WITHIN THE LIMITED DELGATION OF THE

COR OR BY THE CONTRACTING OFFICER.

H. Because this craft is not considered deep-seaworthy, all repair/upgrade work must be performed on this vessel in the San Francisco Bay area, such area to include the up-river areas of Sacramento and Stockton. The craft will be delivered to the contractor’s/sub-contractor’s work site prior to the commencement of work and picked up at the same facility upon completion of work by the Maritime Administration’s Reserve Fleet personnel.

I. The contractor shall gas-free or inert all spaces affected by the work described in this Specification and is responsible for determining all spaces requiring gas freeing. All safety precautions contained in the United States Department of Labor Safety and Health Regulations for Ship Repairing, Title 29 CFR Parts 1501.10, 1501.11, 1501.12, 1501.14, and 1501.15 must be strictly observed. A copy of the gas-free certificate shall be presented to the COR before beginning work on the repairs. Initial Certificates and re-certifications shall be issued by an OSHA Certified Chemist. Gas-Free Certificates shall be updated daily by a Competent Person.

J. All welding shall meet ABS and USCG requirements and conform to American Welding Society (AWS) standards. All welds shall be cleaned prior to painting. All surfaces which have been cut drilled, welded, or otherwise modified shall be cleaned, free of grease, slag and foreign matter;

and painted in accordance with the coating sections of these Specifications. Prior to any production welding contractor shall conduct a joint inspection with the COR for fit-up.

K. The FS-65 MARY ANN was built to US Navy standards, but has been operated as a public vessel by the US Maritime Administration since 1984 as an inland crane and work barge not for hire.

The crane is inspected to FED-OSHA standards. The vessel is not Coast Guard inspected and is not classed by the American Bureau of Shipping. It is the intent of these specifications that working stresses, safety factors, structural arrangements, details and workmanship to be to the same standards as if the vessel was USCG inspected or ABS classed.

L. Contractor shall accomplish all coating processes in accordance with the paint manufacturer’s recommendations (including dry film thicknesses) and under the supervision of the coating manufacturer’s representative. Coating system on the vessel is currently International (AkzoNobel) Paint. Areas of the vessel not intended to be coated shall be protected from overspray.

M. Contractor shall follow Original Equipment Manufacturer (OEM) installation instructions for any new equipment and hardware installed during the execution of this work package.

FS-65 Mary Ann DDX Page 3

STATEMENT OF WORK

1.0 Core Services

The core services of this work package is to drydock or otherwise haul the vessel out of the water, perform surface preparation of the existing coatings, recoat the vessel’s hull and a portion of the main deck, renew all sacrificial anodes, renew the propeller shafts mechanical seals, renew the main engine’s rear oil seals, overhaul the onboard crane, replace the bow bulwark, and other miscellaneous repairs.

1.1 Docking and Undocking

1.1.1 The Government will deliver the vessel under its own power to and from the Contractor’s drydock or synchrolift.

1.1.2 Drydock/haul vessel for inspection, surface preparation, coating and repairs as specified herein. Undock/launch vessel after completion of work specified herein.

1.1.3 Fleet the vessel for access to hull areas obstructed by docking blocks to assure 100% coating coverage on hull bottom.

1.1.4 Provide a docking plan indicating block positions used, location of anodes, keel coolers, and any repairs or modifications made to the hull.

1.2 Hull, Deck and Deckhouse Cleaning and Inspection

1.2.1 Secure all openings into the vessel to prevent the ingress of wash water, including watertight doors, weathertight doors, windows, hatches, vents and port lights.

1.2.2 Remove all anodes on hull, rudders, nozzles and keel coolers. PRIOR TO REMOVING KEEL COOLER ANODES - Test the keel coolers for electrical isolation from the hull with a Simpson 260 series or equal analog VOM, to give the COR an indication of the performance of the keel coolers anode systems. All anodes are aluminum bolt-on type.

1.2.3 Water wash the vessel’s exterior hull, fendering, rudders, main deck, engine house top and bulkheads, Kort nozzles, propellers, propeller shafts and keel coolers, using high-pressure fresh water at a minimum of 3000 PSI to remove dirt, growth and salts. Scrape underwater hull where growth is tightly adhering.

FS-65 Mary Ann DDX Page 4

1.2.4 Examine hull, deck and appurtenances for apparent damage and coating failure.

Submit a written report within two working days detailing conditions found and their location to the COR.

1.2.5 Handling, storage and disposal of hazardous waste, if any, generated as a result of the cleaning operation shall be the responsibility of the contractor, as being the generator.

Disposal of any hazardous waste shall be at the contractor’s expense and in accordance with all local, state and federal regulations.

1.3 Anodes

1.3.1 Hull. Renew twenty bolted anodes as original (AHC-10 aluminum).

1.3.2 Kort Nozzles. Renew four bolted anodes per nozzle as original (AHC-11 aluminum).

1.3.3 Rudders. Renew two bolted aluminum anodes per rudder, one per side, as original. Size/weight of last installed unknown.

1.3.4 Propeller Shafts. Renew three clamp-on collar type anodes per shaft as original (aluminum, for 4” diameter Aquamet stainless steel shafts).

1.3.5 Keel Coolers. Renew seventeen bolted anodes as original:

• Eight ea. AHS-37 aluminum anodes per main engine keel cooler.

• One ea. AHS-20 aluminum anode for the generator keel cooler.

• Inspect copper bonding straps, strap covering and insulators for damage.

• Test the keel coolers for electrical isolation from the hull again after anode renewal. Prove to COR by testing with a Simpson 260 series or equal analog Volt-Ohm Meter.

1.3.6 Install anodes after all coatings have been applied and sufficiently cured.

1.4 Underwater Hull Surface Preparation

1.4.1 Prior to surface preparation, mask and protect all openings to the vessel hull and interior to prevent the ingress of dust and contaminants arising from surface preparation. Rubber fendering is to remain secured to the vessel’s hull and not be

FS-65 Mary Ann DDX Page 5 removed. Contractor is responsible for removal of any dust and contaminants from the crane and within the vessel generated by surface preparation.

1.4.2 Make notations of all hull markings to assure their replacement after the painting process.

1.4.3 Rotary nozzle pressure wash (Rotowash) the underwater hull to remove any loose paint and to roughen up the existing coating surface in preparation for recoating. Do not remove intact coating.

1.4.4 Upon completion of Rotowashing, conduct a visual inspection of the underwater hull and provide a report of conditions found within two working days, including any recommended actions for repair.

1.4.5 Spot bare metal power tool clean to SSPC-SP 11 any areas that are showing active corrosion, pitting or loose paint. Feather back intact paint where adjacent to bare metal.

For bidding purposes, assume 20% of the total square footage of the underwater hull in scattered areas will require SP 11 and feathering.

Proper handling, storage and disposal of any hazardous waste generated as a result of the surface preparation operation shall be the responsibility of the contractor. Disposal of any hazardous waste shall be at the contractor’s expense and in accordance with all local, state and federal regulations.

1.5 Freeboard Surface Preparation

1.5.1 Abrade the freeboard coating to remove any loose paint and to roughen up the existing coating surface in preparation for recoating. Do not remove intact coating.

1.5.2 Spot bare metal power tool clean to SSPC-SP 11 any areas that are showing active corrosion, pitting or loose paint. Feather back intact paint where adjacent to bare metal.

For bidding purposes, assume 20% of the total square footage of the freeboard in scattered areas will require SP 11 and feathering.

1.6 Main Deck Surface Preparation

FS-65 Mary Ann DDX Page 6

1.6.1 Rotowash the main deck from the forwardbulkhead of the engine house (Frame (FR) 7) to the bow to remove any loose paint and to roughen up the existing coating surface in preparation for recoating. Do not remove intact coating.

1.6.2 Power tool clean to bare metal SSPC-SP 11 all main deck areas forwardof the engine house showing active corrosion, pitting or coating damage. Power tool clean to SSPC-SP 3 the four clover-leaf tie-down fittings. Feather back intact paint where adjacent to bare metal. For bidding purposes, assume a total of 10% of the forwardmain deck area will require SP 11 and feathering.

1.6.3 Open flush deck hatch to ballast chain hold and power tool clean the hatch gutter to SSPC-SP 3. Prove gutter drain piping overboard free and clear.

1.7 Coatings

1.7.1 Underwater Hull

• Apply two spot coats of Intershield 300V or equal to areas prepared to SP 11.

Alternate colors to assure coverage.

• Apply one spot coat of Interspeed 6400NA or equal to the underwater areas spot coated above.

• Apply two full coats of Interspeed 6400NA or equal, first coat Black, last coat

Red.

1.7.2 Freeboard

• Apply two spot coats of Intershield 300V or equal to areas prepared to SP 11.

• Apply one spot coat of Interthane 990HS or equal to the freeboard areas spot coated above.

• Apply one full coat of Interthane 990HS or equal, Black.

• Paint in draft marks, hull number and vessel name with two coats of Interthane

990HS or equal, White.

1.7.3 Main Deck, Forward of the Engine House Bulkhead Only

• Apply two spot coats of Intershield 300V or equal.

• Mask the non-skid margin around the forward engine room bulkhead, main deck perimeter, hatches and manhole covers as original.

• Apply a third spot coat to the non-skid area, and while still wet, uniformly broadcast aluminum oxide abrasive.

• Apply one full coat of Interthane 990HS or equal, Deck Gray.

FS-65 Mary Ann DDX Page 7

1.8 Propellers, Nozzles, Shafts, and Bearings

1.8.1 Inspect port and starboard (stbd) propellers, Kort nozzles, shafts and bearings for damage and probable cause. Provide a report of all findings.

1.8.2 Measure clearances in both strut and stern tube bearings and provide a report of findings.

1.8.3 Remove propellers. Inspect and provide a report of findings. Polish and reinstall.

If balancing is required, this will be the subject of a change order.

1.9 Rudders

1.9.1 Measure rudder bearing clearances and provide a report of findings.

1.9.2 Remove rudders and packing. Note: tillers are secured to the rudder shafts with double-stacked set screws. Inspect and clean rudder shafts, bearings, packing, tillers and tie rod, including all ball joints. Provide a report of findings.

1.9.3 Reinstall rudders. Tighten all set screws securing tillers to rudder shafts. Note that set screws are to be double-stacked.

1.9.4 Repack both rudder packing glands. Grease with an approved Environmentally Acceptable Lubricant (EAL) product.

1.10 Propeller Shaft Cathodic Protection System

1.10.1 Uninstall the port and stbd Electro-Guard propeller shaft slip ring assemblies prior to renewal of the mechanical seals specified in 1.11 below.

1.10.2 After reinstallation of the shaft seals, shaft couplings, transmissions, and re-coupling of the transmission-to-propeller shaft couplings, reinstall the shaft slip ring assemblies according to the manufacturer’s instructions. Check the silver slip rings for wear. Polish slip rings. Replace brushes. Check clearances, then check and tighten all electrical and mechanical connections. Manufacturer:

Electro-Guard, Inc.

(530) 926-4000 Email: tsupport@boatcorrosion.com mailto:tsupport@boatcorrosion.com

FS-65 Mary Ann DDX Page 8

1.11 Propeller Shaft Mechanical Seals

1.11.1 Renew both port and stbd 4-inch diameter propeller shaft mechanical seal assemblies with Duramax Model DXU 4000 BRZ water-lubricated shaft seals as original.

Disconnect and reconnect cooling/lubrication water plumbing.

1.12 Main Engines Rear Oil Seal Renewal

1.12.1 Disconnect the port and stbd transmission-to-propeller shaft couplings and back the propeller shafts aft far enough to remove the transmissions.

1.12.2 Remove the port and stbd transmissions and rig aside. Provide inside rigging assistance as necessary.

1.12.3 Obtain the services of Cummins Inc. to renew the rear crankshaft oil seals in both engines. Note: Cummins will need at least two weeks advanced notice to schedule their technician(s) to attend the vessel and perform the seal renewal.

1.12.4 Reassemble transmissions to engines. Provide inside rigging assistance as necessary.

1.12.5 Reassemble transmission-to-shaft couplings.

1.12.6 Jack the engines over by hand to check coupling runout and provide report to

COR.

1.12.7 Provide two mechanics and Cummins Inc. technician(s) to perform a sea trial for up to two hours with the vessel’s crew to prove proper operation of the engines, transmissions and new shaft seals.

Engine and Transmission details:

Serial Number FS-65 MARY ANN Manufacturer Model # Port Stbd Main Engines Cummins QSK19-M-T3 37260581 37260582 Transmissions Twin Disc MG-5202 SC 2129618 2129619

FS-65 Mary Ann DDX Page 9

1.13 Appleton Crane Repairs (model number EB190-80-40, serial number 11213)

1.13.1 Crane Hydraulic System.

• Completely drain the crane hydraulic system, including but not limited to the hydraulic oil tank, hydraulic pump, directional control valves, manifold, piping, hoses and cylinders.

• Clean the hydraulic tank and renew filters with Government Furnished Material

(GFM).

• Renew the directional control valves with GFM.

• Renew boom luff cylinder with GFM.

• Renew boom extend/retract cylinders with GFM.

• Renew all cylinder pins and lock plates with GFM.

• Renew all stainless-steel tubing and fittings inside the boom to the boom cylinders.

• Renew all hydraulic hoses. Return replaced hoses to owner.

• Renew all eight boom slide pucks with GFM.

• Renew the cable track with GFM.

• After installation of the new boom cylinders, refill the system with AW 46 PC:

230341 PK: 981 EAL hydraulic oil.

• Test crane for proper operation. Test the entire system for leaks, and repair as necessary.

1.13.2 Crane Boom

• While the boom is disassembled and cylinders removed, clean all grease and oil from the extendible boom, inside and out.

• Abrade the boom sections’ coatings to remove any loose paint and to roughen up the existing coating surface in preparation for recoating. Do not remove intact coating.

• Spot bare metal power tool clean to SSPC-SP 11 any areas that are showing active corrosion, pitting or loose paint. Feather back intact paint where adjacent to bare metal. For bidding purposes, assume 20% of the total square footage of the boom sections in scattered areas will require SP 11 and feathering.

• Apply two spot coats of Intershield 300V or equal to areas prepared to SP 11.

• Apply two full coats of Interthane 990HS or equal, White. Do not coat over the

“Appleton” name or logos.

FS-65 Mary Ann DDX Page 10

1.13.3 Provide the services of a qualified Fed/OSHA maritime crane inspector and test the crane for quadriennial certification.

1.14 Rebuild the Luff Cylinder, and Extend/Retract Cylinders. (OPTIONAL)

1.14.1 Rebuild the luff and extend/retract cylinders for the Owner to keep as spares.

1.14.2 Test for proper operation and no leakage.

1.14.3 When complete, retract all cylinders and fill with hydraulic oil as a preservative.

1.14.4 Clean and recoat painted surfaces, and coat exposed metal and seals with a preservative.

1.14.5 Crate the cylinders for storage.

1.14.6 Deliver to the owner’s warehouse at Alameda Point for storage.

1.15 Cylinder Pins (OPTIONAL)

• Inspect all hydraulic cylinder pins that were replaced and determine if they are still serviceable to be kept as spares. Deliver pins to Owner.

1.16 Bow Bulwark Replacement

1.16.1 Crop out existing bulwark, supporting gussets, and bulwark fendering on the bow of the vessel. Leave stem piece in place. Grind all cut areas smooth.

1.16.2 Renew the bulwark to original dimensions using 5/16” steel plate. Substitute shaped steel gussets for the original flat steel gussets. Align gusseting with the vessel’s framing as much as possible. Install new 2 ½” SCH 80 pipe trim on top.

• The closed chock on the stbd side is not to be reinstalled. Chock is no longer required.

1.16.3 Install new 10” D black rubber fendering to the outer surfaces in similar fashion to that fendering on the rest of the vessel, coming to a blunt point on the bow as original. This new fendering will extend further aft than the original. Total length of fendering on the bow bulwark to be 10 ft 9 in port and stbd.

FS-65 Mary Ann DDX Page 11

1.16.4 Prior to installing the new fendering, coat the inboard and outboard of the new bulwark, gussets, and adjacent areas where coating was disturbed by cutting and welding with:

o Two full coats of Intershield 300V or equal.

o Two full coats of Interthane 990HS or equal, Black

1.17 Weep Hole Doubling, Engine Room Port Side

There is a weep hole at the turn of the bilge in the bulkhead that separates the Engine Room from the Void space aft (FR 9 ½).

1.17.1 Install a small doubler over the weep hole to restore the watertight integrity of this bulkhead.

1.17.2 Coat new and disturbed areas with two full coats of Intershield 300V or equal, Red, in the Engine Room and Void.

1.18 Additional Windshield Wipers, Wheelhouse Front Windows

Three of the five front windows in the Wheelhouse have windshield wipers.

1.18.1 Install two additional W12 wiper motors, wiper arms and blades matching the original Imtra Marine Products, Coastal Plus Wiper Systems units installed in 2015 for the windows without wipers.

1.18.2 Provide and install wiring and switches for both new wipers.

1.18.3 Test for proper operation to the satisfaction of the COR.

1.19 Broken 4-Inch Gooseneck Vent

1.19.1 Reinstall the broken off 4-inch gooseneck vent pipe on the port side serving the Forward Hold, just forward of FR 2.

1.19.2 Coat with two full coats of Intershield 300V or equal, Black.

1.20 Anchor and Chain

FS-65 Mary Ann DDX Page 12

1.20.1 Remove the vessel’s anchor and chain. There is only about ten feet of chain connected to anchor.

1.20.2 Abrasive grit blast the anchor and chain to SSPC-SP 6.

1.20.3 Coat anchor and chain with two full coats of Intershield 300V or equal, and one full coat of Interthane 990HS or equal, Black.

1.20.4 Reinstall anchor and chain after completion of topside coatings specified in 1.7.2.

1.21 Ballast Chain Hold

1.21.1 Open the flush deck hatch on the main deck to ballast chain hold (FR 3 – FR 5).

1.21.2 Pump out water that has accumulated. Expect approximately two to three inches of water in the aft section of the hold.

1.21.3 Dry out the hold by circulating warm air throughout hold with a heater-fan.

2.0 Supplemental Work

The Contractor shall provide additional labor and materials, if requested by the Government, to address any emergent work which may arise throughout the contract period. These supplemental requirements shall be identified by a “Request for Pricing” issued by the COR or by a “Condition Found Report” issued by the Contractor. If a fair and equitable price can be agreed upon by both parties to perform the supplemental work, the COR and/or Contracting Officer (CO) may issue a Delivery Order to the Contractor which authorizes the Contractor to perform that work.

The total amount of Supplemental Labor and Materials/Subcontractor labor/services ordered shall be at the discretion of the COR and/or CO.

2.1 Supplemental Labor

Supplemental Labor is considered labor performed by direct employees of the Contractor. (It does not include subcontracted labor/services). The Government has estimated a not to exceed of 300 supplemental labor hours for this service. The Contractor shall propose a fully burdened hourly yard-wide labor rate to perform supplemental labor. This rate shall be applicable 24

FS-65 Mary Ann DDX Page 13 hours per day, seven (7) days per week and shall not be increased for overtime or penalty time and will be utilized in negotiating a fixed price Delivery Order for subsequent supplemental labor.

2.2 Supplemental Material/Subcontractor Requirements

Supplemental Material/Subcontractor Requirements are materials and/or subcontracted labor or services which either the Contractor or the Government requires. The Government has provided a not to exceed amount of $10,000.00 for supplemental materials. All costs for supplemental materials and supplemental subcontracted labor/services shall be a pass-through cost without any markup by the Contractor. (Note: Labor which the Contractor provides, using their own personnel, to procure and deliver supplemental materials aboard the ship or in support of subcontracted labor/services, is considered Supplemental Labor). All supplemental material and supplemental subcontracted labor/services which exceed $200.00 shall be supported by hard copies of vendor quotations, paid invoices and/or receipts, if requested by the COR.

File details come from the government source that posted it. Updated .