TX Tabulation of Bids.pdf
PDF 663 KB Posted
- Solicitation number
- 6982AF23B000023
About this file
This Tabulation of Bids document details the bid submissions for a federal highway construction project in Denton County, Texas, involving widening Jones Street and North Kealy Avenue and constructing an adjacent trail near the Lewisville Lake Environmental Learning Area. Three contractors submitted bids: Construction Solutions Group, LLC at $6,323,236.00, SMR Construction, Inc. at $7,315,915.94, and McKenzie Construction and Site Development, LLC at $11,894,131.12, with the engineer's estimate set at $6,965,000.00.
The project scope includes extensive roadway and infrastructure work, such as mobilization, construction survey and staking, quality control, soil erosion control, roadway excavation, subgrade stabilization, concrete pavement, drainage improvements (including pipe culverts, manholes, and inlets), curbing, sidewalks, fencing, traffic control, seeding, and landscaping. The solicitation (No. 6982AF23B000023) is managed by the Central Federal Lands division, with bids opened on 02/27/25 in Lakewood, Colorado. The lowest bid was submitted by Construction Solutions Group, LLC, which is significantly below the engineer's estimate and the other two bidders.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Tabulation of Bids Report Date: 03/05/25
1 out of 13Source Selection Information - See FAR 2.101 & 3.104
Project No: TX FLAP 200(1)
Project Name: WIDENINING JONES STREET AND NORTH KEALY AVENUE AND
CONSTRUCTION OF ADJACENT TRAIL NEAR LEWISVILLE LAKE ENVIRONMENTAL
LEARNING AREA
Schedule: A
Schedule Type: Base
Solcitation No: 6982AF23B000023
Division: Central Federal Lands
State: TX County: Denton
Federal Land: LEWISVILLE LAKE ENVIRONMENTAL LEARNING AREA Opened at: Lakewood, CO
Opened by: Eric Grosskreuz
Date: 02/27/25
I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.
Signed: _______________________________
Title: _______________________________
Date: _______________________________
Contract Awarded to: ____________________ Award Date: ____________________
Contractor Comment Bid Amount Responsive
Construction Solutions Group, LLC $6,323,236.00 425 Highland Ave St. Louis, MO 63122
SMR Construction, Inc. $7,315,915.94 411 Industrial Drive, Suite 109 Richardson, TX 75081
McKenzie Construction and Site Development, LLC $11,894,131.12 2301 Calvert Washington, DC 20008
Engineer's Estimate $6,965,000.00
2 out of 13Source Selection Information - See FAR 2.101 & 3.104
Project No: TX FLAP 200(1)
Project Name: WIDENINING JONES STREET AND NORTH KEALY AVENUE AND
CONSTRUCTION OF ADJACENT TRAIL NEAR LEWISVILLE LAKE ENVIRONMENTAL
LEARNING AREA
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0010 15101-0000 MOBILIZATION
Construction Solutions Group, LLC Lump Sum $1,080,000.00 SMR Construction, Inc. Lump Sum $1,101,427.81 McKenzie Construction and Site Development, LLC Lump Sum $1,838,531.88 Engineer's Estimate ALL LPSM Lump Sum $722,490.00
A0020 15201-0000 CONSTRUCTION SURVEY AND STAKING
Construction Solutions Group, LLC Lump Sum $128,000.00 SMR Construction, Inc. Lump Sum $48,539.53 McKenzie Construction and Site Development, LLC Lump Sum $104,815.88 Engineer's Estimate ALL LPSM Lump Sum $75,000.00
A0030 15301-0000 CONTRACTOR QUALITY CONTROL
Construction Solutions Group, LLC Lump Sum $220,000.00 SMR Construction, Inc. Lump Sum $138,684.37 McKenzie Construction and Site Development, LLC Lump Sum $353,792.11 Engineer's Estimate ALL LPSM Lump Sum $65,000.00
A0040 15401-0000 CONTRACTOR TESTING
Construction Solutions Group, LLC Lump Sum $153,000.00 SMR Construction, Inc. Lump Sum $46,228.12 McKenzie Construction and Site Development, LLC Lump Sum $325,496.42 Engineer's Estimate ALL LPSM Lump Sum $175,000.00
A0050 15501-0000 CONSTRUCTION SCHEDULE
Construction Solutions Group, LLC Lump Sum $62,000.00 SMR Construction, Inc. Lump Sum $16,642.12 McKenzie Construction and Site Development, LLC Lump Sum $34,800.04 Engineer's Estimate ALL LPSM Lump Sum $60,000.00
A0060 15701-0000 SOIL EROSION CONTROL
Construction Solutions Group, LLC Lump Sum $170,000.00 SMR Construction, Inc. Lump Sum $31,781.84 McKenzie Construction and Site Development, LLC Lump Sum $35,781.40 Engineer's Estimate ALL LPSM Lump Sum $51,000.00
3 out of 13Source Selection Information - See FAR 2.101 & 3.104
Project No: TX FLAP 200(1)
Project Name: WIDENINING JONES STREET AND NORTH KEALY AVENUE AND
CONSTRUCTION OF ADJACENT TRAIL NEAR LEWISVILLE LAKE ENVIRONMENTAL
LEARNING AREA
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0070 15720-0000 STORM WATER POLLUTION PREVENTION PLAN
Construction Solutions Group, LLC Lump Sum $85,000.00 SMR Construction, Inc. Lump Sum $6,356.37 McKenzie Construction and Site Development, LLC Lump Sum $8,236.01 Engineer's Estimate ALL LPSM Lump Sum $6,000.00
A0080 15802-0000 WATERING FOR DUST CONTROL
Construction Solutions Group, LLC Lump Sum $86,000.00 SMR Construction, Inc. Lump Sum $99,332.68 McKenzie Construction and Site Development, LLC Lump Sum $139,200.18 Engineer's Estimate ALL LPSM Lump Sum $26,000.00
A0090 20101-0000 CLEARING AND GRUBBING
Construction Solutions Group, LLC $3,000.00 $15,600.00 SMR Construction, Inc. $2,311.41 $12,019.33 McKenzie Construction and Site Development, LLC $9,280.01 $48,256.05 Engineer's Estimate 5.20 ACRE $10,300.00 $53,560.00
A0100 20120-1000 REMOVAL, INDIVIDUAL TREE
Construction Solutions Group, LLC $600.00 $18,000.00 SMR Construction, Inc. $808.99 $24,269.70 McKenzie Construction and Site Development, LLC $1,234.24 $37,027.20 Engineer's Estimate 30 EACH $1,700.00 $51,000.00
A0110 20301-1400 REMOVAL OF INLET
Construction Solutions Group, LLC $1,800.00 $1,800.00 SMR Construction, Inc. $1,733.55 $1,733.55 McKenzie Construction and Site Development, LLC $2,900.00 $2,900.00 Engineer's Estimate 1 EACH $2,500.00 $2,500.00
A0120 20301-2400 REMOVAL OF SIGN
Construction Solutions Group, LLC $120.00 $1,680.00 SMR Construction, Inc. $346.71 $4,853.94 McKenzie Construction and Site Development, LLC $244.12 $3,417.68 Engineer's Estimate 14 EACH $230.00 $3,220.00
4 out of 13Source Selection Information - See FAR 2.101 & 3.104
Project No: TX FLAP 200(1)
Project Name: WIDENINING JONES STREET AND NORTH KEALY AVENUE AND
CONSTRUCTION OF ADJACENT TRAIL NEAR LEWISVILLE LAKE ENVIRONMENTAL
LEARNING AREA
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0130 20302-0200 REMOVAL OF CURB
Construction Solutions Group, LLC $36.00 $2,700.00 SMR Construction, Inc. $23.11 $1,733.25 McKenzie Construction and Site Development, LLC $31.76 $2,382.00 Engineer's Estimate 75 LNFT $25.00 $1,875.00
A0140 20302-0700 REMOVAL OF FENCE
Construction Solutions Group, LLC $3.60 $17,640.00 SMR Construction, Inc. $3.47 $17,003.00 McKenzie Construction and Site Development, LLC $0.69 $3,381.00 Engineer's Estimate 4,900 LNFT $8.00 $39,200.00
A0150 20302-2100 REMOVAL OF PIPE CULVERT
Construction Solutions Group, LLC $18.00 $1,620.00 SMR Construction, Inc. $86.68 $7,801.20 McKenzie Construction and Site Development, LLC $40.60 $3,654.00 Engineer's Estimate 90 LNFT $80.00 $7,200.00
A0160 20303-1600 REMOVAL OF PAVEMENT, ASPHALT
Construction Solutions Group, LLC $13.20 $118,800.00 SMR Construction, Inc. $11.56 $104,040.00 McKenzie Construction and Site Development, LLC $15.77 $141,930.00 Engineer's Estimate 9,000 SQYD $7.50 $67,500.00
A0170 20303-2300 REMOVAL OF PAVEMENT, CONCRETE
Construction Solutions Group, LLC $24.00 $11,400.00 SMR Construction, Inc. $11.56 $5,491.00 McKenzie Construction and Site Development, LLC $44.08 $20,938.00 Engineer's Estimate 475 SQYD $45.00 $21,375.00
A0180 20304-1000 REMOVAL OF STRUCTURES AND OBSTRUCTIONS
Construction Solutions Group, LLC Lump Sum $12,000.00 SMR Construction, Inc. Lump Sum $28,892.58 McKenzie Construction and Site Development, LLC Lump Sum $116,000.15 Engineer's Estimate ALL LPSM Lump Sum $60,000.00
5 out of 13Source Selection Information - See FAR 2.101 & 3.104
Project No: TX FLAP 200(1)
Project Name: WIDENINING JONES STREET AND NORTH KEALY AVENUE AND
CONSTRUCTION OF ADJACENT TRAIL NEAR LEWISVILLE LAKE ENVIRONMENTAL
LEARNING AREA
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0190 20315-0000 SAWCUTTING PAVEMENT
Construction Solutions Group, LLC $8.40 $1,848.00 SMR Construction, Inc. $2.31 $508.20 McKenzie Construction and Site Development, LLC $10.44 $2,296.80 Engineer's Estimate 220 LNFT $15.00 $3,300.00
A0200 20401-0000 ROADWAY EXCAVATION
Construction Solutions Group, LLC $14.40 $109,440.00 SMR Construction, Inc. $8.09 $61,484.00 McKenzie Construction and Site Development, LLC $116.00 $881,600.00 Engineer's Estimate 7,600 CUYD $40.00 $304,000.00
A0210 20441-0000 WASTE
Construction Solutions Group, LLC $18.00 $108,000.00 SMR Construction, Inc. $28.89 $173,340.00 McKenzie Construction and Site Development, LLC $232.00 $1,392,000.00 Engineer's Estimate 6,000 CUYD $25.00 $150,000.00
A0220 20466-0000 CONSERVE AND STOCKPILE TOPSOIL
Construction Solutions Group, LLC $12.00 $15,600.00 SMR Construction, Inc. $8.09 $10,517.00 McKenzie Construction and Site Development, LLC $31.32 $40,716.00 Engineer's Estimate 1,300 CUYD $45.00 $58,500.00
A0230 21101-1000 ROADWAY OBLITERATION, METHOD 1
Construction Solutions Group, LLC $48.00 $42,000.00 SMR Construction, Inc. $28.89 $25,278.75 McKenzie Construction and Site Development, LLC $301.60 $263,900.00 Engineer's Estimate 875 SQYD $25.00 $21,875.00
A0240 21301-0000 SUBGRADE STABILIZATION (8-INCH LIME)
Construction Solutions Group, LLC $5.40 $75,600.00 SMR Construction, Inc. $10.40 $145,600.00 McKenzie Construction and Site Development, LLC $34.80 $487,200.00 Engineer's Estimate 14,000 SQYD $5.00 $70,000.00
6 out of 13Source Selection Information - See FAR 2.101 & 3.104
Project No: TX FLAP 200(1)
Project Name: WIDENINING JONES STREET AND NORTH KEALY AVENUE AND
CONSTRUCTION OF ADJACENT TRAIL NEAR LEWISVILLE LAKE ENVIRONMENTAL
LEARNING AREA
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0250 21301-0000 SUBGRADE STABILIZATION (16-INCH MOISTURE TREATMENT)
Construction Solutions Group, LLC $4.20 $58,800.00 SMR Construction, Inc. $9.25 $129,500.00 McKenzie Construction and Site Development, LLC $69.60 $974,400.00 Engineer's Estimate 14,000 SQYD $12.00 $168,000.00
A0260 21302-0000 LIME (8-INCH DEPTH)
Construction Solutions Group, LLC $492.00 $147,600.00 SMR Construction, Inc. $520.07 $156,021.00 McKenzie Construction and Site Development, LLC $504.09 $151,227.00 Engineer's Estimate 300 TON $350.00 $105,000.00
A0270 25101-0100 PLACED RIPRAP, METHOD A, CLASS 1
Construction Solutions Group, LLC $162.00 $810.00 SMR Construction, Inc. $1,155.70 $5,778.50 McKenzie Construction and Site Development, LLC $361.16 $1,805.80 Engineer's Estimate 5 CUYD $190.00 $950.00
A0280 25101-0200 PLACED RIPRAP, METHOD A, CLASS 2
Construction Solutions Group, LLC $162.00 $1,620.00 SMR Construction, Inc. $260.03 $2,600.30 McKenzie Construction and Site Development, LLC $361.16 $3,611.60 Engineer's Estimate 10 CUYD $410.00 $4,100.00
A0290 30202-2100 ROADWAY AGGREGATE, METHOD 2, SURFACE COURSE
Construction Solutions Group, LLC $75.00 $75,000.00 SMR Construction, Inc. $52.01 $52,010.00 McKenzie Construction and Site Development, LLC $117.43 $117,430.00 Engineer's Estimate 1,000 TON $60.00 $60,000.00
A0300 31103-3000 STABILIZED AGGREGATE SURFACE COURSE, CALCIUM CHLORIDE, IMPORTED AGGREGATE
Construction Solutions Group, LLC $96.00 $7,200.00 SMR Construction, Inc. $264.66 $19,849.50 McKenzie Construction and Site Development, LLC $2,701.88 $202,641.00 Engineer's Estimate 75 TON $40.00 $3,000.00
7 out of 13Source Selection Information - See FAR 2.101 & 3.104
Project No: TX FLAP 200(1)
Project Name: WIDENINING JONES STREET AND NORTH KEALY AVENUE AND
CONSTRUCTION OF ADJACENT TRAIL NEAR LEWISVILLE LAKE ENVIRONMENTAL
LEARNING AREA
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0310 50101-1000 MINOR CONCRETE PAVEMENT, REINFORCED, 10-INCH DEPTH
Construction Solutions Group, LLC $107.94 $1,478,778.00 SMR Construction, Inc. $220.74 $3,024,138.00 McKenzie Construction and Site Development, LLC $149.26 $2,044,862.00 Engineer's Estimate 13,700 SQYD $205.00 $2,808,500.00
A0320 55401-1000 REINFORCING STEEL (HEADWALL)
Construction Solutions Group, LLC $3.00 $570.00 SMR Construction, Inc. $4.62 $877.80 McKenzie Construction and Site Development, LLC $7.33 $1,392.70 Engineer's Estimate 190 LB $5.00 $950.00
A0330 60101-0000 CONCRETE (HEADWALL)
Construction Solutions Group, LLC $1,200.00 $2,400.00 SMR Construction, Inc. $5,200.66 $10,401.32 McKenzie Construction and Site Development, LLC $4,930.00 $9,860.00 Engineer's Estimate 2.0 CUYD $1,700.00 $3,400.00
A0340 60201-0600 18-INCH PIPE CULVERT (RCP)
Construction Solutions Group, LLC $162.00 $243,000.00 SMR Construction, Inc. $231.14 $346,710.00 McKenzie Construction and Site Development, LLC $145.00 $217,500.00 Engineer's Estimate 1,500 LNFT $145.00 $217,500.00
A0350 60201-0800 24-INCH PIPE CULVERT (RCP)
Construction Solutions Group, LLC $186.00 $232,500.00 SMR Construction, Inc. $271.59 $339,487.50 McKenzie Construction and Site Development, LLC $168.20 $210,250.00 Engineer's Estimate 1,250 LNFT $220.00 $275,000.00
A0360 60401-0000 MANHOLE
Construction Solutions Group, LLC $10,200.00 $10,200.00 SMR Construction, Inc. $26,581.17 $26,581.17 McKenzie Construction and Site Development, LLC $9,860.01 $9,860.01 Engineer's Estimate 1 EACH $10,800.00 $10,800.00
8 out of 13Source Selection Information - See FAR 2.101 & 3.104
Project No: TX FLAP 200(1)
Project Name: WIDENINING JONES STREET AND NORTH KEALY AVENUE AND
CONSTRUCTION OF ADJACENT TRAIL NEAR LEWISVILLE LAKE ENVIRONMENTAL
LEARNING AREA
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0370 60403-0000 INLET (10-FOOT)
Construction Solutions Group, LLC $17,400.00 $69,600.00 SMR Construction, Inc. $17,335.55 $69,342.20 McKenzie Construction and Site Development, LLC $12,180.01 $48,720.04 Engineer's Estimate 4 EACH $9,750.00 $39,000.00
A0380 60403-0000 INLET (5-FOOT)
Construction Solutions Group, LLC $21,600.00 $410,400.00 SMR Construction, Inc. $13,868.44 $263,500.36 McKenzie Construction and Site Development, LLC $9,860.01 $187,340.19 Engineer's Estimate 19 EACH $6,500.00 $123,500.00
A0390 60404-1000 CATCH BASIN, FLH TYPE 1
Construction Solutions Group, LLC $6,600.00 $13,200.00 SMR Construction, Inc. $17,335.55 $34,671.10 McKenzie Construction and Site Development, LLC $3,306.00 $6,612.00 Engineer's Estimate 2 EACH $4,500.00 $9,000.00
A0400 60526-0000 DRAINAGE CHASE
Construction Solutions Group, LLC $72.00 $1,800.00 SMR Construction, Inc. $520.07 $13,001.75 McKenzie Construction and Site Development, LLC $214.60 $5,365.00 Engineer's Estimate 25 LNFT $365.00 $9,125.00
A0410 60901-1500 CURB, CONCRETE, 16-INCH DEPTH
Construction Solutions Group, LLC $42.00 $252,000.00 SMR Construction, Inc. $34.67 $208,020.00 McKenzie Construction and Site Development, LLC $89.01 $534,060.00 Engineer's Estimate 6,000 LNFT $60.00 $360,000.00
A0420 61501-0100 SIDEWALK, CONCRETE
Construction Solutions Group, LLC $108.00 $21,600.00 SMR Construction, Inc. $184.91 $36,982.00 McKenzie Construction and Site Development, LLC $129.44 $25,888.00 Engineer's Estimate 200 SQYD $150.00 $30,000.00
9 out of 13Source Selection Information - See FAR 2.101 & 3.104
Project No: TX FLAP 200(1)
Project Name: WIDENINING JONES STREET AND NORTH KEALY AVENUE AND
CONSTRUCTION OF ADJACENT TRAIL NEAR LEWISVILLE LAKE ENVIRONMENTAL
LEARNING AREA
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0430 61504-1000 ACCESSIBILITY RAMP, CONCRETE
Construction Solutions Group, LLC $60.00 $3,900.00 SMR Construction, Inc. $346.71 $22,536.15 McKenzie Construction and Site Development, LLC $290.00 $18,850.00 Engineer's Estimate 65 SQYD $230.00 $14,950.00
A0440 61901-0000 FENCE , PIPE RAIL
Construction Solutions Group, LLC $42.00 $140,700.00 SMR Construction, Inc. $40.45 $135,507.50 McKenzie Construction and Site Development, LLC $32.39 $108,506.50 Engineer's Estimate 3,350 LNFT $60.00 $201,000.00
A0450 61901-0900 FENCE, BARBED WIRE, 4 STRAND
Construction Solutions Group, LLC $21.60 $41,040.00 SMR Construction, Inc. $8.96 $17,024.00 McKenzie Construction and Site Development, LLC $31.74 $60,306.00 Engineer's Estimate 1,900 LNFT $18.00 $34,200.00
A0460 61921-1000 REMOVE AND RESET FENCE
Construction Solutions Group, LLC $150.00 $3,750.00 SMR Construction, Inc. $34.67 $866.75 McKenzie Construction and Site Development, LLC $116.00 $2,900.00 Engineer's Estimate 25 LNFT $50.00 $1,250.00
A0470 62201-0000 EQUIPMENT
Construction Solutions Group, LLC $300.00 $30,000.00 SMR Construction, Inc. $231.14 $23,114.00 McKenzie Construction and Site Development, LLC $232.00 $23,200.00 Engineer's Estimate 100 HOUR $400.00 $40,000.00
A0480 62201-0200 DUMP TRUCK, 8 CUBIC YARD MINIMUM CAPACITY
Construction Solutions Group, LLC $180.00 $3,600.00 SMR Construction, Inc. $115.57 $2,311.40 McKenzie Construction and Site Development, LLC $232.00 $4,640.00 Engineer's Estimate 20 HOUR $160.00 $3,200.00
10 out of 13Source Selection Information - See FAR 2.101 & 3.104
Project No: TX FLAP 200(1)
Project Name: WIDENINING JONES STREET AND NORTH KEALY AVENUE AND
CONSTRUCTION OF ADJACENT TRAIL NEAR LEWISVILLE LAKE ENVIRONMENTAL
LEARNING AREA
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0490 62201-0550 BACKHOE LOADER, 6 CUBIC FOOT MINIMUM RATED CAPACITY BUCKET, 24-INCH WIDTH
Construction Solutions Group, LLC $210.00 $4,200.00 SMR Construction, Inc. $231.14 $4,622.80 McKenzie Construction and Site Development, LLC $174.00 $3,480.00 Engineer's Estimate 20 HOUR $150.00 $3,000.00
A0500 62201-0950 WHEEL LOADER, 3 CUBIC YARD MINIMUM RATED CAPACITY
Construction Solutions Group, LLC $210.00 $4,200.00 SMR Construction, Inc. $288.93 $5,778.60 McKenzie Construction and Site Development, LLC $232.00 $4,640.00 Engineer's Estimate 20 HOUR $170.00 $3,400.00
A0510 62201-1450 BULLDOZER, 350HP MINIMUM FLYWHEEL POWER
Construction Solutions Group, LLC $210.00 $4,200.00 SMR Construction, Inc. $346.71 $6,934.20 McKenzie Construction and Site Development, LLC $179.80 $3,596.00 Engineer's Estimate 20 HOUR $255.00 $5,100.00
A0520 62201-2850 MOTOR GRADER, 12 FOOT MINIMUM BLADE
Construction Solutions Group, LLC $210.00 $4,200.00 SMR Construction, Inc. $346.71 $6,934.20 McKenzie Construction and Site Development, LLC $191.40 $3,828.00 Engineer's Estimate 20 HOUR $200.00 $4,000.00
A0530 62201-3350 HYDRAULIC EXCAVATOR, 1 CUBIC YARD MINIMUM CAPACITY
Construction Solutions Group, LLC $210.00 $4,200.00 SMR Construction, Inc. $346.71 $6,934.20 McKenzie Construction and Site Development, LLC $150.80 $3,016.00 Engineer's Estimate 20 HOUR $125.00 $2,500.00
A0540 62301-0000 GENERAL LABOR
Construction Solutions Group, LLC $90.00 $36,000.00 SMR Construction, Inc. $40.45 $16,180.00 McKenzie Construction and Site Development, LLC $116.00 $46,400.00 Engineer's Estimate 400 HOUR $50.00 $20,000.00
11 out of 13Source Selection Information - See FAR 2.101 & 3.104
Project No: TX FLAP 200(1)
Project Name: WIDENINING JONES STREET AND NORTH KEALY AVENUE AND
CONSTRUCTION OF ADJACENT TRAIL NEAR LEWISVILLE LAKE ENVIRONMENTAL
LEARNING AREA
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0550 62302-1000 SPECIAL LABOR, HIRED TECHNICAL SERVICES (BIOLOGIST)
Construction Solutions Group, LLC $300.00 $6,000.00 SMR Construction, Inc. $86.68 $1,733.60 McKenzie Construction and Site Development, LLC $145.00 $2,900.00 Engineer's Estimate 20 HOUR $130.00 $2,600.00
A0560 62302-1000 SPECIAL LABOR, HIRED TECHNICAL SERVICES
Construction Solutions Group, LLC $300.00 $6,000.00 SMR Construction, Inc. $86.68 $1,733.60 McKenzie Construction and Site Development, LLC $580.00 $11,600.00 Engineer's Estimate 20 HOUR $200.00 $4,000.00
A0570 62302-1100 SPECIAL LABOR, HIRED SURVEY SERVICES
Construction Solutions Group, LLC $150.00 $6,000.00 SMR Construction, Inc. $346.71 $13,868.40 McKenzie Construction and Site Development, LLC $216.92 $8,676.80 Engineer's Estimate 40 HOUR $265.00 $10,600.00
A0580 62405-0300 PLACING CONSERVED TOPSOIL, 4-INCH DEPTH
Construction Solutions Group, LLC $3.60 $41,400.00 SMR Construction, Inc. $1.73 $19,895.00 McKenzie Construction and Site Development, LLC $1.45 $16,675.00 Engineer's Estimate 11,500 SQYD $7.00 $80,500.00
A0590 62510-2000 SEEDING, HYDRAULIC METHOD
Construction Solutions Group, LLC $4,800.00 $16,320.00 SMR Construction, Inc. $8,400.81 $28,562.75 McKenzie Construction and Site Development, LLC $14,848.02 $50,483.27 Engineer's Estimate 3.40 ACRE $3,600.00 $12,240.00
A0600 62515-2000 MULCHING, HYDRAULIC METHOD
Construction Solutions Group, LLC $1,200.00 $4,080.00 SMR Construction, Inc. $8,400.81 $28,562.75 McKenzie Construction and Site Development, LLC $5,080.80 $17,274.72 Engineer's Estimate 3.40 ACRE $5,000.00 $17,000.00
12 out of 13Source Selection Information - See FAR 2.101 & 3.104
Project No: TX FLAP 200(1)
Project Name: WIDENINING JONES STREET AND NORTH KEALY AVENUE AND
CONSTRUCTION OF ADJACENT TRAIL NEAR LEWISVILLE LAKE ENVIRONMENTAL
LEARNING AREA
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0610 62630-0350 PLANTINGS, TREES, BALLED AND BURLAPPED
Construction Solutions Group, LLC $600.00 $18,000.00 SMR Construction, Inc. $1,155.70 $34,671.00 McKenzie Construction and Site Development, LLC $1,160.00 $34,800.00 Engineer's Estimate 30 EACH $390.00 $11,700.00
A0620 63301-0000 SIGN SYSTEM
Construction Solutions Group, LLC $1,020.00 $8,160.00 SMR Construction, Inc. $1,040.13 $8,321.04 McKenzie Construction and Site Development, LLC $638.00 $5,104.00 Engineer's Estimate 8 EACH $1,200.00 $9,600.00
A0630 63316-1000 REMOVE AND RESET SIGN
Construction Solutions Group, LLC $600.00 $1,200.00 SMR Construction, Inc. $924.56 $1,849.12 McKenzie Construction and Site Development, LLC $783.00 $1,566.00 Engineer's Estimate 2 EACH $600.00 $1,200.00
A0640 63401-1500 PAVEMENT MARKINGS, TYPE H, SOLID
Construction Solutions Group, LLC $1.68 $11,760.00 SMR Construction, Inc. $1.44 $10,080.00 McKenzie Construction and Site Development, LLC $4.35 $30,450.00 Engineer's Estimate 7,000 LNFT $1.00 $7,000.00
A0650 63403-0800 PAVEMENT MARKINGS, TYPE H
Construction Solutions Group, LLC $24.00 $5,040.00 SMR Construction, Inc. $2.89 $606.90 McKenzie Construction and Site Development, LLC $20.30 $4,263.00 Engineer's Estimate 210 SQFT $25.00 $5,250.00
A0660 63405-2890 PAVEMENT MARKINGS, TYPE H (SHARED LANE BICYCLE MARKING)
Construction Solutions Group, LLC $480.00 $12,480.00 SMR Construction, Inc. $433.39 $11,268.14 McKenzie Construction and Site Development, LLC $342.20 $8,897.20 Engineer's Estimate 26 EACH $665.00 $17,290.00
13 out of 13Source Selection Information - See FAR 2.101 & 3.104
Project No: TX FLAP 200(1)
Project Name: WIDENINING JONES STREET AND NORTH KEALY AVENUE AND
CONSTRUCTION OF ADJACENT TRAIL NEAR LEWISVILLE LAKE ENVIRONMENTAL
LEARNING AREA
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0670 63501-0000 TEMPORARY TRAFFIC CONTROL
Construction Solutions Group, LLC Lump Sum $270,000.00 SMR Construction, Inc. Lump Sum $36,173.51 McKenzie Construction and Site Development, LLC Lump Sum $290,000.38 Engineer's Estimate ALL LPSM Lump Sum $100,000.00
A0680 63701-0000 FIELD OFFICE
Construction Solutions Group, LLC $72,000.00 $72,000.00 SMR Construction, Inc. $16,815.48 $16,815.48 McKenzie Construction and Site Development, LLC $87,000.11 $87,000.11 Engineer's Estimate 1 EACH $30,000.00 $30,000.00
Total Schedule - All Items
Construction Solutions Group, LLC $6,323,236.00 SMR Construction, Inc. $7,315,915.94 McKenzie Construction and Site Development, LLC $11,894,131.12 Engineer's Estimate $6,965,000.00