Questions Answers NV FLAP WAS CR34(1) Geotechnical Drilling 06 01 2026.pdf
PDF 60 KB Posted
- Solicitation number
- 6982AF26Q000011
About this file
This is a Questions and Answers document for federal contract opportunity 6982AF26Q000011, issued June 1, 2026, concerning NV FLAP WAS CR34(1) Geotechnical Drilling services.
The document addresses two inquiries received on May 28, 2026. The first question clarifies drilling methodology, specifically whether drill crews must core asphalt using a core machine prior to drilling with a 6-inch outside diameter (OD) auger, or if direct auger penetration is acceptable. The contracting officer confirmed that pre-coring is not required and that the 6-inch OD auger should drill directly through existing asphalt without pre-coring. The second question requests clarification regarding labor hours, with a bidder noting that the advertised allocation of one day up to 10 hours may be insufficient given the number of borings and mobilization time between locations, and requesting permission to adjust the bid sheet to 30 hours. The contracting officer rejected this request, directing bidders to submit bids as advertised with the original 10-hour allocation. This document provides binding clarification on contract requirements for prospective bidders.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFQ 6982AF26Q000011 DrillingNV FLAP WAS CR34(1) County Road 34.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
6982AF26Q000011
NV FLAP WAS CR34(1) Geotechnical Drilling June 1, 2026
Questions Answer
Received May 28, 2026
1. Will the drill crew be required to core the asphalt, with a core machine, before drilling with 6” OD auger, or would the drill crew be allowed to penetrate the asphalt with the auger?
No, the 6" OD auger to drill through the existing asphalt without pre-coring
2. I see in the request that 1 day, up to 10 hrs has been allotted for this project. I am thinking given the number of borings, and time to move to each boring this might end up taking 2 to 3 days to complete. Would it be okay to adjust the quantity of hours on the bid sheet to 30?
No, bid as advertised.