Amendment A001 Cedar Tree.pdf
PDF 1 MB Posted
- Solicitation number
- 6982AF25B000024
About this file
This document is an Amendment (A001) to a federal highway construction contract for the Cedar Tree Tower Road and Parking project at Mesa Verde National Park, issued by the Federal Highway Administration's Central Federal Lands Highway Division. The amendment modifies various sections of the original solicitation, including updates to physical data, product certification, contract time, and multiple technical specifications across sections such as excavation, materials testing, soil erosion control, and culvert lining.
Key modifications include changes to survey and staking requirements, implementation of a Stormwater Pollution Prevention Plan, detailed specifications for Cured-In-Place Pipe (CIPP) culvert lining, tribal and archaeological monitoring protocols, and specific requirements for materials like concrete, aggregates, and seed mixes. The project involves road and parking improvements across multiple routes within Mesa Verde National Park, with a completion date of October 30, 2026. The amendment provides comprehensive technical guidance for construction methods, material specifications, environmental protections, and cultural resource preservation throughout the project.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
2. AMENDMENT/MODIFICATION NUMBER
A001
*FAILURE TO ACKNOWLEDGE THIS AMENDMENT IN BLOCK 19 OF THE SF 1442 BY THE DESIGNATED DATE AND HOUR SPECIFIED IN THE SOLICITATION MAY RESULT IN REJECTION OF YOUR BID (REFER TO ITEM 11.)
FEDERAL HIGHWAY ADMINISTRATION
CENTRAL FEDERAL LANDS HIGHWAY DIVISION
12300 WEST DAKOTA AVENUE, SUITE 360
LAKEWOOD, COLORADO 80228
ATTENTION: DENISE MARTINEZ
9A. AMENDMENT OF SOLICITATION NUMBER
6982AF25B000024
5. PROJECT NUMBER (If applicable)
CO NP MEVE 201(1)
10/30/2025
9B. DATED (SEE ITEM 11)
10/14/2025
0*
*See Item 14
X
SCR'S:
Remove and replace all E sheets (delete 59 pages/replace 56 pages). All updates in red include Sections 102A Physical Data; 106.03(b) Product certification, 108.01 Commencement, Prosecution, and Completion of Work & 108.04 Determination and Extension of Contract Time, 108.04(c) Time extensions, 109.06 Pricing of Adjustments and 152.04 General.
E-1
CO NP MEVE 201(1)
Cedar Tree Tower Road and Parking
PMIS 259055
SPECIAL CONTRACT REQUIREMENTS
The following Special Contract Requirements amend and supplement the Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects (FP-24), U.S. Department of Transportation, Federal Highway Administration.
35760
10/28/2025
AMENDMENT A001 10/30/2025
E-2
Cedar Tree Tower Road and Parking
PMIS 259055
Section 101. — TERMS, FORMAT, AND DEFINITIONS
101.03 Abbreviations. Add the following:
CDR – Contractor’s Daily Record
CIPP – Cured in Place Pipe
PLS – Pure Live Seed
VNS – Variety Not Specified
101.04 Definitions. Delete the definition of (c) Supplemental agreement under Contract
Modification.
101.04 Definitions. Add the following:
Masterworks — A web-based system used by the Government, Contractors, and Subcontractors on this Government contract to prepare Contractor Daily Inspection Reports (CDRs) and measurement notes (pay notes and field measurement documentation).
Tribal Monitor – A person designated by the tribes to serve as a representative to observe construction activities for the purpose of identifying and protecting tribal resources and making recommendations to the government.
Section 102. — BID, AWARD, AND EXECUTION OF CONTRACT
102.02A Physical Data. (Added Subsection).
Data and information furnished or referred to below is for the Contractor's information. The
Government is not responsible for any interpretation of, or conclusion drawn from the data or information by the Contractor.
(a) The indications of physical conditions on the drawings and in the specifications are the result of site investigations by:
(1) Non Available
(b) Weather conditions: Contact the National Weather Service.
(c) The following vertical and horizontal survey control points is applicable to this project and posted on https://sam.gov/:
E-3
Cedar Tree Tower Road and Parking
PMIS 259055
(1) RTE 0200 Wetherill Mesa Road
(2) RTE 0205 Cedar Tree Tower Road
(3) RTE 0210 Far View Ruins (Sites) Road
(4) RTE 0404 Far View Residence Road
(5) RTE 0912AZ Far View Terrace Parking A
(6) RTE 0912BZ Far View Terrace Parking B (Loading Dock)
(7) RTE 0918 Visitor Center Parking (Far View Center Parking Lot)
(8) RTE 0925 Side Headquarters and Post Office Parking
(9) RTE 0409A Stone House Road A
(10) RTE 0409A Stone House Road B
(d) The following design data is applicable to this project and posted on https://sam.gov/:
(1) Horizontal alignment listings in Portable Document Format (pdf) and
LandXML (.xml) formats; for all routes
(2) 3D surfaces of existing ground, subgrade, finished grade, and top of base course in LandXML (xml) format; for RTE 0205 Cedar Tree
Tower Road and RTE 0210 Far View Ruins (Sites) Road only.
(3) Proposed 3D breaklines in Drawing Exchange Format (dxf); for RTE
0205 Cedar Tree Tower Road and RTE 0210 Far View Ruins (Sites)
Road only.
(4) 3D coordinates and offset distance from centerline for subgrade and slope staking information and top of base course information at 50-foot
(20-meter) intervals and miscellaneous intermediate stations in Portable
Document Format (.pdf); for RTE 0205 Cedar Tree Tower Road and
RTE 0210 Far View Ruins (Sites) Road only.
(5) Earthwork quantity summary in Portable Document Format (pdf). for
RTE 0205 Cedar Tree Tower Road and RTE 0210 Far View Ruins
(Sites) Road only.
Section 104. — CONTROL OF WORK
104.04 Electronic Documentation. Delete this Subsection and substitute the following:
E-4
Provide documents and drawings electronically using Masterworks.
Request the Masterworks User Account Form (Form Masterworks-001) and submission instructions. Complete and electronically submit Form Masterworks-001 for each individual requiring Masterworks access. Allow 7 days for system access.
Contact the CO to schedule a training session on the use of Masterworks. The virtual training session will be either a video presentation or live training as determined by the CO. The Contractor is responsible for training additional staff that were not present during the original training session.
Maintain active Masterworks accounts for all Contractor staff who use Masterworks. Notify the
CO within 24 hours after an account holder is reassigned or no longer employed by the Contractor and submit a Form Masterworks-001 requesting their account be disabled.
Provide documents and drawings in their native file format (the format produced by the software that the document and drawing was created in) upon request.
Documents and drawings include but are not limited to correspondence, submittals, measurement notes, reports, plans, diagrams, qualifications, certifications, payrolls, schedules, invoices, mix designs, job-mix formulas, test results, notifications, requests, permits, and agreements.
Provide a resolution quality with color, text, and lines clearly discernible. Submit each document and drawing in an individual file. Name files with a unique document name.
Documents and drawings delivered after 5:00 pm local time will be considered received on the next business day.
The CO will reject documents that are unreadable, corrupted, illegible, or include malicious content.
104.08 Load Restrictions. Delete the second sentence of the third paragraph.
Section 105. — CONTROL OF MATERIAL
105.01 Source of Supply and Quality Requirements. Add the following:
Materials containing petroleum-based solvents such as cutback asphalts and traffic paints may be restricted from use by local laws or ordinances in certain geographic areas. Upon presenting proof of such restrictions, alternate materials considered acceptable to the CO may be substituted for the materials specified in the contract.
Certify, according to Subsection 107.10(d), that sources of rock, sand, gravel, earth, subsoil, or other natural material imported into the project construction limits are noxious weed free.
Cover all loads transported to, from and within Mesa Verde National Park.
E-5
Mesa Verde National Park will allow the contractor to use 10,000 gallons of water per day from the park for the duration of the project. Use a Backflow preventer or air gap when using water.
105.04 Handling and Storing Material. Add the following after the second paragraph:
For Contractor-located, non-commercial staging, storing, and material handling areas, secure environmental clearances according to Subsection 107.10.
Add the following:
The Contractor may use the following staging areas. Each route may be closed for the duration of construction on each route except for RTE 0912AZ Far View Terrace Parking A, which must remain partially open to maintain access to the Far View Terrace Café and Gift Shop. Up to 4 routes may be closed concurrently.
• The Contractor may use the area around the Morefield sand shed for staging for Route
0010 (Main) Entrance Road. Coordinate exact location with the CO. Additional staging areas for the lagging wall repairs are identified in the plans.
• The Contractor may use the project area at Route 0912AZ Far View Terrace Parking A for staging for Routes 0912AZ Far View Terrace Parking A, 0912BZ Far View Terrace
Parking B (Loading Dock), Route 0200 Wetherill Mesa Road and Route 0404 Far View
Residence Road. Maintain access to the café and gift shop accessed by Route 0912AZ during staging and construction.
• The Contractor may use the project area at Route 0205 Cedar Tree Tower Road and Route
0210 Far View Ruins (Sites) Road for each of their respective staging areas.
• The Contractor may use Route 0918 Visitor Center Parking (Far View Center Parking Lot) for its own staging area.
• The Contractor may use the overflow lot and Route 0409A Stone House Road A and Route
0409B Stone House Road B for staging of those routes.
• The Contractor may use the southern area of the overflow parking lot for staging of Route
0925 Side Headquarters and Post Office Parking.
Keep staging contained to previously disturbed areas according to section 107.10(e)(6) unless previously approved by the CO to limit disturbance to archeological areas throughout the park.
FHWA CFL has an office trailer on-site in the Chapin Mesa Maintenance Yard that may be used for office space.
Use products according to the manufacturer’s recommendations for handling, storage, and disposal. Follow the requirements of FAR Clause 52.236-10 Operations and Storage Areas and
E-6
FAR Clause 52.236-12 Cleaning Up. Maintain the staging and storage areas in a clean, neat, and orderly condition.
Store construction, building and waste materials, and containers in designated areas indoors or protect with suitable covering.
Keep the manufacturer’s SDS, an inventory of the material, and emergency numbers near the storage area. Take appropriate measures to ensure that incompatible chemicals are not stored next to each other.
Store construction materials within the limits shown in the plans. Properly store materials according to the applicable permit. Check the storage areas weekly and according to the applicable permit.
Submit a site map showing the material storage and stockpile locations at least 14 days before the start of construction activities.
Continually monitor dirt piles for the presence of invasive weeds. Weeds should be treated immediately if found. Herbicides and their application must be approved by the CO. Allow up to
30 days for herbicide use to go through the approval process.
Section 106. — ACCEPTANCE OF WORK
106.01 Conformity with Contract Requirements. Add the following:
If the accuracy of Government test results is disputed, inform the CO. If the dispute is unresolved after reasonable steps are taken to resolve the dispute, further evaluation may be obtained by written request.
Where sample and testing procedures refer to AASHTO, ASTM, or other standards (designated as
FLH T), use the procedure as modified in the FLH Field Materials Manual.
Where the specifications refer to AASHTO T 11, follow “Procedure B - Washing Using a Wetting
Agent”.
Where the specifications refer to AASHTO T 310, follow the “Direct Transmission Method of In-
Place Nuclear Density and Moisture Content”.
106.03 Certification. Delete the third paragraph and substitute the following:
See Table 106-3 for schedule for full or partial acceptance by material certification. Submit certification and sample of material for testing as required.
E-7
Check certifications before incorporating the material into the work to ensure that the requirements of the contract have been met. Mark the certifications with the following information: project number and name; pay item number and description; date; and Contractor-signed certification stating “to the best of our knowledge the materials certified by the attached certification represent the materials incorporated into the work of this contract”.
Table 106-3
Schedule For Full or Partial Acceptance by Materials Certification
Section Description Material Material Property
Or Specification
Certification
Frequency
Sample
Frequency
Crushed
Aggregate Crushed aggregate
Source, quality and gradation 1 per source 1 per source
312 Dust Palliative
Calcium chloride magnesium chloride, lignosulfonate
As specified 1 per shipment First shipment
403 Asphalt Concrete Aggregate asphalt mix
Source quality, gradation, stability, and grade
1 per mix 1 per source
634 and
Permanent
Pavement
Markings, Temporary Traffic
Control
634.02 as applicable, 635 as applicable
As specified 1 per source −
Cementitious
Material
Portland cement, blended hydraulic cement, mortar cement
AASHTO M 85, M
240, ASTM C91 and
ASTM C1392 as applicable
1 per shipment 1 per 100 tons
702.01 Asphalt Binder Asphalt cement
AASHTO M 226
or M 320, as applicable
1 per shipment 1 per shipment
702.02 Emulsified
Asphalt Emulsified asphalt
AASHTO M 140
or
M 208 as applicable
1 per shipment 1 per shipment
702.05 Antistrip Additive As specified As applicable 1 per shipment −
706 Concrete Pipe As specified As applicable 1 per shipment −
707 Metal Pipe As specified As applicable 1 per shipment −
708 Plastic Pipe As specified As applicable 1 per shipment −
E-8
Section Description Material Material Property
Or Specification
Certification
Frequency
Sample
Frequency
Reinforcing Steel and Wire Rope As specified As applicable 1 per shipment
For 709.01 submit 3, 1-yard bars of each size and grade of bar furnished.
For 709.02 submit 1
6-foot length for each size furnished
Fencing and Mesh
Fabrics As specified As applicable 1 per shipment −
Concrete Curing
Material and
Additives
As specified As applicable
1 per material source per material type
712 Joint Material As specified As applicable 1 per shipment −
Roadside
Improvement
Material
As specified As applicable 1 per shipment −
Geosynthetic
Material As specified As applicable 1 per shipment
1 per project per type
715 Piling As specified As applicable 1 per shipment −
Material for
Timber Structures
Timber and hardware As applicable 1 per shipment −
717 Structural Metal As specified As applicable 1 per shipment
For 717.01(e) minimum
6 per shipment for each size used.
For 717.09
1 per project
Traffic Signing and Marking
Material
As specified As applicable 1 per shipment −
719 Coating Material As specified As applicable 1 per batch\lot
1 sample for quantities
> 25 gallons
Structural Wall and Stabilized
Embankment
Material
As specified As applicable
1 per shipment per material type
Electrical and
Illumination
Material
As specified As applicable
1 per shipment per material type
722 Anchor Material As specified As applicable
1 per shipment per material type
E-9
Section Description Material Material Property
Or Specification
Certification
Frequency
Sample
Frequency
Dampproofing and
Waterproofing
Material
Asphalt materials used for damproofing and waterproofing concrete and masonry surfaces
As specified for each type of asphalt material
1 per shipment −
724 Guardrail As specified As applicable 1 per shipment −
Miscellaneous
Material As specified As applicable
1 per shipment per material type
106.03(b) Production certification. Delete subsection (3) and substitute the following:
(3) Substantiating evidence that the material conforms to the contract quality requirements, including the following:
(a) Test results on material from the same lot and documentation of the inspection and testing system;
(b) A statement from the manufacturer that the material complies with the contract; and
(c) Manufacturer’s signature or other means of demonstrating accountability for the certification.
Section 107. — LEGAL RELATIONS
AND RESPONSIBILITY TO THE PUBLIC
107.01 Laws to be Observed. Add the following:
(b) National Pollutant Discharge Elimination System (NPDES). Comply with the requirements of the applicable Construction General Permit (CGP) as shown in Table 107-1.
The applicable CGP is Colorado.
Prepare a Stormwater Pollution Prevention Plan (SWPPP) according to Section 157. If the current CGP expires during the contract, amend the SWPPP when a new permit goes into effect to meet new permit conditions.
Obtain a separate NPDES permit associated with industrial activity for mobile asphalt and concrete plants that provide material for the project. Provide a copy of the permit and acknowledgement letter to the CO.
E-10
(1) Notice of Intent (NOI). After the SWPPP is approved, file the NOI according to the applicable CGP as shown in Table 107-1. Allow the regulatory review period, shown in
Table 107-1, from submittal of NOI to receipt of authorization of coverage under the CGP.
Provide a copy of the NOI and confirmation letter to the CO.
Post all project authorization numbers near the entrance to the site and on the bulletin board.
(2) Payment of permit fees. Submit the appropriate permit fees and renewal fees required for both the Contractor and Government to the regulatory agency.
(3) Notice of Termination (NOT). If applicable, file a NOT when the conditions listed in the CGP have been met or transfer the NOI to the maintaining agency after final acceptance.
Table 107-1
NPDES Permits
State / Agency Permit Number and Link Effective Date Expiration Date
Regulatory
Review Period
Arizona AZG2020-001 7/1/2020 6/30/2025 30 days
California(1) 2022-0057-DWQ 9/1/2023 8/31/2028 7 days
Colorado
(Federal) COR10F000 2/17/2022 2/16/2027 14 days
Colorado
(Other) COR400000 4/1/2024 03/31/2029 10 days
Hawaii
HAR 11-55,
Appendix C
1/29/2024 1/29/2029 10 days
Indian Country XXR10I000 2/17/2022 2/16/2027 14 days
Kansas S-MCST-2208-1 12/1/2021 11/30/2026 60 days
Nebraska NER210000 12/1/2021 11/30/2026 7 days
Nevada NVR100000 1/5/2015 1/4/2020(2) 14 days
New Mexico NMR100000 2/17/2022 2/16/2027 14 days
North Dakota NDR11-0000 4/1/2020 3/31/2025 7 days
Oklahoma OKR10 10/18/2022 10/17/2027 14 days(3)
South Dakota SDR100000 11/1/2023 10/31/2028 15 days
Texas (Small)(4) TXR150000 3/5/2023 3/5/2028 2 days
Texas (Large) TXR150000 3/5/2023 3/5/2028 7 days
Utah UTRC00000 07/1/2024 06/30/2029 None
Wyoming
(Small)(5) WYR10-A000 9/11/2020 8/1/2025 None
Wyoming
(Large) WYR100000 9/11/2020 8/1/2025 10 days
E-11
(1) Upload the SWPPP to the California Water Boards Stormwater Multiple Application and Report Tracking
System (SMARTS) and complete the NOI application previously started by the Government. Notify the CO once the NOI application is complete. Do not certify the NOI.
(2) Permit administratively extended.
(3) 45 days for projects over 40 acres or in a sensitive watershed.
(4) Prepare a Construction Site Notice rather than an NOI.
(5) Prepare a SWPPP rather than an NOI. Implement the SWPPP before ground disturbing activities.
107.02(d) Utilities. Add the following:
The locations of the utilities shown in the plans have been certified to a Quality Level D according to the CFLHD Utility Data Quality Certification requirements available at https://highways.dot.gov/federal-lands/rw-util/cfl.
Table 107-2
Status of Utilities(1)
Company Utility Type
Contact
Name Phone Number
Status
1, 2, 3, or 4
1 Empire Electric Primary Electric Ana Jimenez (970)-565-4444 4
Communication
(Fiber Optic)
Lumen Technologies Cynthia
Horton
(571)-730-6431 4
3 NPS Secondary Electric Brandon Bell (970) 529-5092 4
4 NPS Sewer Brandon Bell (970) 529-5092 4
5 NPS Gas Brandon Bell (970) 529-5092 4
6 NPS Water Brandon Bell (970) 529-5092 4
Status is defined as follows:
Status 1: The utilities are in conflict with the project and require relocation by others during construction.
Status 2: The utilities are in conflict with the project and require relocation or adjustment by the Contractor during construction.
Status 3: The utilities are in conflict with the project and require relocation by others before construction.
Status 4: The utilities are located within the project right-of-way but require no relocation.
107.05 Responsibility for Damage Claims. Delete the first sentence of the third paragraph and substitute the following:
Before work starts, submit “certificates of insurance” certifying that the policies will not be changed or canceled until 30 days’ written notice has been given to the Government.
107.08 Sanitation, Health, and Safety. Delete the first paragraph and substitute the following:
Follow the requirements of FAR Clause 52.236-13 Accident Prevention, Alternate 1. Submit an accident prevention plan.
E-12
107.10(a) Federal Water Pollution Control Act (Clean Water Act) 33 USC § 1251 et seq. Add the following:
(4) Do not ford running streams with construction equipment. Obtain approval from the
CO to use temporary bridges or other structures whenever crossings are necessary.
(5) Locate machinery servicing and refueling areas away from streambanks, wetlands, shorelines, lakes, and reservoirs to reduce the possibility and minimize the impacts of accidental spills or discharges.
107.10(b) Oil and hazardous substances. Delete the third and fourth paragraphs and substitute the following:
Do not use equipment with leaking fluids. Repair equipment leaks immediately. Keep absorbent material manufactured for containment and cleanup of hazardous material on the job site. Sand and soils are not approved absorbent materials.
Notify the CO of hazardous spills. Report the spill to the appropriate federal, state, and local authorities as required by the SPCC plan or hazardous spill plan.
107.10(c) Dirt, plant, and foreign material. Add the following:
All vehicles and equipment entering the project area must be clean of noxious weeds and free from oil leaks and are subject to inspection. Thoroughly wash construction equipment, including the undercarriage and any surface where soil containing exotic seeds may exist.
Allow the CO to inspect each piece of equipment before entering the park. Provide the cleaning and inspection records to the CO.
107.10(d) Clearances for Contractor-selected, noncommercial areas. Add the following to the end of the first paragraph:
Use rock, sand, gravel, earth, subsoil, or other natural materials from a Contractor-selected non-commercial materials source that has been certified free of noxious weeds. Materials imported into the project limits which do not include a noxious weed free certification may be rejected and ordered to be removed from the project limits. The CO has the discretion of requesting inspection of certified materials by a third party and rejecting the use of the source if noxious weeds or seeds thereof are found to be present.
Add the following after Subsection (4):
(5) Any required certifications.
Add the following:
107.10(e) Project-specific commitments.
E-13
(1) Archeological monitoring by NPS and the contractor provided Tribal Monitoring will occur during all earth disturbing activities. Provide the CO with a minimum 2 week notice prior to beginning any ground disturbing activities. The Contractor is responsible for coordinating with the Tribal monitors during the entirety of the fieldwork task to ensure daily fieldwork schedules are synchronized between the Contractor and Tribal monitors. Qualifications for monitors are included in 623.03(b) and the Archeological
Monitoring Plan is included in Appendix B.
All earth disturbing activities require monitoring by the NPS Archeological Monitor and the contractor provided Tribal Monitor. In the event of non-responsiveness, the Contractor must provide proof of contact, including at least two phone calls and two email attempts, to demonstrate efforts at tribal engagement. These attempts must occur at least 14 days prior to any ground disturbance. If no response is received after these documented efforts, the Contractor may proceed with construction activities.
Tribal and Archeological monitors must be present during all ground disturbing activities including but not limited to:
• Erosion control installation and management
• BMP installation
• Clearing and Grubbing
• Culvert cleaning, lining and replacement
• Culvert outlet grading
• Ditch grading
(2) In the event of an archaeological discovery during construction, stop all work in the vicinity of the discovery and notify the CO. Coordinate with the CO to take measures to prevent further impacts or to mitigate loss in accordance with 36 CFR 800.13.
Consultation with SHOP, Advisory council on historic preservation and associated Native
American tribes may take place in accordance with 36 CFR 800, The Native American
Graves Protection and Repatriation Act, and all other applicable state and federal laws.
(3) The Contractor staff and subcontractor staff to attend a Park orientation meeting prior to beginning work so they are aware of park rules protecting cultural and natural resources, how to recognize an archeological site (including historic trash), procedures for reporting possible archeological discoveries, and penalties for damaging cultural and natural resources. This requirement includes staff hired, and all staff reporting to the project at any point throughout the duration of the project. Record the first meeting for workers coming on to the project after the initial training. Provide a log to the CO for all completed trainings.
E-14
(4) Do not feed or disturb wildlife. To prevent unnatural attractants to wildlife, keep all foods, pet foods, garbage, drinks, trash, or food and drink containers inside vehicles, or enclosed construction equipment, except during actual use. Supply garbage bins, within the construction site that are bear and animal proof. Remove all garbage and food trash from the project site daily.
(5) Do not disturb cultural resources. Cultural resources exist in many locations immediately adjacent to the roadway. Do not disturb the area beyond the construction limits. Do not excavate, remove, damage, alter or deface any archeological or paleontological remains or specimens.
(6) Clearly define the limits of construction with fencing, flagging or method approved by the CO. No disturbance is to occur beyond these limits other than erosion/sediment control measures, installation of signs, placement of boulders and riprap, and culvert cleaning/extensions as approved by the CO. Do not walk or step beyond the limits of construction as shown in the plans. Do not park or drive construction vehicles beyond the limits of construction as shown in the plans. Do not disturb any plants beyond the limits of construction as shown in the plans. The limits of construction in all parking areas must be identified using durable high-visibility ribbon which is to be maintained by
Contractor until final acceptance. No payment will be made for installation, maintenance and removal of ribbon in parking areas.
(7) Notify the CO immediately if a nest is found in the vicinity of the project between March
1-July 31 to ensure no damage to the nests of migratory birds.
(8) Straw bales and non-fumigated products are not permitted for erosion control. If silt fence is used provide an inspection and cleaning schedule to the CO for approval.
(9) If headwall replacements are required, discreetly carve the current year into the header face of one stone at the end of the new course.
(10) Complete excavation work around historic culverts by hand.
(11) Cover historic headwalls with blankets and tarps while performing work in the vicinity.
107.11 Protection of Forests, Parks, and Public Lands. Add the following:
Comply with the fire prevention plan included in Appendix A. The CO will order the emergency suspension of operations when conditions are unsafe as determined by the CO and the land management agency. Work may be suspended during dry periods where fire danger is extreme.
E-15
Section 108. — PROSECUTION AND PROGRESS
108.01 Commencement, Prosecution, and Completion of Work. Add the following: Delete this subsection and substitute the following:
A preconstruction conference will be held after the contract is awarded and before starting work.
Seven days before the preconstruction conference, submit copies of the preliminary work plan according to Section 155.
Limit operations according to Sections 107 and 156.
Limit operations as follows:
(a) Do not begin site work prior to 3/6/2026.
(b) Only use existing pullouts and parking areas for truck turnaround locations. Use signage and flaggers at truck turnaround points as approved by the CO.
Perform no work except to maintain traffic control devices, erosion control devices, the roadway driving surface, and to control dust during the listed holidays and surrounding days as shown in
Table 108-2.
E-16
Table 108-2
Holidays and Surrounding Days
Holiday Time Remarks
Birthday of
Martin Luther
King, Jr.
Noon Friday to
6:00 a.m. Tuesday
Washington’s
Birthday
Noon Friday to
6:00 a.m. Tuesday
Memorial Day Noon Friday to 6:00 a.m. Tuesday −
Juneteenth
National
Independence
Day
Noon June 18 to
6:00 a.m. June 20
If June 19 falls on a Saturday, do not work the preceding Friday. If
June 19 falls on a Sunday, do not work the following Monday.
Independence
Day
Noon July 3 to
6:00 a.m. July 5
If July 4 falls on a weekend, Friday, or Monday, do not work the weekend. If July 4 falls on a
Saturday, do not work the preceding Friday. If July 4 falls on a Sunday, do not work the following Monday.
Labor Day Noon Friday to 6:00 a.m. Tuesday −
Columbus Day Noon Friday to 6:00 a.m. Tuesday −
Veterans Day Noon November 10 to
6:00 a.m. November 12
If November 11 falls on a
Saturday, do not work the preceding Friday. If November 11 falls on a Sunday, do not work the following Monday.
Thanksgiving
Day
Noon Wednesday to
6:00 a.m. Monday
Christmas Day /
New Year’s
Day
Noon December 23 to
6:00 a.m. January 2
If December 23 or January 1 falls on a Monday, do not work the adjacent weekend and do not work on December 23. If January 1 falls on a Friday, do not work the weekend.
Schedule at least 2 non-workdays out of every 14 days. The selected non-workdays do not need to be consecutive, but they must be scheduled. Notify the CO at least 2 weeks before changing the scheduled days off.
The CO may grant written approval for exemptions to scheduled days off for specific project operations and for periods of limited duration.
E-17
Add the following:
The CO will issue the NTP before commencement of any work. The completion date is October
30, 2026.
No additional contract time will be added if Option X is awarded.
108.03 Subcontracting. Delete the second paragraph and substitute the following:
Within 14 days of subcontract award, submit a completed SF 1413 and 1413S. Complete Part I for each Subcontractor, and include Part II when the Subcontractor performs on-site work. Complete other forms that may be required by the Government to show the work subcontracted and the total dollar amount of the subcontract. Submit the above required information for each Subcontractor at lower tiers.
108.04 Determination and Extension of Contract Time. Delete the first sentence.
108.04(c) Time extensions. Add the following:
If a quantity variation described in Subsection 109.06(e) results in an increase in the time necessary for completion, the Contractor may request, in writing, an extension of time as provided within this Subsection.
108.05 Failure to Complete Work on Time. Delete the second and third paragraphs and substitute the following:
Liquidated damages in the amount specified in FAR Clause 52.211-12 Liquidated Damages —
Construction will be assessed for each day beyond the time allowed to complete the contract until substantial completion of the work.
If a winter shutdown occurs during this period, liquidated damages in an amount equal to 10 percent of the amount shown in FAR Clause 52.211-12 Liquidated Damages — Construction will be assessed for each day until work resumes at which time full liquidated damages will be assessed.
Delete Table 108-1.
Section 109. — MEASUREMENT AND PAYMENT
109.01 Measurement of Work. Delete the seventh paragraph and substitute the following:
Prepare, sign, and submit electronic measurement notes (pay notes and supporting field documentation) using Masterworks. Unacceptable measurement notes will be electronically rejected and returned. Correct rejected measurement notes and resubmit electronically.
109.06 Pricing of Adjustments. Add the following:
E-18
(e) Variation in estimated quantity. If the quantity of a unit-priced item is an estimated quantity and the actual quantity of the unit-priced item varies more than 15 percent above or below the estimated quantity, an equitable adjustment in the contract price may be made upon request of either party. The equitable adjustment will be based upon any increase or decrease in costs due solely to the variation above 115 percent or below 85 percent of the estimated quantity.
109.08(a) General. Delete the last sentence and substitute the following:
The CO may withhold partial progress payment according to Subsection 109.08(h) for failure to make satisfactory progress until a construction schedule or schedule update is approved.
109.08(c) Government’s receiving report. Delete this Subsection and substitute the following:
The Government’s receiving report will be developed using the measurements and quantities from Pay Notes received by the CO in Masterworks and determined acceptable.
109.08(d) Closing date and invoice submittal date. Add the following:
No closing dates will be permitted from September 1 to October 14. Do not submit invoices between September 1 and October 14.
109.08(e)(1) Proper invoices. Delete this Subsection and substitute the following:
(1) Invoices received by the 7th day following the closing date.
(a) Proper invoices. If the invoice meets the requirements of Subsection 109.08(b), and the quantities and unit prices shown on the Contractor's invoice agree with the corresponding quantities and unit prices shown on the Government's receiving report, the invoice will be paid.
(b) Defective invoices. If the invoice does not meet the requirements of Subsection
109.08(b), or if any of the quantities or unit prices shown on the Contractor's invoice exceed the corresponding quantities and unit prices shown on the Government's receiving report, the invoice will be deemed defective, and the Contractor so notified according to FAR Clause 52.232-27(a)(2). Defective invoices will not be corrected by the Government and will be returned to the Contractor within 7 days after the
Government's designated billing office receives the invoice.
Revise and resubmit returned invoices by the 18th day following the closing date. The CO will evaluate the revised invoice. If the invoice is deemed proper, it will be forwarded for processing within 7 days of receipt. If the invoice still does not meet the requirements of
Subsection 109.08(b), the Contractor will be so notified according to FAR Clause 52.232-
27(a)(2), and no progress payment will be made that month. Correct the deficiencies and resubmit the invoice the following month.
E-19
If the revised invoice meets the requirements of Subsection 109.08(b), but still has quantities or unit prices exceeding the corresponding quantities and unit prices shown on the Government's receiving report, the Government's data for that item or work will be used. The Contractor's invoice, as revised by the Government's receiving report, will be forwarded for processing by the 23rd day following the closing date. The Contractor will be notified by the 23rd day following the closing date of the reasons for any changes to the invoice.
109.08(e)(2) Defective invoices. Delete this Subsection and substitute the following:
(2) Invoices received between the 8th and 16th day following the closing date.
(a) Proper invoices. If the invoice meets the requirements of Subsection 109.08(b), and the quantities and unit prices shown on the Contractor's invoice agree with the corresponding quantities and unit prices shown on the CO's receiving report, the invoice will be deemed proper and forwarded for processing within 7 days of receipt.
(b) Defective invoices. If the invoice does not meet the requirements of Subsection
109.08(b), the invoice will be deemed defective, the Contractor so notified according to FAR Clause 52.232-27(a)(2), and no progress payment will be made that month.
Correct the deficiencies and resubmit the invoice the following month.
If the invoice meets the requirements of Subsection 109.08(b) but has quantities or unit prices exceeding the corresponding quantities and unit prices shown on the Government's receiving report, the Government's data for that item of work will be used. The Contractor's invoice, as revised by the Government's receiving report, will be forwarded for processing within 7 days of the Government's receipt of the invoice. The Contractor will be notified of the reasons for any changes to the invoice.
109.08(f) Partial payments. Delete this Subsection and substitute the following:
(f) Partial payments. Progress payments may include partial payment for material to be incorporated in the work according to FAR Clause 52.232-5(b)(2), provided the material meets the requirements of the contract and is delivered on, or in the vicinity of, the project site or stored in acceptable storage places.
Partial payments for stockpiled manufactured material (aggregates) will be based on
Contractor process control test results. If test results show the material to be out-of-specification, or in “reject” where statistical evaluation procedures are used, no payment for stockpiled materials will be made.
Partial payment for material does not constitute acceptance of such material for use in completing items of work. Partial payments will not be made for living or perishable material until incorporated into the project.
E-20
Individual and cumulative partial payments for preparatory work and material will not exceed the lesser of:
(1) 80 percent of the contract bid price for the item; or
(2) 100 percent of amount supported by copies of invoices submitted.
The quantity paid will not exceed the corresponding quantity estimated in the contract. The
CO may adjust partial payments as necessary to protect the Government.
Section 152. — CONSTRUCTION SURVEY AND STAKING
Construction Requirements
152.04 General. Add the following to the fifth paragraph:
No horizontal or vertical control information will be furnished for Route 0010 (Main) Entrance
Road or for the Road Connection in the RTE 0918 Visitor Center Parking area.
152.04 General. Add the following to the fifth paragraph:
The Government will establish vertical and horizontal survey control points.
The Government will furnish design data listed in 102.02A(c).
The Government will establish vertical and horizontal survey control points for the following
Routes:
• RTE 0200 Wetherill Mesa Road
• RTE 0205 Cedar Tree Tower Road
• RTE 0210 Far View Ruins (Sites) Road
• RTE 0404 Far View Residence Road
• RTE 0912AZ Far View Terrace Parking A
• RTE 0912BZ Far View Terrace Parking B (Loading Dock)
• RTE 0918 Visitor Center Parking (Far View Center Parking Lot)
• RTE 0925 Side Headquarters and Post Office Parking
E-21
• RTE 0409A Stone House Road A
• RTE 0409B Stone House Road B
The Government will furnish the following for use during bidding and construction:
(6) Horizontal alignment listings in Portable Document Format (pdf) and
LandXML (.xml) formats; for all routes
(7) 3D surfaces of existing ground, subgrade, finished grade, and top of base course in LandXML (xml) format; for RTE 0205 Cedar Tree
Tower Road and RTE 0210 Far View Ruins (Sites) Road only.
(8) Proposed 3D breaklines in Drawing Exchange Format (dxf); for RTE
0205 Cedar Tree Tower Road and RTE 0210 Far View Ruins (Sites)
Road only.
(9) 3D coordinates and offset distance from centerline for subgrade and slope staking information and top of base course information at 50-foot
(20-meter) intervals and miscellaneous intermediate stations in Portable
Document Format (.pdf); for RTE 0205 Cedar Tree Tower Road and
RTE 0210 Far View Ruins (Sites) Road only.
(10) Earthwork quantity summary in Portable Document Format (pdf).
for RTE 0205 Cedar Tree Tower Road and RTE 0210 Far View Ruins
(Sites) Road only.
These files are considered Physical Data according to FAR 52.236-4 Physical Data.
152.05(b) Centerline establishment. Add the following:
Reestablishment of centerline may be ordered and paid for under Section 623 for purposes other than to control the work.
152.05(d)(2) Conventional survey methods. Add the following:
For RTE 0205 Cedar Tree Tower Road and RTE 0210 Far View Ruins (Sites) Road, When the centerline curve radius is less than or equal to 250 feet, use a maximum longitudinal spacing between stakes of 25 feet. When the centerline is on a tangent or the curve radius is greater than 250 feet, use a maximum longitudinal spacing between stakes of 50 feet.
152.05(f)(1) AMG method. Delete this Subsection and substitute the following:
Use conventional survey methods for grade finishing.
152.05(g) Culverts. Delete this Subsection and substitute the following:
E-22
(1) Verify and set culvert locations at the inlet, outlet, and inlet basin points as shown in the plans. Plot to scale the profile along the culvert centerline. Show the existing ground, flow line, roadway section, and culvert including end treatments and other appurtenances.
Show the elevations, grade, culvert length, degree of elbow, catch points, and hinge points on the plot.
(2) Perform the following if the culvert design shown in the plans does not fit field conditions, when the CO requires adjustment to a culvert location, or when a culvert design isn’t furnished for a new culvert, culvert replacement, or culvert extension:
(a) Recommend a revised culvert location and alignment if needed.
(b) Survey and record the ground profile along the culvert centerline and additional channel profile for an appropriate offset to capture required information in Subsection
152.05(g)(2)(e).
(c) Determine the slope catch points at the inlet and outlet.
(d) Set reference points and record information necessary to determine culvert length and end treatments.
(e) Plot to scale the profile along the culvert centerline. Show the existing ground, flow line, roadway section, culvert, end treatments, and other appurtenances. Show elevations, grade, culvert length, and degree of elbow.
(1) For single skewed culverts, submit a plotted field-design cross-section normal to roadway centerline and at each end section. Plot the offset and elevation of existing ground at the end section and at proposed template break points between centerline and the end section. Ensure the template design embankment slope is not exceeded.
(2) For multiple skewed culverts, submit a plotted field design cross-section normal to roadway centerline and at the end sections (left and right) nearest to the shoulder.
Plot the offset and elevation of existing ground at the end section and at proposed template break points between centerline and the end section. Ensure the template design embankment slope is not exceeded.
(3) Submit the plotted field-design cross-section for approval of final culvert length and alignment. Plot at a clear and readable scale.
(4) Set inlet, outlet, and reference stakes when the field design has been approved.
Stake inlet and outlet ditches to ensure the culvert and end treatments (such as drop inlets) are functional.
(5) Adjust slope, reference, and clearing stakes as necessary to provide for culvert inlet treatments in cut slopes. Readjust slope, reference, and clearing stakes as necessary when culvert inlets are moved from their plan locations. Review slope adjustments with the CO and obtain approval.
E-23
152.05(i) Retaining walls, rockeries, special rock embankments, rock buttresses, gabion walls, and reinforced soil slopes. Delete the first sentence and substitute the following:
Survey and record profile measurements along the face of the proposed wall, rockery, embankment, buttress, or reinforced soil slope along the face of the proposed wall or slope, and at
5 feet and 10 feet in front of the wall or slope face.
152.05 Survey and Staking Requirements. Add the following:
(m) Centerline verification and staking. Verify stationing shown in the plans by measuring along the existing centerline with an approved method. Calibrate all measuring devices and provide calibration data to the CO before use. Use landmarks, such as culverts, pullouts, and approach roads, to verify that the ground stationing matches the stationing shown in the plans.
Use white spray paint to mark each centerline station. Add station equations to adjust field stationing to match the plans. Notify the CO of any readjustment or change to stationing or establishment of additional centerline points.
Measure the existing surface width at 200-foot intervals on tangent and at 50-foot intervals on curves. At each location, each side of the roadway and outside the construction limits, place an offset stake of adequate dimensions to place all required information. Label each stake with the following information:
(1) Station;
(2) Offset from striped centerline or other location as directed; and
(3) Offset from the proposed edge of pavement.
Measure stations to the nearest foot and offsets to the nearest 2 inches. Record the above information and provide to the CO.
Use this recorded information to control the proposed roadway width and reestablish striping.
152.05 Survey and Staking Requirements. Add the following:
(n) Pavement preservation roadway width verification. Measure the existing pavement surface width at 500-foot intervals on tangents and at 100-foot intervals on curves. Use white spray paint to mark the pavement with the station on each side of the roadway. Take additional measurements between the above required intervals if the width varies more than 1 foot from the pavement surface width shown in the plans. Provide a record of width measurements and corresponding station locations to the CO for approval before starting surfacing operations.
Take additional measurements, at no additional cost to the Government, when requested. The revised approved surface widths will become the new surfacing width unless otherwise directed.
152.07 Add the following:
E-24
Measure centerline verification and staking only one time per project.
Section 153. — CONTRACTOR QUALITY CONTROL
Description
153.01 Add the following:
This work also consists of using Masterworks to prepare electronic CDRs and measurement notes (pay notes and supporting field documentation), including entering labor, equipment, subcontractors, and inspection records into the system.
Construction Requirements
153.03(b) QC procedures. Add the following to Subsection (3):
List the material to be tested by pay item, tests to be conducted, the location of sampling, and the frequency of testing.
153.03 Quality Control Plan. Add the following after Subsection (c):
(d) Subcontractors and suppliers. Include the work of all subcontractors. If a subcontractor is to perform work under this Section, explain how the subcontractor’s inspection plan will interface with the Prime Contractor first tier subcontractors and lower tier subcontractors and organizations, and the CO. Include the work of major suppliers and suppliers of structural and geotechnical services and materials.
153.03 Quality Control Plan. Add the following:
Modifications or additions may be required to any part of the plan that is not adequately covered.
Acceptance of the quality control plan will be based on the inclusion of the required information.
Acceptance does not imply any warranty by the Government that the plan will result in consistent contract compliance. It remains the responsibility of the Contractor to demonstrate such compliance.
153.05 Certifications and Submittals. Delete this Subsection and substitute the following:
For materials or work accepted by certification according to Subsection 106.03, review all certifications to ensure compliance with the requirements of the…